ML20059A922
| ML20059A922 | |
| Person / Time | |
|---|---|
| Issue date: | 12/14/1993 |
| From: | NRC OFFICE OF THE INSPECTOR GENERAL (OIG) |
| To: | |
| Shared Package | |
| ML20059A918 | List: |
| References | |
| OIG-93A-26, NUDOCS 9401030206 | |
| Download: ML20059A922 (18) | |
Text
.
J; OFFICE OF THE INSPECTOR GENERAL g-US NUCLEAR
.g REGULATORY COMMISSION l
1 INDEPENDENT REVIEW I-OF FINANCIAL AND ADMINISTRATIVE CONTROLS FOR WORK PERFORMED BY DEPARTMENT OF ENERGY LABORATORIES I
OIG/93A-26 December 14,1993 I
AUDIT REPORT l
4RREGg j
+
o
~,
5, L e 22 f 8
I H
g l
\\;%j i
300037 I
I Review of Controls for Work by DOE Labs l
REPORT SYNOPSIS g
The Office of the Inspector General (OIG) recently issued two audit reports addressing financial and administrative accountability for the U.S. Nuclear Regulatory Commission's (NRC) Office of Nuclear Regulatory Research l
(RES) work placed with the Department of Energy's (DOE) laboratories.
These reports identified serious management breakdowns in RES' oversight I
of projects placed with the DOE laboratories and identified eight areas for improvement.
g In the 1994 Energy and Water Development Appropriations Bill, the Committee on Appropriations expressed concerns about the RES financial management problems identified by OIG. The Committee requested that NRC perform an independent review to ensure that necessary corrective actions were taken by RES and to determine whether similar problems exist in other NRC offices. The Chairman, NRC, asked OIG to conduct this I
review.
g Our review focused on NRC work placed with the laboratories by RES, the Office of Nuclear Reactor Regulation (NRR), the Office for Analysis and Evaluation of Operational Data (AEOD), and the Office of Nuclear Material -
l Safety and Safeguards. These four offices accounted for the bulk of FY 1992 active projects and payments made to DOE.
We found that RES has taken necessary corrective actions to address the deficiencies cited in our previous audit reports. Our review also disclosed that other NRC offices had conditions similar to those identified in RES.
However, they have addressed the conditions and implemented appropriate corrective actions in most areas. As a result of our follow-up efforts, we made l
three recommendations to strengthen project management in NRR and AEOD.
I I
I ola/9u-26 p.ge a I
I
I Review of Controls for Work by DOE Labs l
TABLE OF CONTENTS I
REPORT SYNOPSIS...............................
i f
INTRODUCTION..................................
1 B ACKG ROUND.............................
1 I
FIND I NG S.......................................
3 The Office of Nuclear Regulatory Research Has Taken Necessary Corrective Actions to Address Its Deficiencies.....................
3 I
Similar Conditions Exist in Other NRC Program Offices; Corrective Actions are Underway.........
3 g
The Office of the Controller Has Taken Action j
on Prior Recommendations....................
6 CON CLU SION S..................................
6 RECOMMENDATIONS............................
7 AG ENCY COMMENTS............................
7 APPENDICES I
Objectives, Scope, and Methodology II Summary of the Eight Audit Issues 1
-l III Agency Comments on Draft Repon IV U.S. NRC Functional Organization Chart V
Major Contributors to this Report I
I
I Review of Controls for Work by DOE Labs l
INTRODUCTION g
The Office of the Inspector General (OIG) recently issued two audit reports 2
addressing the financial and administrative accountability by the U.S. Nuclear Regulatory Commission's (NRC) Office of Nuclear Regulatory Research l
(RES) for work placed with the Department of Energy's (DOE) laboratories.
These reports identified serious management breakdowns in RES' financid I
management oversight and identified eight areas for improvement: (1) project closing ard deobligation of funds, (2) accounting for NRC-funded property, (3) transfers of prior-year funds, (4) final laboratory performance evaluations, g
(5) tracking of project status, (6) review of project costs, (7) organization and retention of project files, and (8) training of key personnel. These reviews also found that the Office of the Controller (OC) did not have adequate l
controls over the review, approval, and verification of payments to DOE.
I In the 1994 Energy and Water Development Appropriations Bill, the Committee on Appropriations expressed concerns about the RES financial management problems identified by OIG. The Committee requested that l
NRC perform an independent review to ensure that RES implemented necessary corrective actions and to determine whether similar problems exist in other NRC offices. As a result, the Chairman, NRC, requested that OIG undertake this review to address the Committee's concerns.
