ML20055A586

From kanterella
Jump to navigation Jump to search
Interim Deficiency Rept Re Significant Const Deficiency 45 Concerning Failure of Akr 50 Relay Bell Switch Mounting.Matl Installation & Rework Completed.Final Rept Will Be Submitted by 820723
ML20055A586
Person / Time
Site: Waterford Entergy icon.png
Issue date: 07/06/1982
From: Mclendon G
LOUISIANA POWER & LIGHT CO.
To: Jay Collins
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION IV)
References
10CFR-050.55E, 10CFR-50.55E, W3K-82-0391, W3K-82-391, NUDOCS 8207190214
Download: ML20055A586 (1)


Text

LoulSIANA f 24a OuAnONoE srnur POWE R & L1G H T/ P O BOX 6000

  • NEW ORLEANS. LOUISIANA 70174 . (504) 366 2345 uT ONE$YIU July 6, 1982 G. D. McLENDON Senior Vice President W3K-82-0391 Q-3-A35.07.45 Mr. John T. Collins, Regional Administrator, Region IV U. S. Nuclear Regulatory Commission lI D 611 Ryan Plaza Drive, Suite 1000 fM @[5 ((\W Arlington, Texas 76012 fj/

Subject:

Waterford SES Unit No. 3 \ R l 21982 Docket No. 50-382 \- '

Significant Construction Deficiency No. 45 "AKR 50 Relay Bell Switch Mounting Failure" l

Reference:

LP&L Letter W3K-82-0080

Dear Mr. Collins:

The material installation and rework required to correct the "AKR 50 Relay Bell Switch Mounting Failure" has now been completed by LP&L personnel. EBASCO is now compiling those required documents to provide closure of this SCD-45.

The final report will be submitted on July 23, 1982.

Very truly yours,

?

cc: 1) Director Office of Inspection & Enforcement U. S. Nuclear Regulatory Commission Washington, D. C. 20555

2) Director Office of Management Information and Program Control

}X U. S. Nuclear Regulatory Commission p Washington, D. C. 20555 \p 8207190214 820706 PDR ADOCK 05000392 S pon j