Monthly Operating Summary Repts for May 1982
ML20054M112
Person / Time
Site: Hope Creek, Turkey Point, 05000000
Issue date: 06/15/1982
From: Pace P
FLORIDA POWER & LIGHT CO.
To:
Shared Package
ML20054M092 List:
References
NUDOCS 8207090260
Download: ML20054M112 (3)


Text

.

SUMMARY

OF OPERATING EXPERIENCE DOCKET NO.

50-250 UNIT Turkey Point Unit No. 3 DATE June 15, 1982 COMPLETED BY Paul L. Pace TELEPHONE (305) 552-3654 REPORT MONTH May 1982 Unit 3 operated at essentially full power except for outages on 5/15, 5/19 and 5/20. See the " Unit Shutdown Report" and Power Reduction for details.

Major Safety-related maintenance activities performed during the month included:

Steam Generator Blowdown line snubber, and pipe hangers were rebaired.

Diesel Generator auto start compressor was repaired.

Inspections and requirements of IE Bulletins and NUREG-0737 are continuing.

Florida Power & Light Company commitments for NUREG-0737 Implementation are continuing. Refer to correspondence between FPL and NRC for additional information.

l l

t.

l l

i t

S

{

l.

8207090260 820615 PDR ADOCK 05000250 R

PDR L

t I

o I

t l

SUMMARY

OF OPERATING EXPERIENCE DOCKET NO.

50-251 UNIT Turkey Point Unit No. 4 DATE June 15, 1982 COMPLETED BY P.L. Pace TELEPHONE (305) 552-3654 REPORT MONTH May 1982 Unit 4 operated at essentially full power for the entire month, except for an outage on May 5.

See the " Unit Shutdowns and Power Reductions" Report for details.

Major maintenance activities performed during the month included:

Diesel Generator auto start compressor was repaired.

Inspections and requirements of IE Bulletins and NUREG-0737 implementation are continuing.

Refer to correspondence between FPL and NRC for additional information.

See the " Unit Shutdowns and Power Reductions" Report for additional maintenance activities.

SUMMARY

OF OPERATING EXPERIENCE DOCKET NO.

50-335 UNIT St. Lucie Unit No. 1 DATE June 15, 1982 COMPLETED BY P.L. Pace TELEPHONE (305) 552-3654 IEPORT MONTII May 1982 Unit 1 operated at essentially full power except for the scheduled outage for steam generator tube inspector.

Major Safety-related maintenance activities performed during the month included:

Steam genergtor tube eddy current testing.

Reactor coolant pump seal repair.

Code pressurizer safety valve replacement Inspections and requirements of IE Bullentins and NUREG 0737 in progress.

Florida Power & Light Company commitments for NUREG-0737 implementation are continuing.

Refer to correspondence between FPL and NRC for additional information.