I Appendix I details our audit objectives, scope, and methodology. Appendix II notes the eight problem areas that OIG identified in prior reports and addressed in this report.
BACKGROUND Since 1978, NRC has placed work with DOE's laboratories under a g
Memorandum of Understanding that includes guidelines for program
'OIG/92A-08, August 31,1992, Improvements Needed in NRC's Process for Anproving Payments to the Department of Enerev; and OIG/92A-20, March 5,1993, Improvements I
Needed in Financial and Administrative Accountability for Office of Nuclear Regulatory i
Research Funded Work at Department of Enerev Laboratories onor m -m r.se 1 I
I
o-3 Il se Review of Controls for Work by DOE Labs planning, implementation, control, and funding of interagency research programs and related activities. NRC's Management Directives (MDs) 11.7 and 11.8 provide specific procedures regarding work placed with the g<
laboratories.
On December 3,1992, following criticism of NRC's project management l-practices by OIG and NRC's own review groups, the Executive Director for Operations (EDO) delegated oversight authority to the - Office of g
Administration (ADM) for the contract management of NRC projects at DOE 5
laboratories. The EDO also released the draft of a new management directive, which consolidated and updated MDs 11.7 and 11.8, and directed ADM ta initiate a 6-month pilot study at RES that'would serve as a practical basis for using the draft management directive. The EDO's goal was to develop and implement an agency-wide standard for DOE work.
l ADM completed its pilot study at RES on July 30, 1993. Following its g
consideration of various NRC offices' comments, ADM plans to forward the 5
revised draft management directive to the EDO for approval.
In fiscal year (FY) 1992, NRC had 666 active projects at DOE laboratories, with payments totaling about $115 million. Our review focused on NRC work placed with the laboratories by RES, the Office of Nuclear Reactor l
Regulation (NRR), the Office of Nuclear Material Safety and Safeguards (NMSS), and the Office for Analysis and Evaluation of Operational Data g
(AEOD). These four NRC offices accounted for 91 percent of the active 5
projects and 97 percent of the payments made to DOE in FY 1992.
Project managers in each NRC office are responsible for controlling work placed with DOE laboratories.
Technical monitors assist the project E
managers in NRR, NMSS, and AEOD. Each office has developed internal 3
procedures for managing DOE projects.
I I
I g
I Review of Controls for Work by DOE Labs l
FINDINGS g
RES has taken corrective actions to address the deficiencies cited in our previous audit reports. Although other NRC offices had conditions similar to those identified in RES, they corrected most problem areas prior to this l
review.
TIIE OFFICE OF NUCLEAR REGULATORY RESEARCII HAS TAKEN NECESSARY CORRECTIVE ACTIONS TO ADDRESS ITS DEFICIENCIES I
RES has implemented corrective actL,ns for the eight audit deficiencies I
identified in our two previous audit reports. Additional effort, however, is needed to complete corrective actions for closing projects and deobligating funds an? for developing a system to track project status.
Using a January 1992 project listing, RES identified 1,147 DOE projects that l
were completed, but not yet closed. RES' goal was to close these projects and deobligate $1.5 million by February 1994. As of July 1993, RES had closed 101 projects and deobligated over $380,000.
RES is currently developing the Research Information Management System I
(RIMS) for the purpose of unifying its project and financial management systems. RIMS will possess the capability to track milestones and to monitor the status of all project closecut actions. Therefore, we believe that RIMS l
will eventually be an important management tool for helping to ensure timely project closures. The scheduled completion date for RIMS is May 1994.
I SIMilAR CONDrrIONS EXIST IN OTIIER NRC PROGRAM OFFICES; CORRECrlVE ACTIONS ARE UNDERWAY The Office of Nuclear Reactor Regulation NRR initiated an internal review in August 1992 to identify any problems in its project management process. The NRR review team found many problem
"~ ~
~
I I
I Review of Controls for Work by DOE Labs areas and made 34 recomme,dations to NRR management for improving project management for work placed with the laboratories and commercial contract work. We considered the recommendations to be appropriate and g
found that many of them addressed problems similar to those identified at RES. However, the report did not fully address training, nor did it cover tracking of project status.
