Ltr Contract,Mod 2,terminating Task Order 206, Reactor Operator Licensing Requalification Exam at Fermi Nuclear Power Plant to Provide for no-cost Settlement Agreement
ML20057A987
Person / Time
Site: Fermi DTE Energy icon.png
Issue date: 08/16/1993
From: Michael Scott
NRC OFFICE OF ADMINISTRATION (ADM)
To: Peterson L
SONALYSTS, INC.
References
CON-NRC-03-89-031, CON-NRC-3-89-31 NUDOCS 9309170032
Download: ML20057A987 (2)


Text

.

~..

1M1 _.

a prof

. 1, i

0 UNITED STATES

]

3 i!

NUCLEAR REGULATORY COMMISSION 1

/-

f WASHINGTON, D.C. 20555-0001 O

Sonalysts, Inc.

ATTN: Leon R. Petersen Manager of Contracts 215 Parkway North i

Post Office Box 280 Waterford, Connecticut 06385

Dear Mr. Petersen:

Subject:

Modification No. 2 Task Order No. 206, " Reactor Operator Licensing -

Requalification Exam at Fermi Nuclear Power Plant," under Contract No. NRC-03-89-031 l

This modification is issued to terminate Task Order No. 206 for the convenience of the Government, to provide for a no-cost settlement agreement, and to reflect the resultant ceiling adjustment for this task order. Therefore, you are hereby notified that Task Order No. 206, under Contract No. NRC-03-89-031 is terminated completely for the Government's convenience under clause 52.249-6, entitled, i

" Te rmi n a ti o n-Co s t-Re i mbu rsemen t". This termination, which results from a change in NRC's requirements, is effective isnediately.

The Contractor unconditionally waives any charges against the Government because of the termination of this task order and releases it _from all obligations under the task ' order or due to its termination.

The Government agrees that all obligations under the task order are concluded.

As a result of this no-cost i

settlement, the total task order ceiling is reduced from $14,539.00 to $0.00.

Accounting data for this modification is as follows:

~

1 B&R No.:

320-19-15-080 3

FIN No.:

L12893 APPN No.:

31X0200.320 Total deobligation amount in FY93:

$14,539.00 Acknowledgement and acceptance of this letter is required, and shall be indicated by signing three copies of this document in the space provided and returning two i

copies to the Contract Administrator identified below.

One copy is to' be retained for your records.

t 01 9309170032 930016~

PDR CONTR

.NRC-03-89-031. PDR2 l

l i

u

)

- 2 Any questions regarding this letter should be addressed to Sharlene McCubbin, Contract Administrator on (301) 492-7764.

Sincerely, O

WO M

diary ynn cott, Contracting Officer Contract Administration Branch No. 1 Division of Contracts and Property Management Office of Administration Acknowledged and Accepted:

~

AME trca p.,

PEigp.sgN MANAGER OF CONTRACTS SONALYSTS, INC.

TITLE E J )',>