Text
f
'
SEP 2 41993
.
Docket Nos. 50-266; 50-301
Wisconsin Electric Power Company
ATTN:
Mr. R. E. Link
Vice President
Nuclear Power
231 West Michigan Street - P379
Milwaukee, WI
53201
Dear Mr. Link:
This refers to the routine safety inspection conducted by Messrs. K. R. Jury,
J. Gadzala and J. H. Neisler of this office, from July 15 through September 6,
1993, of activities at the Point Beach Nuclear Plant Units 1 and 2.
Our
findings were discussed with Mr. G. J. Maxfield and members of his staff at
the conclusion of the inspection.
Areas examined during the inspection are identified in the report.
Within
these areas, the inspection consisted of selective examinations of procedures
and representative records, interviews with personnel, and observations.
No violations of NRC requirements were identified during the course of this
inspection.
It was noted, however, that the unavailability of safety related
equipment was unnecessarily extended on two recent occasions as a result of
poor communications between the Operations and Maintenance groups.
Although
out-of-service times did not exceed technical specification limits,
improvements in inter-group communications appear warranted. We will review
this issue further in future inspections.
In accordance with 10 CFR 2.790 of the Commission's regulations, a copy of
this letter and the enclosures will be placed in the NRC Public Document Room.
We will gladly discuss any questions you have concerning this inspection.
Your cooperation with us is appreciated.
N;j,
I
Sincerely,
Qdafwi 41pc( (y
J. A. Gavula, Acting Chief
Reactor Projects Section 3A
Enclosure:
Inspection Reports
No. 50-266/93013(DRP);
No. 50-301/93013(DRP)
See Attached Distribution
Rill
RIII
RIII
RIII
RHh
fit )
Tongue
Gavula
Gardner
Olteanu
Gre F.r
0100;e
4H
9310040031 930924
ADDCK 05000266
.
G
F
.
.
Docket Nos. 50-266; 50-301
Wisconsin Electric Power Company
ATTN:
Mr. R. E. Link
Vice President
Nuclear Power
231 West Michigan Street - P379
Milwaukee, WI 53201
Dear Mr. Link:
This refers to the routine safety inspection conducted by Messrs. K. R. Jury,
J. Gadzala and J. H. Neisler of this office, from July 15 through September 6,
1993, of activities at the Point Beach Nuclear Plant Units 1 and 2.
Our
findings were discussed with Mr. G. J. Maxfield and members of his staff at
the conclusion of the inspection.
Areas examinee during the inspection are identified in the report.
Within
these areas, tie inspection consisted of selective examinations of procedures
and representative records, interviews with personnel, and observations.
No violations of NRC requirements were identified during the course of this
inspection.
It was noted, however, that the unavailability of safety related
equipment was unnecessarily extended as a result of poor communications
between the Operations and Maintenance groups.
Although out of service times
did not exceed technical specification limits, improvements in inter-group
communications are warranted.
In accordance with 10 CFR 2.790 of the Commission's regulations, a copy of
this letter and the enclosures will be placed in the NRC Public Document Room.
We will gladly discuss any questions you have concerning this inspection.
Your cooperation with us is appreciated.
Sincerely,
J. A. Gavula, Acting Chief
Reactor Projects Section 3A
Enclosure:
Inspection Reports
No. 50-266/93013(DRP);
No. 50-301/93013(DRP)
See Attached Distribution
RIII
Ill
Rill
Rlll
Rill
cAf
'yW
CC<3
Tongue
la
Gardner
Olteanu
Greger
9fMh3
f[14f3
QM
M
k
/
'
SEP 2 41993
-
Wisconsin Electric Power
2
Company
.
i
Distribution
cc w/ enclosure:
G. J. Maxfield, Plant Manager
OC/LFDCB
.,
Resident Inspector, RIII
-
i
Virgil Kanable, Chief