(
NRR Training Most of NRR's project management staff have not received required formal training. For example,176 employees (including 112 technical monitors) of the total 208 involved with DOE projects have not taken either of the Offlee of Personnel's (OP) courses, " Acquisition for Project Managers," or
" Acquisition for Supervisors and Managers," as required by NRR office l
procedures. Although NRR's internal report recognized this lack of formal training as a problem area, it did not fully address the problem in its recommendations.
2 NRR requested that ADM " consider flexibility in the training requirements for technical monitors" and suggested "a new shorter duration course that would focus on the more limited needs of a technical monitor." ADM recently informed OIG that it was considering revisions to current OP training l
requirements. However, until the revisions are complete, ADM believes that NRR should schedule training for those employees who have not received the g'
required formal training in project management. We agree with ADM's 5
position, especially in view of conditions noted in NRR's own internal review and conditions previously reported by OIG at RES.
g NRR Tracking of Project Status I
Our review of NRR's system to track project status identified 8 of 10 sampled t
projects that were categorized as " active," but were actually complete. We g
believe that NRR should include performance periods on status reports 5
distributed to project managers and their supervisors. This would allow NRR to more quickly identify completed projects and ensure their timely closure.
l 2
Specifically, ADM's Division of Contracts and Property Management olarnA-26 rap 4
- 5.
Review of Controls for Work by DOE Labs According to one NRR project manager, previous status reports contained performance periods that highlighted expiring projects that would soon need to be closed out. NRR personnel could not explain why this practice was I
abandoned in FY 1992; we believe it should be reinstated.
I The Office of Nuclear Material Safety and Safeguards l
NMSS was performing project management adequately in all but one area.-
Specifically, NMSS was not annually reconciling and disposing of all property remaining from completed projects. We believe the primary reason for this I
breakdown was that the Division of Contracts and Property Management (DCPM) had not distributed annual DOE inventory lists to the program g
offices ~ as we previously reported.
DCPM has started distributing the inventory lists to NMSS, and NMSS has begun to reconcile its portion of the inventory.
The Office for Analysis and Evaluation of Opemtional Data AEOD officials stated that they examined controls over DOE laboratory work g
after reviewing a draft management directive on placing work with DOE laboratories and our audit reports on RES. AEOD identified five problem areas that were similar to those found at RES.
1 We found that AEOD has taken corrective actions in all areas except tracking I
of project status. AEOD lacks a process or system to identify active projects and their performance periods. We believe that this impedes AEOD's ability to initiate timely closecut actions on completed projects. For those projects l
that AEOD has identified as complete and is currently closing, we found that almost half have been expired for over 2 years.
~ l As part of its financial management process, AEOD prepares quarterly funding reports that track the financial status of the projects it administers.
I We believe these reports should include performance periods for each project.
This would aid project managers in identifying completed projects that should be closed.
,I
{
osarnh-u ray 5 I
I Review of Controls for Work by DOE Labs THE OFFICE OF TIIE CONTROLLER HAS TAKEN ACTION ON PRIOR RECOMMENDATIONS We previously recommended that OC, prior to final posting to NRC's accounting system, verify completion of the review and approval process for payments made to DOE. NRC disagreed with our recommendation and
.l sought guidance from the General Accounting Office (GAO).
GAO responded by suggesting alternative controls related.to NRC payments to g
DOE.
B OC has adopted the GAO suggestions except for implementing yearend cutoff g
procedures for identifying those payments to DOE that project managers did not verify as received and accepted.
In an OIG meeting with OC representatives, the Controller said that there is a need to identify the payments. Subsequently, GAO provided additional guidance to NRC. GAO granted relief from recording a yearend adjusting entry if the balance of E
unverified payments to DOE is immaterial and if there would be a short 5
period of time after yearend before the payments were verified and bills returned to OC. NRC officials believed that this condition would exist at l
yearend and not require an adjustment. OIG will reevaluate this matter during our upcoming audit of the agency's FY 1993 financial statements.
CONCLUSIONS g
RES management has taken decisive and appropriate actions to address the g
financial management deficiencies cited in our previous audit reports..We 3
also found that other NRC offices have addressed financial management problems in their project management processes and have implemented appropriate corrective actions in most areas. However, to preclude recurring problems, NRC management must sustain its financial management initiatives.
We are making three reconunendations based on our follow-up efforts.
l I:
I, g
y
I.
l Review of Controls for Work by DOE Labs l
RECOMMENDATIONS We recommend that the Director, NRR:
1.
Ensure that all key personnel, including technical monitors, receive formal training in project management; and 2.
Improve reports issued to project managers and their I
supervisors by including each project's performance period.
j We recommend that the Director, AEOD:
3.
