Forwards Insp Repts 50-245/93-19,50-336/93-14 & 50-423/93-15 on 930630-0817.No Violations Noted
ML20057F463
Person / Time
Site: Millstone  Dominion icon.png
Issue date: 10/06/1993
From: Blough A
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION I)
To: Opeka J
NORTHEAST NUCLEAR ENERGY CO.
Shared Package
ML20057F464 List:
References
NUDOCS 9310180034
Download: ML20057F463 (4)


See also: IR 05000245/1993019

Text

_ . - _ _ - _ - - _ - _ _ - _ _ _ - _ - - _ _ _ _ _ _ _ _ _ _ _ _ _

ng~

s

(Q '>

.

I

October 6,1993

l

Docket Nos. 50-245

50-336

50-423

Mr. John F. Opeka

Executive Vice President - Nuclear

.

Northeast Nuclear Energy Company

P.O. Box 270

Hartford, Connecticut 06141-0270

i

Dear Mr. Opeka:

SUBJECT:

MILLSTONE COMBINED INSPECTION NOS. 50-245/93-19;

50-336/93-14; AND 50-423/93-15

This refers to the safety inspection conducted by Mr. P. Swetland and others rithis office on

June 30,1993 through August 17,1993, at Millstone Station in Waterford, Connecticut.

l

The preliminary nndings were discussed with Mr. S. Scace, the Unit Directors, and others of

your staff at the conclusion of the inspection. Areas examined during the inspection are

1

described in the enclosed report. Within these areas, the inspection focused on issues

important to public health and safety, and consisted of performance observations of ongoing

activities, independent veri 6 cation of safety system status and design configuration,

interviews with personnel, and review of quality records.

The events surrounding the August 5,1993, Unit 2 plant shutdown and subsequent plant

start-up raised serious NRC concern as to the level of operator attention to and management

~

oversight of these activities. In addition to the work control and management oversight

de6ciencies regarding the leak repair activities which caused the plant shutdown, failures in

work control and plant con 6guration control during the outage resulted in a reactor cooldown

system draindown event and a main steam leak inside containment during the start-up.

Opemtor inattention to the feedwater system caused an automatic reactor trip during the start-

up. As a result, you commissioned several task groups to review the causes of these

problems and implemented several immediate corrective actions to assure the safety of

continued operations. The issues concerning the poor maintenance practices which caused

the shutdown have been documented in NRC Inspection Repon 50-336/93-18. The other

events are documented herein and NRC follow-up of your ongoing corrective actions will be

the subject of future NRC inspections.

9310100034 931006

PDR

ADOCK 05000245

G

PDR

J_Ec(

ju

_

_ ...-

_

-_

.

_

_

_

e

October 6, 1993

l

'.

,

Northeast Nuclear

2

i

Energy Company

l

,

l

During this inspection, we also evaluated your self-identification and correction of problems

l

related to missing penetration fire barriers at Unit 1, late inservice tests at Unit 2, service

water system work control process problems at Unit 3, and inadequate foreign material

!'

exclusion at the Unit 3 spent fuel pool. We determined that your corrective actions for these

.

issues were acceptable and the problems individually posed minor safety consequences.

Therefore, m accordance with Section VII.B of the NRC Enforcement Policy, enforcement

l

discretion was exercised and violations were not cited for these cases. Regarding the Unit 3

!

'

service water obstruction, due to the safety importance of this system, your attention is

warranted to assure that it remains free from design and operational vulnerabilities in the

i

future.

j

!

During this inspection, we evaluated your corrective actions regarding the three violations

issued in inspection Report 50-336/91-05. These violations involved the failure to follow

i

procedures by station personnel involving the installation of an environmentally qualified

electrical splice and were the subject of an enforcement conference on March 27,1991. We

j

found your corrective actions in this matter comprehensive and satisfactory

l

'

We appreciate your cooperation.

Sincerely,

A. Randolph Blough, Chief

l

Projects Branch No. 4

Division of Reactor Projects

j

i

Enclosure:

NRC Combined Inspection Report Nos. 50-245/93 19; 50-336/93-14;

j

and 50-423/93-15

1

<

<

- -,

,

-

. . , - .

.,

- - . .

,,

,

- - - - - - - - .

.

-

-

..

_ _ _ . _ . _ _ _ _ _ _ _ _ _ _ _

"'

'

October' 6,1993

!

.

Northeast Nuclear

3

Energy Company

cc w/ encl:

,

W. D. Romberg, Vice President - Nuclear, Operations Services

S. E. Scace, Vice President, Millstone Station

>

J. P. Stetz, Vice President, Haddam Neck Plant

i

H. F. Haynes, Nuclear Unit Director, Unit i

G. H. Bouchard, Nuclear Unit Director, Unit 2

'

F. R. Dacimo, Nuclear Unit Director, Unit 3

R. M. Kacich, Director, Nuclear Licensing

i

J. M. Solymossy Director of Nuclear Quality and Assessment Services

i

Gerald Garfield, Esquire

Nicholas Reynolds, Esquire

K. Abraham, PAO (2)

i

Public Document Room (PDR)

Local Public Document Room (LPDR)

Nuclear Safety Information Center (NSIC)

NRC Resident Inspector

State of Connecticut SLO

j

.J

!

-!

l

.

-

.

-

-

.-

..

-

. -

.

.

.

.

.

_-

_.

.

i.

October 6, 1993

.

Northeast Nuclear

4

Energy Company

bec w/ encl:

>

Region I Docket Room (with concurrences)

,

bec w/enci (VIA F MAIL)

J. Stolz, NRR/PD l-4

V. McCree, OEDO

I

D. Jaffe, PM, NRR

'

J. Andersen, PM, NRR, Unit 1

G. Vissing, PM, NRR, Unit 2

i

V. Rooney, PM, NRR, Unit 3

?

i

-l

i

i

!

.

!

'

,

RI:I"!P

RI:DRP

RI:DRP

-

T

Swetland

Do.e(Gein

Blough

..

gfy

g,y

10/4 /93

10/1/93

10/3/93

OFFICIAL RECORD COPY

'

G:\\BRANCli4\\MS191415. INS