Final Deficiency Rept Re Replacement of Cracked Reactor Core Isolation Cooling Underground Piping,Initially Reported 820125.Piping Will Be Completely Replaced by 821015
ML20054L104
Person / Time
Site: LaSalle  Constellation icon.png
Issue date: 06/29/1982
From: Schroeder C, Shroeder C
COMMONWEALTH EDISON CO.
To: James Keppler
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III)
References
10CFR-050.55E, 10CFR-50.55E, 4438N, NUDOCS 8207070155
Download: ML20054L104 (1)


Text

.

/

/ / one First [!ational Plaza. Chicago. Illinois

\(v{ NAddressCommonwzith Reply to: Post Office Box 767Edison Chicago, Illinois 60690 June 2 9, 1982 Mr. James G. Keppler, Regional Administrator Directorate of Inspection and Enforcement - Region III U.S. Nuclear Regulatory Commission 799 Roosevelt Road Glen Ellyn, IL 60137

Subject:

LaSalle County Station Units 1 and 2 10 CFR 50.55(e) #82-10 RCIC Underground Piping Revised Final Report NRC Docket Nos. 50-373 and 50-374 Reference (a): C. E. Sargent letter to J. G. Keppler dated January 25, 1982.

Dear Mr. Keppler:

The purpose of this letter is to update information previously provided to you in Reference (a).

Re ference (a) stated that replacement piping for Unit 1 will be completed by July, 1982. It should be noted that although the Unit 1 piping has successfully passed required tests, Common-wealth Edison Company decided to replace it, along with the Unit 2 piping which exhibited cracking.

Commonwealth Edison has determined that the replacement of the Unit 1 piping will not be completed by July, 1982. The primary reasons for not meeting the July,1982 completion date are bad working weather (most of the piping is underground) and redirection of craf t manpower to other critical tasks.

The revised expected completion date for the replacement of the currently intact Unit 1 piping is October 15, 1982. This revised date includes some margin for currently unforseen problems.

If there are any questions in this matter, please contact this office.

Sincerly, CP)

C. W.

k a/2sist Schroeder Nuclear Licensing Administrator 1m cc: NRC Resident Inspector - LSCS Director of Inspection and En forcement - Washington, D.C.