E July 7, 1993 Project No. 680 Mr. Charles B. Brinkman, Acting Director Nuclear Systems Licensing AB5 Combustion Engineering Nuclear Power 1000 Prospect Hill Road P.O. Box 500 Windsor, Connecticut 06095-0500
Dear Mr. Kennedy:
SUBJECT:
STAFF REQUIREMENTS MEMORANDUM (SRM) RELATED TO SECY-93-104 Enclosed for your information is the staff's requirement memorandum (SRM) related to SECY-93-104, " Program Analysis and Recommendations Concerning the Nuclear Regulatory Commission review of the Advanced Reactor (PRISM, MHTGR, and PIUS) and CANDU 3 designs." With regard to PIUS, the SRM directs the staff to document the results of the preapplication review and then terminate all other activities until an application for design certification is submit-ted.
In response to the Commission's direction, the staff plans to expend minimal effort over the next few months to closecut and document the Office of Nuclear Reactor Regulation's (NRR's) review and the outstanding Office of Nuclear Regulatory Research and NRK contract efforts related to PIUS which are expected to be completed by the end of 1993. We believe this approach is consistent with the views your representatives expressed in the recent telephone conversations with the staff.
If you have questions regarding this action, please contact D. Scaletti at (301) 492-1104, hfg!8afshnbd by Robert C. Pierson Robert C. Pierson, Director Advanced Reactors Project Directorate Associate Directorate for Advanced Reactors and License Renewal Office of Nuclear Reactor Regulation
Enclosure:
As stated cc w/ enclosure:
hh h.bp h7j7 7 p@7ky
, dILa u
"/)
See next page yge is,-
j Distribution:
Central file PDR DMCrutchfield, NRR RCPierson, NRR THCox, NRR EDThrom, NRR DScaletti, NRR PShea, NRR PDAR R/F 0FC PDFt4DAR.
LA:PDST kPDAR: API D:PDAR;4bAR ADMIMR/
DS h N t PWShea M THC RCPieb Dbtchfield NAME on DATE 07/9/93 07/~//93 [ /93 \\
07/i/93 07/ ') /93 g
0FFICIAL RECORD COPY DOCUMENT NAME:
SRM93104.DCS n
g b "Y 9309270343 930707
/
- f. '
PIUS Project No. 680 cc: Regis Matzie, Director 9354-0401 Ulf Lindelow, Section Chief Advanced Water Reactor Projects PWR Core Design, Fuel Division ABB Combustion Engineering ABB Atom, ABB Nuclear Power S-721 63 Vasteras 1000 Prospect Hill Road Sweden Windsor, Connecticut 06095-0500 John F. Carew Mark Crump, Manager 9341-0407 Building 475 B Reactor Engineering Brookhaven National Laboratory ABB Combustion Engineering Upton, New York 11973-5000 Nuclear Power 1000 Prospect Hill Road Gregory J. Van Tuyle Windsor, Connecticut 06095-0500 Building 475 B Brookhaven National Laboratory Chuck Molnar 9377-0407 Upton, New York 11973-5000 Nuclear Systems Licensing ABB Combustion Engineering Johann Lindner, Vice President Nuclear Power Technology and Engineering 1000 Prospect Hill Road ABB Atom, Inc.
Windsor, Connecticut 06095-0500 200 Great Pond Drr.e Windsor, Connecticu 06095 Lars Nilsson, Technical Manager PlVS Reactor Division Ernie H. Kennedy, Man:ger ABB Atom AB Nuclear Systems Licensing S-721 63 Vasteras ABB Combustion Engineering Sweden Nuclear Power 1000 Prospect Hill Road Harold D. Thornburg P.O. Box 500 ABB Atom, Inc.
