Advises of Rev to Commitment Made in WCNOC Response to NRC GL 83-28, Required Actions Based on Generic Implications of Salem ATWS Events
ML20058Q347
Person / Time
Site: Wolf Creek Wolf Creek Nuclear Operating Corporation icon.png
Issue date: 12/20/1993
From: Carns N
WOLF CREEK NUCLEAR OPERATING CORP.
To:
NRC OFFICE OF INFORMATION RESOURCES MANAGEMENT (IRM)
References
GL-83-28, WM-93-0173, WM-93-173, NUDOCS 9312280199
Download: ML20058Q347 (2)


Text

= _..

r 7

t 4

WipLF CREEK

~

NUCLEAR OPERATING CORPORATION Ned S "Ba# Carns December 20, 1993.

Presedent and cniet Exeamve officer WM 93-0173 I

U. S. Nuclear Regulatory Commission ATTN: Document Control Detk Mail Station P1-137 Washington, D.

C.

20555

Reference:

Letter KMLNRC 66-231, dated December 10, 1986, from G.

L.

Koester,-KG&E, to H.

R. Denton, NRC

Subject:

Docket No. 50-482:

Revision to NRC Commitment Made l

in WCNOC's Response to NRC Generic Letter 83-28

+

Gentlemen:

i The purpose of ~ this letter is to advise the NRC of a revision to.a commitment made in the Reference.

The Reference ~ submitted a report in response to Generic Letter B3-28,

" Required Actions Based on Generic Implications of Salem ATWS Events," describing the vendor interface program which was implemented at Wolf Creek Generating Station (WCGS).

Specifically, the Reference stated.

" Vendor manuals at WCGS are considered design documents.

Design.

changes to vendor manuals are generated' as part of the Plant Modification Request (PMR) process.

When a vendor manual change i

associated with a design change is received at WCGS, the. document l

is forwarded to the Engineering group where it undergoes-a technical adequacy review.

If it is determined that the vendor manual change should be incorporated. into the manual, the change is accomplished via the PMR process, j

During the preliminary stages of PMR development, the PMR is' forwarded to Operations,. Maintenance, I&C, Training,- and Results l

Engineering.

Each of these groups is responsible for identifying i

individual documents (i.e.,

Surveillance Procedure, Operating Procedure, Maintenance Procedure, etc.)

requiring changes 'and whether or not training is required.

Upon approval for implementation, the PMR is transmitted.back.to the affected groups for implementation of document changes.

The ' organization l

responsible' for implementing the PMR will. also verify the completeness of this process."

l I

The description of the vendor interface program as established in the Reference has been revised to state:

9312280199 931220 PDR ADOCK 05000482 f!

P PDR Su RO. Box 411/ Burhngton. KS 66839 / Ptone: (316) 3648831 g p An Eaunt OpportonHy Employer fA>F!HC/ VET

t WM 93-0173 Page 2 of 2

" Vendor manuals at WCGS are controlled documents.

Changes to vendor manuals are generated as part of the Permanent Modification and Configuration Control process.

When a vendor manual change associated with a design change is received at WCGS, the document is forwarded to the Engineering group where it undergoes a technical adequacy. review.

If it is determined that the vendor-manual change should be incorporated into the manual, the change is acconplished per the above process.

During the above process the vendor manual change is forwarded to the appropriate groups for review.

Each group is responsible for updating individual documents (i.e.,

Surveillance Procedure, Operating Procedure, Maintenance Procedure, etc.). requiring.

changes and identifying whether or not training is required."

The design process continues to meet the criteria of 10 CFR 50, Appendix B,

" Design Control," because the cognizant organization will review the l

change prior to issuance to ensure the design basis / function of the' system or component is maintained.

If this review determines that the design / function has been affected, the change will be processed as a design change, revised so as not to affect the design / function, or-canceled.

If you have any questions concerning this matter, please contact me at (316) 364-8831, extension 4000, or Mr. Kevin J. Moles at extension 4565.

Very truly yours, Q

%=

Neil S. Carns President and Chief Executive Officer

.NSC/jra cc:

J. L. Milhoan (NRC)

G.

A. Pick (NRC)

W.

D. Reckley (NRC)

L. A. Yandell (NRC)

I 1