Responds to 820308 Request for Addl Info Re IE Bulletin 80-11, Masonry Wall Design. Block Wall Mods Will Be Completed by Nov 1983
ML20055A994
Person / Time
Site: Davis Besse Cleveland Electric icon.png
Issue date: 07/14/1982
From: Crouse R
TOLEDO EDISON CO.
To: Stolz J
Office of Nuclear Reactor Regulation
References
REF-SSINS-6820 841, IEB-80-11, NUDOCS 8207200225
Download: ML20055A994 (1)


Text

HREDO

%se EDISON Docket No. 50-346 License No. NPF-3

8"58 "8' Serial No. 841 July 14, 1982 Director of Nuclear Reactor Regulation Attention:

Mr. John F. Stolz Operating Reactor Branch No. 4 Division of Operating Reactors United States Nuclear Regulatory Commission 1

Washington, D.C.

20555

Dear Mr. Stolz:

Your letter dated March 8, 1982 (Log No. 918) requested additional information concerning Masonry Wall Design, IE Bulletin 80-11, as it relates to Davis-Besse Nuclear Power Station Unit No.

1.

Toledo Edison responded to all the concerns except one in our May 3, 1982 and June 16, 1982 submittals (Serial Nos. 814 and 826). The remaining concern was a scchedule for the conclusion of the wall modifications.

Toledo Edison is currently in an extended refueling outage that has caused a considerable slippage in most work items not outage related.

The reasons for this are all related to the reallocation of resources to ensure a timely return of Davis-Besse to power operation. Upon completian of the outage related work, resources may once again be scheduled for more routine work.

Based on our estimates at this time, Toledo Edison expects to complete the block wall modifications associated with IE Bulletin 80-11 work by November 1983.

Very truly yours,