Forwards QA Program Insp Rept 99900289/82-01 on 820322-25 & Notice of Nonconformance.Written Response Requested within 30 Days
ML20054M582
Person / Time
Issue date: 06/18/1982
From: Potapovs U
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION IV)
To: Dubrow A
BYRON JACKSON PUMP
Shared Package
ML20054M583 List:
References
REF-QA-99900289 NUDOCS 8207130637
Download: ML20054M582 (2)


Text

-

$'o Docket No. 99900289/82-01 JUN 181982 Nuclear Valve Division Borg Warner Corporation ATTN:

Mr. A. L. DuBrow President and General Manager 7500 Tyrone Avenue Van Nuys, CA 91409 Gentlemen:

This refers to the inspection conducted by Mr. J. W. Sutton of this office on March 22-25, 1982, of your facility at Van Nuys, California, associated with the manufacture of nuclear valves and to the discussion of our findings with Mr. C. P. Spiegel and members of your staff at the conclusion of the inspection.

This inspection was made as a result of the identification by:

(1) Duke Power Company of internal binding in 8-inch gate valves furnished to Catawba 1 and 2; and by (2) Tennessee Valley Authority concerning the specification on a Borg Warner drawing of excessive bolt torque for a flow control valve furnished to Bellefonte 1 and 2.

Areas examined and our findings are discussed in the enclosed report.

Within these areas, the inspection consisted of an examination of procedures and representative records, interviews with personnel, and observations by the inspector.

During the inspection it was found that the implementation of your QA program failed to meet certain NRC requirements.

The specific findings and references to the pertinent requirements are identified in the enclosures to this letter.

Please provide us within 30 days from the date of this letter a written statement containing:

(1) a description of steps that have been or will be taken to correct these items; (2) a description of steps that have been or will be taken to prevent recurrence; and (3) the date your corrective actions and preventive measures were or will be completed.

Consideration may be given to extending your response time for good cause shown.

C R& CPS SC:

CS BC:VPB D:IESYN RA:RIV

'Sutton/rf I

s UPotapovs EHJohnson JThollins AN

)

82 6/S/82 6/6/82 6/p/82 sp &

8207130637 820618 PDR GA999 EMVBORG QC 99900289 PDR

W s.

Nuclear Valve Division The response requested by this letter is not subject to the clearance procedures of the Office of Management and Budget as required by the Paperwork Reduction Act or 1980, PL 96-511.

In accordance with 10 CFR 2.790 of the Commission's regulations, a copy of this letter and the enclosed inspection report will be placed in the NRC's Public Document Room.

If this report contains any information that you believe to be exempt from disclosure under 10 CFR 9.5(a)(4), it is necessary that you (a) notify this office by telephone within 10 days from the date of this letter of your intention to file request for with-holding; and (b) submit within 25 days from the date of this letter a written application to this office to withhold such information.

If your receipt of this letter has been delayed such that less than 7 days are available for your review, please notify this office promptly so that a new due date may be established.

Consistent with section 2.790(b)(1), any such application must be accompanied by an affidavit executed by the owner of the information which identifies the document or part sought to be withheld, and which contains a full statement of the reasons on the basis which it is claimed that the information should be withheld from public disclosure.

This section further requires the statement to address with specificity the considerations listed in 10 CFR 2.790(b)(4).

The information sought to be withheld shall be incorporated as far as possible into a separate part of the affidavit.

If we do not hear from you in this regard within the specified periods noted above, the report will be placed in the Public Document Room.

Should you have any questions concerning this inspection, we will be pleased to discuss them with you.

Sincerely, Uldis Potapovs, Chief Vendor Programs Branch

Enclosures:

1.

Appendix A - Notice of Nonconformance 2.

Appendix B - Inspection Report No. 99900289/82-01 3.

Appendix C - Inspection Data Sheets (7 pages) bcc:

IE Files ASME AE00 NBB&PVI QAB NRC:PDR Reg. Administrators, I, II, III, IV, V i