ML20057D247

From kanterella
Jump to navigation Jump to search
Forwards Insp Repts 50-266/93-13 & 50-301/93-13 on Stated Date.No Violations Noted
ML20057D247
Person / Time
Site: Point Beach  NextEra Energy icon.png
Issue date: 09/24/1993
From: James Gavula
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III)
To: Link R
WISCONSIN ELECTRIC POWER CO.
Shared Package
ML20057D252 List:
References
NUDOCS 9310040031
Download: ML20057D247 (3)


See also: IR 05000266/1993013

Text

f

'

SEP 2 41993

.

Docket Nos. 50-266; 50-301

Wisconsin Electric Power Company

ATTN:

Mr. R. E. Link

Vice President

Nuclear Power

231 West Michigan Street - P379

Milwaukee, WI

53201

Dear Mr. Link:

This refers to the routine safety inspection conducted by Messrs. K. R. Jury,

J. Gadzala and J. H. Neisler of this office, from July 15 through September 6,

1993, of activities at the Point Beach Nuclear Plant Units 1 and 2.

Our

findings were discussed with Mr. G. J. Maxfield and members of his staff at

the conclusion of the inspection.

Areas examined during the inspection are identified in the report.

Within

these areas, the inspection consisted of selective examinations of procedures

and representative records, interviews with personnel, and observations.

No violations of NRC requirements were identified during the course of this

inspection.

It was noted, however, that the unavailability of safety related

equipment was unnecessarily extended on two recent occasions as a result of

poor communications between the Operations and Maintenance groups.

Although

out-of-service times did not exceed technical specification limits,

improvements in inter-group communications appear warranted. We will review

this issue further in future inspections.

In accordance with 10 CFR 2.790 of the Commission's regulations, a copy of

this letter and the enclosures will be placed in the NRC Public Document Room.

We will gladly discuss any questions you have concerning this inspection.

Your cooperation with us is appreciated.

N;j,

I

Sincerely,

Qdafwi 41pc( (y

J. A. Gavula, Acting Chief

Reactor Projects Section 3A

Enclosure:

Inspection Reports

No. 50-266/93013(DRP);

No. 50-301/93013(DRP)

See Attached Distribution

Rill

RIII

RIII

RIII

RHh

fit )

Tongue

Gavula

Gardner

Olteanu

Gre F.r

0100;e

4H

9310040031 930924

PDR

ADDCK 05000266

.

G

PDR

F

.

.

Docket Nos. 50-266; 50-301

Wisconsin Electric Power Company

ATTN:

Mr. R. E. Link

Vice President

Nuclear Power

231 West Michigan Street - P379

Milwaukee, WI 53201

Dear Mr. Link:

This refers to the routine safety inspection conducted by Messrs. K. R. Jury,

J. Gadzala and J. H. Neisler of this office, from July 15 through September 6,

1993, of activities at the Point Beach Nuclear Plant Units 1 and 2.

Our

findings were discussed with Mr. G. J. Maxfield and members of his staff at

the conclusion of the inspection.

Areas examinee during the inspection are identified in the report.

Within

these areas, tie inspection consisted of selective examinations of procedures

and representative records, interviews with personnel, and observations.

No violations of NRC requirements were identified during the course of this

inspection.

It was noted, however, that the unavailability of safety related

equipment was unnecessarily extended as a result of poor communications

between the Operations and Maintenance groups.

Although out of service times

did not exceed technical specification limits, improvements in inter-group

communications are warranted.

In accordance with 10 CFR 2.790 of the Commission's regulations, a copy of

this letter and the enclosures will be placed in the NRC Public Document Room.

We will gladly discuss any questions you have concerning this inspection.

Your cooperation with us is appreciated.

Sincerely,

J. A. Gavula, Acting Chief

Reactor Projects Section 3A

Enclosure:

Inspection Reports

No. 50-266/93013(DRP);

No. 50-301/93013(DRP)

See Attached Distribution

RIII

Ill

Rill

Rlll

Rill

cAf

'yW

CC<3

Tongue

la

Gardner

Olteanu

Greger

9fMh3

f[14f3

QM

M

k

/

'

SEP 2 41993

-

Wisconsin Electric Power

2

Company

.

i

Distribution

cc w/ enclosure:

G. J. Maxfield, Plant Manager

OC/LFDCB

.,

Resident Inspector, RIII

-

i

Virgil Kanable, Chief

Boiler Section

,

Cheryl L. Parrino, Chairman

l

Wisconsin Public Service

.

,

Commission

State Liaison Officer

i