Informs of Surveillance Program for Alternate Equipment Hatch Airlock.Surveillance Will Consist of Insp & Lubrication of Door Hinges,Interlock Shaft Pillow Blocks & Universal Joints & Chain Drives Interlock Sys
ML20054L501
Person / Time
Site: Crane Constellation icon.png
Issue date: 06/30/1982
From: J. J. Barton
GENERAL PUBLIC UTILITIES CORP.
To: Barrett L
Office of Nuclear Reactor Regulation
References
4400-82-L-0105, 4400-82-L-105, NUDOCS 8207080183
Download: ML20054L501 (2)


Text

e

/

GPU Nuclear

]

g g{

P.O. Box 480 Middletown Pennsylvania 17057 717-944-7621 Writer's Direct Dial Number:

June 30, 1982 4400-82-L-0105 TMI Program Office Attn:

Mr. L. H. Barrett, Deputy Program Director US Nuc1 car Regulatory Commission C/0 Three Mile Island Nuclear Station Middletown, PA 17057

Dear Sir:

Three Mile Island Nuclear Station, Unit 2 (TMI-2)

Operating License No. DPR-7?

Docket No. 50-320 Personnel Airlocks GPU letter 4400-82-L-0090 which responded to several NRC questions on the Personnel Airlocks (PAL's) committed GPU to provide the NRC with a proposal for performing surveillances on the alternate equipment hatch airlock. Accordingly, GPU has reviewed the airlock design and determined that following the present maintenance and lubrication program an annual surveillance will be initiated. This surveillance will consist of inspection and lubrication of the following components:

1.

Door hinges and interlock shaft pillow blocks 2.

Interlock shaf t universal joints 3.

Latch and valve linkage pivots 4.

Push / pull cable and 1cver 5.

Chain drives interlock system Other major components in the airlock such as the door latches, the Geneva gear unit, and the interlock system are considered to be " lifetime" lubricated by the manufacturer; therefore, no surveillances are proposed for these components.

E m

ki L1 Your letter suggested that theproposedsurveillancesbeincludedasay requested change to the Recovery Operations Plan. However, because of -

g <n the maintenance program GPU is performing on both airlocks, and the Q

commitment, stated above, to institute an annual operations surveillance c,p 5E N

_s~

u u

5 N

r boo 7 8207080183 820630 PDR ADOCK 05000320 P

PDR GPU Nuclear is a part of the General Public Utilities System

4400-82-L-0105 Mr. L. II. Barrett -o r

on each airlock, a specific Recovery Operations plan surveillance for the alternate equipment hatch airlock should not be required.

If you have any further questions on this subject, please contact Mr.

J.

E. Larson of my staff at extension 8832.

S ncerely, f

I J'.

Barton Acting Director, TMI-2 JJB/JEL/JJB/jep CC:

Dr. B. J. Snyder, Program Director - TMI Program Office