Application to Amend License NPF-11,adding License Condition Re Torquing of Nonpressure Boundary Bolts on safety-related Valves Located Outside of Primary Containment.W/Class II Amend Fee
ML20055A997
Person / Time
Site: LaSalle Constellation icon.png
Issue date: 07/14/1982
From: Schroeder C
COMMONWEALTH EDISON CO.
To: Schwencer A
Office of Nuclear Reactor Regulation
References
NUDOCS 8207200228
Download: ML20055A997 (5)


Text

.

. [^ 's Commonwealth Edison

/ ') LaSalle County Nuclear Station RuralRoute 01, Box 220

( 7 Marseilles, Illinois 61341 s / Telephone 815/357-6761 x.-

July 14,1982 Mr. A. Schwencer, Chief Licensing Branch #2 Division of Licensing U.S. Nuclear Regulatory Commission Washington, D.C. 20555

SUBJECT:

LaSalle County Station Unit 1 Proposed Amendment to NPF-ll NRC Docket No. 50-373

Dear Mr. Schwence r:

The purpose of this letter is to request the following change in the i License NPF-11 for LaSalle County Station Unit 1:

I l Change Request NPF-11/82-9 Add license condition regarding torquing of non pressure boundary bolts on Safety-Related valves located outside of primary containment.

Thi s change reques t is being submitted at the direction of the NRC.

This change is one Class 11 amendment since i t simply incorporates into the license an agreement that was previously reached between the licensee and the Office of Inspection and Enforcement - Region 111.

This proposed change is addressed in the Attachment. This change has o/

received on-si te and of f-si te review and approval . Attachment "B" lists the status of License Change Requests for LaSalle. s

/'

QGt W/64 Pursuant to 10 CFR 170, this change reflects one Class ll amendment. A remittance of $1,200.00 is , the refore, enclosed. b Please contact this office if there are any questions Ir. this matter.

8207200228 820714 PDR ADOCK 05000373 PDR A

Three (3) signed originals and thi rty-seven (37) copies of this transmittal and attachments are provided for your use.

Very truly yours, 7l1+} 6%

C. W. Schroeder Nuclear Licensing Administrator CWS/msJ Attachments cc: NRC Resident inspector - LaSalle SUBSCRIBED AND SWORN ~ T0.

before me this- N . day of nbts ,~ 1982.

V f dAIL NOTARY PU@ C -

LASALLE COUNTY STATION UNIT 1 LICENSE CHANGE REQUEST NPF-11/82-9 SUBJ ECT: Add license condition regarding torquing of non pressure boundary bolts on Safety-Related valves located outside Primary Containnent.

BACKGROUND During the review of allegations at LaSalle, Region ill, 1&E Personnel questioned the adequacy of torquing of bolting. The licensee addressed the issues and demonstrated their basis for confidence that torquing of bolting was satisfactory. In order to provide addi tional assurance, at the NRC's request, the licensee agreed to perform the following actions:

a) Prior to exceeding 5% power, check the torque on non pressure boundary bolts (bolts whose failure will affect the operation of the valve) on each Safety-Related valve located inside the primary containnent.

b) Within 6 months, check the torque on non pressure boundary bolts (bolts whose failure will affect the operation of the valve) on each Safety-Related valve located outside the primary containment.

DISCUSSION The torque on non-pressure boundary bolts has already been checked on Safety-Related valves located inside the Primary Containment.

Therefore, action (a) above has been completed.

On July 14, 1982, Dr. A. Bournia of the NRC staff notified the licensee that the requi rement for action (b) above had to be addressed as a license condition and he directed the licensee to submit the following statement as a proposed license change:

" Prior to January 15, 1983, the licensee shall check the torque on all non pressure boundary bolts (bolts whose failure will affect the operation of the valve) on each Safety-Related valve located outside of containment."

Commonwealth Edison Company notes the following clarifications on this statement:

1) Containment refers to primary containment.
2) Torque wrenches can not be utilized to check torque on certain bolts due to the as-installed configuration. It is NOT the intent of this condition to require the destruction of the system to perform the required check. Rather, the licensee wi l l ut i l ize a "best ef fort" on inaccessible bolts to demonstrate adequate torquing.

_ _ _ _ _ _n

r 4

CONCLUSION Commonwealth Edison finds no unreviewed safety question. This license condition simply confirms a previous commitment made by the licensee.

o STATUS OF CHANGE REQUESTS NRC

  1. TOPlc SUBMITTED ACTION NPF-11/82-1 Hydrogen Recombiner Temperature 5/24/82 issued Am. 1 Controller Setpoint Deviation. .

6/18/82 (Requi red Prior to Criticali ty) .

NPF-11/82-2 MSIV Closure Scram Setpoint 5/24/82 issued Am. 1 (Requi red Prior to Cri ticali ty). 6/18/82 NPF-11/82-3 Special Test Exception Change for 6/01/82 6/03/82 verbal Confirmatory Flow induced Vibration Authorization Test (Required Prior to Test 6/07/82 letter which commenced 6/03/82). Issued Am.1.

6/18/82 NPF-11/82-4 Revised Snubber List (License -

6/07/82 1ssued Am. 1 Condi tion 2.C. (5), (a) Requi red 6/18/82 Prior to Criticality).

NPF-11/82-5 Tendon Tables (License Condition 6/14/82 Issued Am. 1 2.C. (7) Requi red Prior to Full Power). 6/18/82 NPF-11/82-6 Fi re Detector Tables (License Condi tion 6/14/82 issued Am. 1 2.C.(25)(b) Required Prior to 6/18/82 Criticality)

NPF-11/82-7 SRM Count rate (Required prior to source 6/14/82 issued Am. 2 decay below 3 cps). 7/9/82 NPF-11/82-8 Revise RCIC suction delta p alarm 7/02/82 Issued Am.'2 setpoint (Required prior to 7/9/82 pressurization).

NPF-11/82-9 Add commi tnent to complete torque 7/14/82 checks on bolting on S/R valves outside containment (NRC Requested to be submitted ASAP)