Windsor, Connecticut 06095-0500 901 South Warficld Drive Mt. Airy, Maryland 21771 Daniel F. Giessing, Director Office of LWR Safety and Technology Mail Stop NE-42 U.S. Department of Energy Washington, DC 20585 Steve Goldberg, Budget Examiner Office of Management and Budget 725 17th Street, NW Washington, DC 20503 i
i
'..t i-ENCLOSURE
' " ~
Action: Murley, NRR
[,c,,
UNITED STATES f '. ',, 7 NUCLEAR REGULATORY COMMISSION Cys Tay1'or.
n I
wassincTou.o.c. rosss Sniezek Thompson
%, *..../'
Blaha June 9. 1993 Beckjord,RES orFsCE OF THE Stroggins, DC stenETAnv N-Rabideau, OC Case, NRR Pierson, NRR MEMORANDUM TO:
James M. Taylor NRR RECEIVED: 6/10 NRR ACTION: DAR:DC Executive Direc fo Operations NRR RDUTING:
C TEM /FJM FROM:
Samuel J.
Chil ecre ary gg
SUBJECT:
SECY-93-104 - PROGRAM ANALYSIS AND RECOMMENDATIONS CONCERNING THE NUCLEAR TG NRR Mail b REGULATORY COMMISSION (NRC) REVIEWS OF THE ADVANCED REACTOR (PRISM, MHTGR, AND PIUS) AND 1
CANDU 3 DESIGNS This is to advise you that the Commission, with all Commissioners agreeing, has provided the following guidance to the staff on the subject SECY paper.
CANDU-3:
With respect to the CANDU-3 pre-application review, the l
Commission requests the staff to continue its activities to prepare for the design certification application by: (1) l maintaining cognizance of the design, (2) continuing staff familiarization on the design at the technical branch levels, (3) maintaining technical progress on key issues, and (4) computer code development and benchmarking.
It is the Commission's understanding that within one year AECL Technologies is considering submittal of its application to i
certify the CANDU-3 nuclear power plant design.
The Commission recognizes that the staff currently does not have the resources to conduct five reactor certification reviews in parallel, particularly for a plant design which significantly differs from reactors previously licensed in the United States.
i i
SECY NOTE:
SECY-93-104 WAS RELEASED TO THE PUBLIC ON APRIL 29, 1993.
THE SRM AND THE VOTE SHEETS OF THE CHAIPJmN, AND COMMISSIONERS ROGERS, CURTISS AND REMICK WILL BE MADE PUBLICLY AVAILABLE 10 WORKING DAYS FROM THE DATE OF THIS SRM.
'~
h
I I
f
.4
. Assuming that AECL Technologies, Inc. submits its application in i
1994, the Commission requests the staff to identify the estimated RES and NRR resources (i.e., FTE and funds) required to certify the CANDU-3 design along with the associated certification review schedule.
An alternate allocation of resources and review schedule may also be provided.
The resource description should include an identification of both the available resources'as well as the additional resources needed to complete the certification.
-FEiX4-(NRR)
(SECY Suspense:
12/30/93) 9200145 MHTGR and PRISM:
With respect to the MHTGR and PRISM designs, the staff is to continue its review efforts and maintain cognizance of Congressional activities in this area.
Should the Congress decide not to fund the development of the MHTGR and PRISM programs, the staff should contact the respective reactor vendors to determine if they intend to sponsor their activities.
The staff should inform the Commission of the vendors' desire to sponsor their design reviews should the U.S. Government decide not to support these programs.
-P DC9- (NRR)
(SECY Suspense:
As Appropriate)
MHTGR - 8600267 PRISM - 8600269 PIUS:
With respect to PIUS, the staff should document the results of ABB-CE's preapplication review activities conducted to date and terminate all other activities until an application is submitted by ABB-CE.
4EEK9- (NRR)
(SECY Suspense:
3/15/94) 9200146 cc:
The Chairman Commissioner Rogers Commissioner Curtiss Ccmmissioner Remick Commissioner de Planque OGC OIG Office Directors, Regions, ACRS, ACNW (via E-Mail)
ASLBP (via FAX)
.