Submits SBO Rule Final Response for EDG Reliability Program. Informs That EDG Reliability Program Upgrade Implemented by Technical Svcs Dept Sys Engineering Memo (JSEM-93-044) Approved on 930910
ML20059C454
Person / Time
Site: FitzPatrick Constellation icon.png
Issue date: 10/28/1993
From: Ralph Beedle
POWER AUTHORITY OF THE STATE OF NEW YORK (NEW YORK
To:
NRC OFFICE OF INFORMATION RESOURCES MANAGEMENT (IRM)
References
JAFP-93-077, JAFP-93-77, TAC-M68546, NUDOCS 9311010161
Download: ML20059C454 (2)


Text

. -

U3 Mairi Street Wh4e Plains. New York 10001 e

~'

a 914 (>816846 M NewYorkPower u m.......

4# Authority lll;; n r g ; " -

October 28,1993 JPN-93-077 U. S. Nuclear Regulatory Commission ATTN: Document Contrc,1 Desk Mail Station P1-137 Washington, D. C. 20555

Subject:

James A. FitzPatrick Nuclear Power Plant Docket No. 50 333 Station Blackout Rule (SBO)

Final Response for Emeraency Diesel Generator (EDG) Reliability Proaram

References:

1. NRC letter, R. A. Plasse to R. E. Beedle (TAC M68546) dated June 9,1992, " Supplemental Safety Evaluation of JAFNPP Response to the Station Blackout Rule."
2. NYPA letter, R. E. Beedle to NRC (JPN-93-025) dated April 1,1993

" Supplemental Response for Station Battery Capacity Calculations, SBO Procedure, EDG Reliability Program, and Modifications."

3. NYPA JAF Technical Services Report " Emergency Diesel Generator.

1 Reliability Program," JAF-RPT-EDG-01263 approved on July 30,1993.

Dear Sir:

The NRC found the Authority response to the station blackout (SBO) rule to be acceptable in Reference 1. The NRC staff requested notification upon completion of the program upgrades detailed in Authority responses to the SBO rule. The Authority provided completion information on the upgraded battery capacity calculations and SBO procedure in Reference 2.

The Authority also stated in Reference 2 that an EDG reliability program conforming to the guidance of NUMARC 87-00, and Regulatory Guide 1.155, would be implemented by September 30,1993. The EDG reliability program upgrade, (Reference 3) has been implemented by Technical Services Department i

Systems Engineering Memorandum (JSEM-93-044) approved on September 10,1993.

j If you have any questions, please contact Mr. J. A. Gray, Jr.

)

Very tru

urs,

/D

-e p

s

""'P" " 8*

  • d'*

010043 i t' l

9311010161 931028ADOCK 05000333 6[F PDR P

PDR.h

W cc: Regional Administrator U.S. Nuclear Regulatory Commission

~

475 Allendale Road King of Prussia, PA 19406 Office of the Resident inspector U.S. Nuclear Regulatory Commission P.O. Box 136 Lycoming, NY 13093 Mr. Brian C. McCabe Project Directorate 1-1 Division of Reactor Projects -l/Il U.S. Nuclear Regulatory Commission Mail Stop 14 B2 Washington, D.C. 20555 e