i, 000KETED UNITED STATES OF AMERICA L'SE NUCLEAR REGULATORY COMMISSION 82 ED -6 P1 :46 ATOMIC SAFETY AND LICENSING BOARD Before Administrative Judges cer;cy cF Secs t s Marshall E. Miller, Chairman DOCXEllhG & SEPd Kenneth A. McCollom WCH Richard F. Cole SERVED AUG G1982
)
In the Matter of
)
Docket Nos. 50-445
)
50-446 TEXAS UTILITIES GENERATING COMPANY, et al.
)
)
(Application for (Comanche Peak Steam Electric Station,
)
Operating License)
Units 1 and 2)
)
)
August 6, 1982 SCHEDULING ORDER The following is the schedule for the remaining hearings on Contention 5 and the commencement of hearings on Contention 22:
August 23, 1982 Discovery completed. All responses filed.
Motions for summary disposition filed.
August 30, 1982 Responses to motions for summary disposition filed.
September 3, 1982 Prefiled written testimony in the hands of the Board and the parties.
September 13, 1982 Hearing commences.
Location and starting time to be announced later.
The scheduled hearing will encompass all remaining matters on Contenticn 5 and all matters on Contention 22 unless the Staff advises the Board and prties that it will not be prepared to proceed on particular subparts of Contention 22.
8208090148 820906 PDR ADOCK 05000445 G
a
. The dates given above are the dates by which materials are to be filed by being placed in the mail for overnight delivery with the exception of the date for filing testimony.
As noted above, the testimony must be in the hands of the Board and parties on September 3.
This may be accomplished by hand delivery or by overnight delivery to arrive on that date.
Discovery on Contention 22 may commence immediately. To facilitate meeting the schedule, the time for responses to motions for production of documents is shortened to fourteen (14) days.
Discovery on Contention 5 is closed except for possible depositions of rebuttal witnesses. The opportunity renains for appropriate motions, pursuant to 10 CFR 2.740(b), concerning other discovery on Contention 5.
It is so ORDERED.
FOR THE ATOMIC SAFETY AND LICENSING BOARD WL4/hAA "t-Marsha l
- i. Miller, Chairman-~
~
ADMINISTRATIVE JUDGE August 6, 1982