Text

APPENDIX F Template for 10 CFR 52.103(g) Letter to Licensee LIC-114, Revision 1 "Title 10 of the Code of Federal Regulations (10 CFR) Section 52.103(g)

Finding and Communication Process"

[date]

[Senior Officer Name]

[Licensee]

[Licensees address]

SUBJECT:

FINDING THAT ALL ACCEPTANCE CRITERIA ARE MET FOR [plant name]

COMBINED LICENSE [if interim operation is allowed, add: AND ORDER ALLOWING INTERIM OPERATION]

Dear [senior officer name]:

In accordance with Section 185b. of the Atomic Energy Act of 1954, as amended, and Title 10 of the Code of Federal Regulations (10 CFR) 52.103(g), the U.S. Nuclear Regulatory Commission (NRC) has made the finding that all the acceptance criteria are met for the inspections, tests, analyses, and acceptance criteria (ITAAC) included in Appendix C to combined license [license number] for [plant name]. This finding is effective as of [date]. [If interim operation is allowed, add: Also, the NRC has determined in accordance with Section 189a.(1)(B) of the Atomic Energy Act of 1954, as amended, and 10 CFR 52.103(c) that there is reasonable assurance of adequate protection of the public health and safety during a period of interim operation. Based on this determination, the NRC has issued an order allowing interim operation that is effective as of [date].]

Therefore, in accordance with 10 CFR 52.103(g) [if interim operation is allowed, add: and 10 CFR 52.103(c)], the [licensee] may now operate the facility in accordance with combined license [license number] [if interim operation is allowed and additional terms and conditions are included, add: and the terms and conditions in the order allowing interim operation]. The ITAAC in COL [license number] no longer constitute regulatory requirements.

Enclosed is the NRCs finding that the acceptance criteria are met [if interim operation is allowed, add: and the order allowing interim operation]. The basis for the 10 CFR 52.103(g) finding is documented in the 10 CFR 52.103(g) Basis Document for

[plant name] and can be found in the NRCs Agencywide Documents Access and Management System (ADAMS) at Accession No. [ADAMS ML number]. The Basis Document can also be found on the NRCs public Web site. [If interim operation is allowed, add: The basis for the NRCs determination that there is reasonable assurance of adequate protection of the public health and safety during a period of interim operation is in the [Commission Order], dated [date].]

F-1

If you have questions, please contact [licensing project manager] at [phone number], or

[NRC e-mail address].

Sincerely,

[name], Director Division of [division name]

Office of [office name]

Docket No. [docket number]

Enclosure:

Finding that Acceptance Criteria in the Combined License Are Met

[If interim operation is allowed, add: Order Allowing Interim Operation]

F-2