Notice of Violation from Insp in May & Sept 1992.Violation Noted:Identified Logs as Being Incomplete & Inaccurate
ML20058P030
Person / Time
Site: Vermont Yankee File:NorthStar Vermont Yankee icon.png
Issue date: 10/15/1993
From:
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION I)
To:
Shared Package
ML20058P029 List:
References
NUDOCS 9310220002
Download: ML20058P030 (1)


Text

_ ._.

s ENCLOSURE NOTICE OF VIOLATION Vermont Yankee Nuclear Power Corporation Docket No. 50-271 Vermont Yankee Nuclear Power Station License No. DPR-28 During NRC inspections conducted in May and September, 1992, violations. of NRC requirements were identified. In accordance with " General Statement of Policy and Procedures for NRC Enforcement Actions," 10 CFR Part 2, Appendix C, the violations are listed below:

10 CFR 50.9, completeness and accuracy of information, requires, in part, that information required by statute or by Commission regulations, orders, or license conditions to be maintained by the licensee shall be complete and accurate in all material respects.

Contrary to the above, the licensee determined that records required to be maintained by .

Commission regulations or license conditions were not complete and accurate in all material repects. Specifically, during the periods of May and June,1992, one licensed and two non-licensed auxiliary operator round logs were identified as being incomplete or inaccurate. These errors were material in that they evidenced that checks had been made when they had not.

Datedgt King of Prussia, Pennsylvania thisifAday of October 1993 OFFICIAL RECORD COPY a:VYFALSE.NOV 9310220002 931015 PDR ADOCK 05000271 0 PDR sb ,