Revise the office's quarterly financial reports to include performance periods for all DOE projects, thereby giving project managers added visibility concerning those projects that should be targeted for closure.
AGENCY COMMENTS I
On November 26,1993, the Deputy Executive Director for Nuclear Reactor Regulation, Regional Operations and Research (DEDO) responded to our draft report and agreed with the three recommendations contained therein.
l He also suggested clarifying language for one section of the report, and we have made changes where we believed appropriate. Appendix III contains a copy (without enclosures) of the DEDO's comments.
I I
.I I
.I onopa-26 c., 7 I
I
I I
Appendbc I Review of Controls for Work by DOE Labs OBJECTIVES, SCOPE, AND METHODOLOGY The Office of the Inspector General recently issued two audit reports addressing financial and administrative accountability for the U.S. Nuclear ig Regulatory Commission's (NRC) Office of Nuclear Regulatory Research (RES) work placed with the Department of Energy's (DOE) laboratories. In those reports, we focused on the closeout process, showed serious l
management breakdowns in RES' oversight of projects with DOE, and identified eight areas for improvement (see Appendix II for details of the I-eight areas). We also found that the Office of the Controller (OC) did not have adequate controls over the review, approval, and verification of payments to DOE.
I Because of our reports, the Committee on Appropriations expressed concerns in the 1994 Energy and Water Development Appropriations Bill about RES' financial management problems. The Committee requested that NRC ensure that RES implemented necessmy corrective actions and determine whether
!g similar problems exist in other NRC offices. The objective of this review was 5
to address the Committee's concerns.
'l We held interviews and discussions with NRC management and administrative staff from RES, OC, the Office of Nuclear Reactor Regulation, the Office of Nuclear Material Safety and Safeguards, the Office for Analysis and I.
Evaluation of Operational Data, and the Office of Administration. Our review included an examination of selected project files, supporting financial I
mformation, and training records for personnel involved with DOE project management activities.
i
- l We conducted our review at NRC Headquarters in July and August 1993, according to generally accepted Government auditing standards.
.j i
I I
II
Ea Appendbc il Review of Controls for Work by DOE L. abs
SUMMARY
OF THE EIGHT AUDIT ISSUES 1.
Project Closing and Deobligation of Funds According to agency guidance, projects with the Department of Energy l
(DOE) should be closed promptly after completion and all uncosted funds should be deobligated. At the Office of Nuclear Regulatory E
Research (RES), projects were not being closed after completion. At 5
least $1.4 million was available for other agency use.
2.
Accounting for NRC-Funded Property Agency guidance provides specific requirements regarding the responsibilities of the U.S. Nuclear Regulatory Commission (NRC),
DOE, and the laboratories for the proposal, authorization and E
purchase, receipt, inventory control, and disposal of NRC-funded 5
property and equipment.
At RES, project managers were not following agency guidance for tracking and disposing of property and g
equipment acquired under DOE projects.
3.
Transfers of Prior-Year Funds Agency guidance on authorizing financial flexibility does not allow I
authorized funds to be transferred between projects after the end of 5
the fiscal year without the prior approval of the Controller. From FY 1989 to June 1992, RES transferred $23 million of prior-year funds l
without the required approval of the Controller.
4.
Final Laboratory Performance Evaluations Agency guidance on closing DOE projects requires project managers to evaluate and document the laboratory's performance to include the technical, schedule, and cost aspects of the project. Since RES was not closing projects, it also was not conducting final laboratory performance evaluations.
I oiapw26 r,1 or 2 J
B
I Appendix il Review of Controls for Work by DOE Labs I
5.
Tracking of Project Status RES did not use available management tools for tracking project status. Of particular interest to us was system information that could I
be used for the early identification of completed projects for closeout purposes. RES developed a comprehensive RES system several years ago to provide cost, schedule, and performance information on
(
individual projects, but this system was not routinely used by project managers. As of October -1992, RES could not account for the completion status of 1,400 projects begun since FY 1975.
.I' 6.
Review of Project Costs Agency guidance requires the project manager to recommend approval or disapproval of cost vouchers. There was no evidence that RES'
-l project managers had reviewed DOE cost vouchers since at least 1986.
Most project managers we interviewed could not initially support costs to date with information from their project files.
7.
Organization and Retention of Project Files Agency guidance provides specific instructions for maintaining administrative documents and records for work placed with DOE. The
.l guidance outlines project file sections, section contents, and individual responsibilities. At RES, many project files were missing, many files lacked'significant portions of the required contents, and most of the I
files in our sample were disorganized.
