ML20056C888
| ML20056C888 | |
| Person / Time | |
|---|---|
| Site: | Peach Bottom |
| Issue date: | 07/20/1993 |
| From: | Bettenhausen L NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION I) |
| To: | Danni Smith PECO ENERGY CO., (FORMERLY PHILADELPHIA ELECTRIC |
| References | |
| NUDOCS 9307260088 | |
| Download: ML20056C888 (3) | |
Text
.e.
'4:
JUL 2 01993 Docket Nos. 50-277 50-278 Mr. D. M. Smith Senior Vice President-Nuclear Philadelphia Electric Company Nuclear Group Headquarters Correspondence Control Desk P. O. Box 195 Wayne, Pennsylvania 19087-0195
Dear Mr. Smith:
SUBJECT:
10 CFR 50.54 QUALITY ASSURANCE PROGRAM CHANGE REVIEW
References:
Letter dated June 29,1993, from Mr. G. R. Rainey to the U. S. Nuclear Regulatory Commission transmitting Revision 11 of the Updated Final Safety Analysis Report and the Submittal of the Annual Revision to the Peach Bottom Atomic Station, Units 2 and 3 Quality Assurance Program Description We received your 10 CFR 50.71(e) submittal, referenced above, transmitting the annual submittal of changes to the Peach Bottom Quality Assurance (QA) Program Description as required by 10 CFR 50.54(a). An initial review of this QAP change submittal has begun; however, based on our current review' schedule, we anticipate that it will require more than 60 days to complete our review. Upon completion, you will be notifici of the results.
If you have any questions concerning the above, please contact Mr. N. Blumberg at (215) 337-5199 or Mr. F. Bower at (215) 337-5328.
Sincerely, ORIGINAL stGNED BY HORMAN 3 BLUMBERG Ixe H. Bettenhausen, Chief Operations Branch Division of Reactor Safety
~~
9307260008.930720
%i PDR ADDCK-05000277
\\4)
P PDR
Mr. D. M. Smith 2
JUL 2 01993 cc:
J. Doering, Chairman, Nuclear Review Board D. B. Miller, Vice President, Peach Bottom Atomic Power Station
.G. Rainey, Vice President, Nuclear Services Department I
G. Cranston, General Manager, Nuclear Engineering Division C. Schaefer, External Operations - Nuclear, Delmarva Power & Light Co.
G. Edwards, Plant Manager, Peach Bottom Atomic Power Station A. J. Wasong, Manager, Experience Assessment G. A. Hunger, Jr., Manager, Licensing Section J. W. Durham, Sr., Senior Vice President and General Counsel J. A. Isabella, Director, Generation Projects Department, Atlantic Electric B. W. Gorman, Manager, External Affairs R. McLean, Power Plant Siting, Nuclear Evaluations D. Poulsen, Secretary of Harford County Council R. Ochs, Maryland Safe Energy Coalition J. H. Walter, Chief Engineer, Public Service Commission of Maryland Public Document Room (PDR)
Imal Public Document Room (LPDR)
Nuclear Safety Information Center (NSIC)
NRC Resident Inspector Commonwealth of Pennsylvania TMI - Alert (TMIA) bec:
Region I Docket Room (with concurrences)
V. Curley, DRS (2).
DRS Files (2) bec: (Via E-Mail)
V. McCree, OEDO Joseph Shea, NRR M. Boyle, Acting PDI-2, NRR
.j R. Gramm, NRR F. Bower, DRS I
1 l
i OFFICIAL RECORD COPY G:PBQA629.FLB 1
.- i
Mr. D. M. Smith 3
JUL 201993 (VIA FeMAIL AND NO ATTACIIMENTS)
L. Bettenhausen, DRS N. B_lumberg, DRS
.i. Caruso, DRS i
i RI:DRS RI:DRS RI:DRS Bower /aj '
Blum erg Bettenhausen h
&f LH0 07//k93 07/h93 07/l 93 OFFICIAL RECORD COPY.. G:PBQA629.FLB q