) Comm:nw:alth Edison LaSalle County Nuclear Station ep.
Rural Route #1, Box 220
_V Marseilles,lilinois 61341
- Telephone 815/357-6761
{
l July 14, 1982 Mr. James G. Keppler Regional Administrator Director of Regulatory Operations - Region 111 U. S. Nuclear Regulatory Commission 799 Roosevelt Road Glen Ellyn, Illinois 60137
Dear Sir:
In accordance with LaSalle County Station Unit 1 Facility Operating License NPF-11, Appendix B, Section 3.', we are submitting to you a a
copy of the NPDES noncompliances for LaSalle County Nuclear Generating Station Permit No. ILOO48151.
.$13 R. H. Holyoak Superintendent LaSalle County Station RHH/CLN/djp Enclosure cc: DVR Report 8207260404 820714 JIJL 1 9 kw PDR ADOCK 05000373
_ _ - _ _ _ - - - - - - - - - _ _ - - - - - - -G[g S
u M
LASALLE COUh W NUCLEAR GENERATING STATION N.P.D.E.S. PETWlT'NOKILOO48151 NONCOMPLIANCE REPORT ' ' '
~.
~ ~..
DISCHARG5 NUMBER AND DESCRIPTION:
001c - Low Volume Wastes Regen. Wastes Soln. Discharge Tank PARAMETER AND PERMIT LIMIT:
Tota 1 Iron - 15 mg/l NONCOMPLIANCE, DATE, AND DURATION:
2.4 mg/1, 15 JUNE 82, 2t hours CAUSE OF NONCOMPLIANCE:
The hydrogen peroxide system was found to be air bound on the day in question.
No solution had been injected into the raw well water, i
CORRECTIVE ACTION:
A permanent hydrogen peroxide system is to be installed as soon as equipment can be obtained.
This system should relieve problems with the operation of the temporary system.
DATE RECOGNIZED AS,A VIOLATION:
28 JUNE 82 DATE INVESTIGATED:
\\
-..