8.
Training of Key Personnel Agency guidance requires NRC office directors to ensure that project
. l !-
managers are trained properly to perform project management duties.
At RES, not all project managers and their supervisors (including I.
senior managers) had taken required formal training. Many project managers who had been trained still did not properly follow agency procedures.
I Olo/93A-26 Page 2 of 2 I
I
Appendix ill Review of Controls for Work by DOE Labs i
AGENCY COMMENTS
/
UNITED STATES
[
j NUCLEAR REGULATORY COMMISSION 2
WA&mOToN. o.c. ausHmM November 26. 1993 8
MEMORANDUM FOR:
Thomas J. Barchi Assistant Inspector General for Audits I
FROM:
James H. Sniezek, Deputy Executive Director for Nuclear Reactor Regulation, Regional Operations and Research I
SUBJECT:
DRAFT REPORT - INDEPENDENT REVIEW 0F FINANCIAL AND ADMINISTRATIVE CONTROLS FOR WORK PERFORMED BY DEPARTMENT OF ENERGY LABORATORIES I have reviewed the subject report, forwarded by your memorandum of October 19, 1993, and agree with the basic findings and recommendations. For accuracy, I an enclosing a markup of page 4 of the report that recognizes the I
beneficial effects of draft M.D.11.7 in late 1992 on recognition and correction of the areas related to O!G review of RES DOE laboratory work.
The following actions are being taken in response to the recomendations I
contained in the report.
RECOMMENDATION (1) (NRR)
Ensure that all key personnel, including technical monitors, receive formal I
training in project management.
RESPONSE (1)
I NRR has initiated an effort to ensure that all key personnel attend either the
' Acquisition for Project Managers' course or the " Acquisition for Supervisors and Managers' course sponsored by the Office of Personnel by May,1995. It should be noted that potentially in excess of 200 individuals in NRR will I
require this training. In light of the current course size and frequency (approximately quarterly), NRR has estimated a schedule of approximately eighteen months to complete the training of key personnel. If the demand warrants, NRA plans to work with the Office of Personnel to schedule additional courses to expedite training of key NRR Personnel.
RECOMMENDATION (2) (NRR)
Improve reports issued to project managers and their supervisors by including I
each project's performance period.
RESPONSE (2)
. I NRR wiii modify its financiai tracking system to inciede each 00E project,
IN period of performance by June 30, 1994.
olG/93A46 rage 1 or2 I
I
Ee Append!x ill-Redew of Controls for Work by DOE Labs
~
Thomas J. Barchi RECOMEEATION (31 (AE001 Revise the office's quarterly financial reports to include performance periods for all DOE projects, thereby giving project managers added visibility concerning those projects that should be targeted for closure.
RESPONSE (31 AEOD will modify the office's monthly financial reports to include performance periods for all DOE projects by February 1, 1994 and has instituted a revised g
priority for close-out of completed projects.
g In addition to the specific recormendations cited above, page 3 of the report refers to the internal review initiated by NRR in August 1992 and the 34 recone.endations resulting from that review. Attached for your information is NRR's response to each of the 34 recommendations.
I appreciate the opportunity to review this report prior to its publication.
, s n us h, H
sH.Sniezek,DeputyENeutiveDirector E'
forNuclearReactorRegulation, g
R4gional Operations and Research
Enclosures:
3,
- 1. Markup of page 4 g
- 2. Response to internal review recommendations I
I I
I I
I g
I.
'll i
'l Apperdbc N
.. m Tieview of Controls for Work by DOE Labs U.S. NRC FUNCTIONAL ORGANIZATION CHART
.I NRC
'I Commissioners I
Executive Director for Operations e- -
~$
~
d
.2% =9:-
Fi=s.t.
~'
~
g g
g
,=:i i
i i
i
..=
..a g s-
= :-
l
,&'iC+-
=~
I N-aE -
J=""=-
w~a.
I a.,s a omm I
- -l, L~
- ,rJ a-
~~
I Areas Aedhed I
~,,,
I
~
Appendix V Review of Controls for Work by DOE Labs I
MAJOR CONTRIBUTORS TO THIS REPORT William Glenn, Team Ixader l
RussellIrish, Senior Auditor Doris Martin, Contract Auditor George Pourchot, Contract Auditor I
I I
I I
I I
I I
~,,,
I