Forwards Insp Rept 50-341/93-21 on 931004-08.No Violation Noted
ML20059B073
Person / Time
Site: Fermi DTE Energy icon.png
Issue date: 10/21/1993
From: Gardner R
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III)
To: Gipson D
DETROIT EDISON CO.
Shared Package
ML20059B076 List:
References
NUDOCS 9310280023
Download: ML20059B073 (2)


See also: IR 05000341/1993021

Text

_-

,

q

p arcoq UNITED STATES

,e

[g '

jog NUCLEAR REGULATORY COMMISSION

REGION lll

., .n g

5  : .c 799 ROOSEVELT ROAD

o jf GLEN ELLYN, ILUNOIS 6o137-5927 2

%,

'"**

/

OCT 'J 1993

Docket No. 50-341

The Detroit Edison Company

ATTN: D. R. Gipson

Senior Vice President

Nuclear Generation

6400 North Dixie Highway

Newport, MI 48166

Subject: Station Blackout Inspection Report No. 50-341/93021(DRS)

Dear Mr. Gipson:

This refers to the special safety inspection conducted by Mr. Rolf A. Westberg

and others of this office on October 4-8, 1993. The inspection reviewed the

implementation of the Station Blackout (SBO) Rule,10 CFR 50.63, at the Fermi

2 Nuclear Power Station. At the conclusion of the inspection, the findings

were discussed with you and those members of your staff identified in the

enclosed report.

The team considered the SB0 Rule to be adequately implemented. The materiel

condition of the plant was good. In addition, the team noted that the plant's

self assessment of SB0 identified many of the same concerns as our team. The

team identified some minor weaknesses in the SB0 calculations but these

weaknesses did not change the overall results of the calculations.

The enclosed copy of our inspection report identifies areas examined during

the inspection. Within these areas, the inspection consisted of a selective

examination of procedures and representative records, observations, and

interviews with personnel.

No violations of NRC requirements were identified during the course of this

inspection.

l

270070

l

'b j

"*

9310280023 931021

PDR

ADOCK 05000341

G pyg ,'

uf .g_ g g

, . . . . . .-

_. 0 : r

_

-- i

-

-

OCT i : 1993 ~i

Detroit Edison Company 2

-

.;

1

1

In accordance with 10 CFR 2.790 of the Commission's regulations, a copy of- ';

this letter and the enclosed inspection report will be placed'in the NRC

-

Public Document Room. We will gladly discuss any questions-you have

concerning this inspection. ,

.:

'

Sincerely,

bwdh -  % dC

Ronald N. Gardner, Chief .

Plant Systems Section  !

Enclosures:

1. Inspection Report  ;

No. 50-341/93021(DRS) l

2. Appendix A - Persons Contacted  ;

Distribution  !

cc w/ enclosure:

John A. Tibai, Supervisor

of Compliance

P. A. Marquardt, Corporate i

Legal Department

OC/LFOCB

Resident insp.ector, RIII .j

James R. Padgett, Michigan Public j

Service Commission

Michigan Department of ~a'

Public Health

Monroe County Office of

Civil Preparedness

Fermi, LPM, NRR

R. Hasse, TSS