Advises That Tech Spec Change Request Re NUREG-0737,Items II.E.1.1 & II.E.1.2 Concerning Auxiliary Feedwater Sys Will Be Submitted by 820915.Delay Due to Organizational Changes,Workload & Unit 2 Outage
ML20058G185
Person / Time
Site: Prairie Island  
Issue date: 07/28/1982
From: Musolf D
NORTHERN STATES POWER CO.
To:
Office of Nuclear Reactor Regulation
References
RTR-NUREG-0737, RTR-NUREG-737, TASK-2.E.1.1, TASK-2.E.1.2, TASK-TM NUDOCS 8208030228
Download: ML20058G185 (1)


Text

l Northern States Power Company 414 Nicollet Mall Minneapohs. Minnesota 55401 Telephone (612) 330-5500 July 28, 1982 Director Office of Nuclear Reactor Regulation U S Nuclear Regulatory Commission Washington, DC 20555 PRAIRIE ISLAND NUCLEAR GENERATING PLANT Docket Nos. 50-282 License Nos. DPR-42 50-306 DPR-60 NUREG-0737, Items II.E.1.1 and II.E.1.2, Safety Evaluation Report, Requirements for Auxiliary Feedwater Systems The NRC Safety Evaluation Report dated March 22, 1982, for NUREG-0737, Items II.E.1.1 and II.E.1.2, contained a requirement to submit a Technical Speci-fication change request covering administrative control for the condensate storage tank supply valves to the auxiliary feedwater pumps. The change was to be submitted 90 days af ter receiving the Safety Evaluation Report.

Due to organizational changes, work load, and the Unit 2 outage we were unable to submit the Technical Specification change request as originally scheduled.

The Technical Specification change is in the process of being draf ted and will be submitted by September 15, 1982. We apologize for this delay.

Please contact us if you have any questions concerning our schedule for completing this requirement.

Ow David Musolf Acting Head-Nuclear Supp t Services DMM/SAF/bd cc:

Regional Administrator-III, NRC NRC Resident Inspector NRR Project Manager, NRC oy4 G Charnoff 8206030228 B20728 PDR ADocg Opoooggy P