r h

J a

MSIP NORTHERN STATES POWER COMPANY l

M I N N E A PO L_l s. M t N N E s O*r A 55401 September 23, 1975 Mr. J. C. Keppler Director - Region III Office of Inspection and Enforcement United States Suclear Regulatory Commission 799 Roosevelt Road Glen Ellyn, Illinois 60137

Dear Mr. Keppler:

MONTICELLO LTCLE/J1 GENERATING TLAhT Docket No. 50-263 License No. DPR-22 5

In compliance with your request outlined in IE Bulletin 7A-04A, this monthly surr.ary report is submitted. All items scheduled for completion by September 1, 1975, as discussed in our response to IE Bulletin 75-04A (reference letter f rom L. J. Uachter to J. G. Keppler, dated June 27, 1975) have been completed.

In addition, review of fire detector sensor and fire hose station locations to verify adequate coverage of all areas where occurrence of fire would have high safety significance was completed on August 29, 1975. All remaining ite7.s are still expected to be cor:pleted as scheduled.

Yours very truly, O

L.

. Wachter Vice President - Power Production and System Operation ec:

Mr. R. S. Boyd Mr. G. Charnoff Minnesota Pollution Control Agency Attention:

Mr. J. W. Fernan 9104240495 750923 CF ADDCK 05000263 CF

.