Text
l 001 2 8 1993
\\
l i
l Docket No. 50-339 License No. NPT-7 Virginia Electric and Power Company l
ATTN: Mr. W. L. Stewart l
Senior Vice President - Nuclear 5000 Dominion Boulevard Glen Allen, VA 23060 Gentlemen:
)
SUBJECT:
CONFIRMATION OF MEETING ARRANGEMENTS - NORTH ANNA UNIT 2 This confirms the arrangements made between Mr. M. Bowling of Virginia Electric and Power Company and Mr. M. Branch of my staff on October 26, 1993, concerning an Enforcement Conference to be conducted at the Nuclear Regulatory Commission's Renion 11 office in Atlanta on November 10, 1993, at 10:00 a.m.
The purpose of the conference is to discuss the circumstances associated with the High Head Safety Injection subsystem flow rate being less than the Technical Specification required flow rate when measured on October 14, 1993. Since this occurrence is similar to two previous ones, you should be prepared to discuss effectiveness of your corrective actions. A proposed agenda is included as an enclosure.
Should you have any questions regarding these arrangements, we will be pleased to discuss them.
Sincerely,
/s Ellis W. Merschoff, Director Division of Reactor Projects
Enclosure:
Meeting Agenda cc w/ encl:
M. L. Bowling, Jr., Manager Nuclear Licensing Virginia Electric & Power Company 5000 Dominion Boulevard Glen Allen, VA 23060 G. E. Kane, Station Manager North Anna Power Station P. O. Box 402 Mineral, VA 23117 cc w/ encl cont'd:
(See page 2)
I 13n!'l J
9312140237 931028
/
PDR ADOCK 05000339 I
O PDR
\\
Vircinia Electric & Power Company 2
OCT 2 8 lgg3 cc w/ encl cont'd:
Executive Vice President Old Dominion Electric Cooperative 4201 Dominion Boulevard Glen Allen, VA 23060 Dr. W. T. Lough Virginia Corporation Commission Division of Energy Regulation P. O. Box 1197 Richmond, VA 23209 William C. Porter, Jr.
County Administrator Louisa County P. O. Box 160 Louisa, VA 23093 Michael W. Maupin, Esq.
Hunton and Williams 9S1 E. Byrd Street Richmond, VA 23219 Attorney General Supreme Court Building 101 North 8th Street Richmond, VA 23219 Robert B. Strobe, M.D., M.P.H.
State Health Commissioner P. O. Box 2448 Richmond, VA 23218 bec w/ enc 1:
G. Belisle, RIl L. Garner, RII L. Engle, NRR Document Control Desk NRC Resident Inspector Route 2, Box 78-A Mineral, VA 23117 hil:DRP RII:DRP RII:DRP RII:DRS R11:DRSS RII:0RA LGarner GBelisle MSinkule AGibson JStohr LReyes 10/ 93 10/ /93 10/ /93 10/ /93 10/ 93 10/ /93 Rll:EICS Ell:0GC GJenkins CEvans 10/ /93 10/ 93
- SEE PREVIOUS CONCURRENCE' CONCURRENCE PAGE FOR SIGNATURES.
I Lti t o LcG3 Virginia Electric & Power Company 2
cc w/ encl cont'd:
i Ray D. Peace, Chairman Surry County Board of Supervisors P. O. Box 130 Dendron, VA 23839 Dr. W. 1. Lough Virginia State Corporation Commission l
Division of Energy Regulation P. O. Box 1197 i
Richmond, VA 23209 Michael W. Maupin Hunton and Williams Riverfront Plaza, East Tower 951 E. Byrd Street Richmond, VA 23219 i
Robert B. Strobe, M.D., M.P.H.
State Health Commissioner l
Virginia Department of Health r
P. O. Box 2448 Richmond, VA 23218 l
Attorney General Supreme Court Building 101 North 8th Street Richmond, VA 23219 i
bcc w/ encl:
G. Belisle, RI!
L. Garner, RIl B. Buckley, NRR Document Control Desk i
NRC Resident Inspector Route 1, Box 166 Surry,.VA 23883 NRC Resident Inspector Route 2, Box 78-A l
Mineral, VA 23117 l
RII:DRP RI.:
P R
DRP RII:JR RII:DRJS RII:0 l
f
},
1/ ')
LGarner GBel MSi e AGi on JSt r LR es 10A793 10/g)/93 10/1?/93 10/p/93 10 93
/-
93
/
RJ
,S RII:0GC G enk ns CEv'a s 10/p/93 10/g!93
4 y
t i
a i
ENCLOSURE l
PROPOSED ENFORCEMENT CONFERENCE AGENDA U. S. NUCLEAR REGULATORY COMMISSION AND j
VIRGINIA ELECTRIC AND POWER CO.
NOVEMBER 10, 1993 l
e I.
Introductions and opening remarks L. Reyes, Deputy Regional Administrator t
II.
Discussion of the Enforcement Policy G. Jenkins, Director l
Enforcement and Investigation Coordination Staff 111.
Overview - L. Reyes IV.
Apparent Violation and NRC concerns E. Merschoff, Director Division of Reactor Projects V.
Licensee Presentation J. O'Hanlon, Vice President - :iuclear Operations ISSUES ASSOCIATED WITH FAILURE TO MEET TECHNICAL SPECIFICATION HIGH HEAD SAFETY INJECTION SUBSYSTEM FLOW REQUIREMENT AND FAILURE TO PRECLUDE RECURRENCE A.
Description of the circumstances which lead to the High Head Safety Injection suosystem not meeting the Technical Specification required minimum flow rate and previous similar events.
B.
Safety consequences and significance of' having less than the Technical Specification required High Head Safety Injection subsystem flow rate available.
1 C.
Root cause of the event.
D.
Corrective actions to prevent recurrence.
VI.
NRC followup questions VII.
Closing - L. Reyes