ML20056D919
| ML20056D919 | |
| Person / Time | |
|---|---|
| Site: | Hope Creek |
| Issue date: | 07/20/1993 |
| From: | Horinka M COLTEC INDUSTRIES, INC. |
| To: | Wray D Public Service Enterprise Group |
| References | |
| NUDOCS 9308190011 | |
| Download: ML20056D919 (1) | |
Text
7:
L.,
Fairbs.nks Morto Coltec Industries -
Engine Division.
~
701 Lawton Avenue Beloit. Wisconsin 53511-5492 Telephone; 608/364-4411 Telecopier: 608/364 0382 -
- Public Service' Electric and Gas Company 20 July,--1993 Hope Creek Generating System P.O.-Box 236 Hancocks Bridge, N.J.
08038
Reference:
Hope Creek letter of 1/6/93 to T. Stevenson (Coltec)
HCT-93-11 l-Attna Mr.
D.
Wray, Systems Engineer PSE&G
Dear:
Hr. Wray After an extensive Engineering review by both our Systems and Engine Engineering groups, it has been determined that a substantial Safety
. Hazard'does not exist.
Therefore Fairbanks Horse does not consider the event reported to us as a Part 21 from our. stand point.
By copy of this letter to Mr.
W.
Haass, the USNRC is.being advised of our findings.
Furthermore,- a series of check valves were installed to prevent _the:
reverse flow.-discharge feeding intake, scenario. described.in1several letters sent-to1us.
If the check valves are in place.'there can be'no reverse flow through'either of the pumps.
We have found the root cause to be that upon receipt of.-these_ pumps:at Fairbanks Horse,_they were' mismarked'with the wrong.part number.
Only:.
4 of these pumps were ordered for Service Stock, and the location of the fourth pump is not at a Nuclear Site.
A check of our Parts Dedication Program'(SP 750) shows that a flow Echeck is required to-verify the correct rotation of<the pump.
Thus in any. future Safety Related orders you can be assured'that the correct rotation pumps will be delivered.
-nsh Sincerely.
Michael S.
Horinka Manager _ Quality: Assurance and Field' Quality
[ k kSh$ N Haahsi[USNRb $
T. Stevenson
- N.[Traeger G.JGutoski pp ]'
O
- Sko
'930Bikd'011 930720 PDR. ADDCK 05000354 A *=n of cona inoamn i g
<