ML20055B757

From kanterella
Jump to navigation Jump to search
Fifth Interim Deficiency Rept Re ITE-Gould Starter Coil Failure in Containment Cooling Fans.Coils Replaced.Final Rept Will Be Submitted on or Before 820914
ML20055B757
Person / Time
Site: Waterford Entergy icon.png
Issue date: 07/15/1982
From: Mclendon G
LOUISIANA POWER & LIGHT CO.
To: Jay Collins
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION IV)
References
10CFR-050.55E, 10CFR-50.55E, W3K-82-0420, W3K-82-420, NUDOCS 8207230267
Download: ML20055B757 (1)


Text

r -

m LOUISIANA 242 ouAnoNoe srnter POWER & LIGHT p o sox 6008

= cawa

,N bh f5 f h/ uly 15, 1982 G D McLENDON

' Senior Vice Presodent

~

.y W3K-82-0420 Q-3-A35.07.40 Mr. John T. Collins, Regional Administrator, Region IV U. S. Nuclear Regulatory Commission 611 Ryan Plaza Drive, Suite 1000 Arlington, Texas 76012

SUBJECT:

Waterford SES Unit No. 3 -

Docket No. 50-382 Significant Construction Deficiency No. 40 "ITE-Gould Starter Coil Failure in Containment Cooling Fans" Fifth Interim Report

Reference:

LP&L Letter W3K 82-0353 dated June 17, 1982

Dear Mr. Collins:

Louisiana Power & Light Company committed to submitting a Final Report on the subject Significant Construction Deficiency by July 12, 1982.

We are unable to submit a final report on this date.

The twelve (12) replacement coils identified have been replaced. Six (6) of the coils in question are to be returned to vendor for examination and evaluation as to coil failure.

The Final Report of Significant Construction Deficiency No. 40 will be submitted on or before September 14, 1982.

If you have any questions, please advise.