LOUISIANA / 142 DRARONDE STRHT POWER & LiG H T/ P O BOX 6008
]; [M@{]$fMgg@p 14,1982 V~~~~ _
-1 G D. McLENDON l L)
Senior Vice President JUL 191982 i
<\\
l'g, W3K 82-0414
~
Q-3-A35.07.38 Mr. John T. Collins, Regional Administrator, Region IV U. S. Nuclear Regulatory Commission 611 Ryan Plaza Drive, Suite 1000 Arlington, Texas 76012 Subj ec t : Waterford SES Unit No. 3 Docket No. 50-382 Significant Construction Deficiency No. 38
" Start-Up Test Control; Flooding of Emergency Diesel Generator Control and Relay Pancl" Second Interim Report
Reference:
LP&L Letter W3K 81-0422 to NRC dated November 30, 1981
Dear Mr. Collins:
Replacement panels for the Emergency Diesel Generator are scheduled on site for July 15, 1982.
Installation should be complete to allow the final report to be submitted on August 16, 1982.
If you have any questions, please call me.
Very truly yours,
. &. M ' A GDMcL/LLB/grf cc:
- 1) Director Office of Inspection & Enforcement U. S. Nuclear Regulatory Commission Washington, D. C. 20555
- 2) Direc tor Office of Management Information and Program Control U. S. Nuclear Regulatory Commission 4
Washington, D. C. 20555