ML20054K215

From kanterella
Jump to navigation Jump to search
Informs That Changes to NUREG-0737,Item II.E.4.2.6 Is Complete for Units 1 & 3 & Will Be Completed for Unit 2 During Upcoming Outage in Aug.Schedule for Item II.B.3 Revised from 811028 & 1120 Submittals.New Schedule Listed
ML20054K215
Person / Time
Site: Browns Ferry  Tennessee Valley Authority icon.png
Issue date: 06/28/1982
From: Mills L
TENNESSEE VALLEY AUTHORITY
To: Harold Denton
Office of Nuclear Reactor Regulation
References
RTR-NUREG-0737, RTR-NUREG-737, TASK-2.B.3, TASK-2.E.4.2, TASK-TM NUDOCS 8207010301
Download: ML20054K215 (1)


Text

',

t TENNESSEE VALLEY AUTHORITY CHATTANOOGA. TENNESSEE 374o1 400 Chestnut Street Tower II June 28, 1982 Mr. Harold R. Denton, Director Office of Nuclear Reactor Regulation U.S. Nuclear Regulatory Commission Washington, DC 20555

Dear Mr. Denton:

In the Matter of the

)

Docket Nos. 50-259 Tennessee Valley Authority

)

50-260 50-296 The purpose of this letter is t'o inform you of changes on two, NUREG-0737 items for Browns Ferry Nuclear Plant. In my October 28 and November 20, 1981 letters to you, we erroneously indicated that item II.E.4.2.6, " Containment Isolation Dependability," was complete on all three units. At the time.of these submittals, this work was complete on unit 1, ongoing on unit 3, and planned for the unit 2 late summer 1982 outage. At present, this item is complete on units 1 and 3 and will be completed on unit 2 during the upcoming outage in August. The correct schedule for this work was provided to you in my February 19, 1982 letter on the subject of containment purge.

Also, the schedule for item II.B.3, " Post Accident Sampling (PASF),"

has been revised from our October 28 and November 20, 1981 submittals. The new schedule is as follows for outage-related work.

Start Date Complete Date Unit 2 Cycle 5 - April 1984 Unit 2 Cycle 6 - December 1985 l

Unit 1 Cycle 6 - October 1984 Unit 1 Cycle 7 - June 1986 Unit 3 Cycle 6 - March 1985 Unit 3 Cycle 7 - November 1986 o46 l

l 8207010301 820628 PDR ADOCK 05000 P

I An Equal Opportunity Employer

4 4 Mr. Harold R. Denton June 28, 1982 Non-outage related work will be ongoing during this time.

The above schedule extensions are necessary because of higher priority work related to torus work and scram discharge volume modifications that must be done on elevation 565 of the Reactor Building.

Modifica-tions necessary to tie in the PASF must be done on this same elevation.

will be required to complete the PASF.Present estimates indicate that 8,000 to 9,000 Very truly yours, TENNESSEE VALLEY AUTHORITY L. M. Mills, anager Subscribe Nuclear Licensing sworn before me this day of, M 1982.