((0 q
a-Department of Nuclear Engineering -
l IOWA STATE
- Ii'l5sil2%"
1
' UNIVERSITY.
Telephone 515-2945840-Docket.No. 50-116 Ref:
' July-20,11990~
U.S. Nuclea'r Regulatory Commission ATTN:- Doc"=ent Control Desk i
Washirgton, D.C.l20555
'RE: ' DECOMMISSIONING. REPORT FOR THE IOWA STATE UNIVERSITY NUCLEAR REACTOR e
Pursuant.to paragraph 50.75(d) of-10 CFR Part 50, we are subt.itting a'decommis-e Mioning report.
~
L
-1.
Estimated cost o_f decommissioning: $740,000 4
This is the most pessimistic estimate because it is based on the assumption
~ that all materials within the biological shield, the coolant system, and the fuel storagespit are classified as radioactive wastes and must-be shipped 1
and buried.
2.-
Statement of Intent:
Funds for decommissioning will be obtained when neces--
4 sary.
3.
The Reactor Staff.will update the cost estimate annually by applying.the 1
latest charges to the transportation and burial category, and by applying the current escalator toL labor-and materials-dependent categories.
Very truly yours, j
B.I.9arnol Bernard I. Spinrad 1
. Facility--Director 1
p The-' Statement of Intent is approved.
-l AY y
k
. Warren R. Madden
.Vice' President for Business and Finance J
/rpa n
~
CC :-- Regional Administrator, US NRC, Region III
.D. T. Kao, Dean, Engineering College T. H. Okiishi, Chm., Mechanical Engineering Dept.
i R. A. Jacobson, Chm., Radiation Safety Comm.
l-E. E. Sobottka, Dir., -Environmental Health & Safety Dept.
l.
R. A. Danofsky, Chm., Reactor Use Comm.
l h
Ob50 $00fffu 4/d i