LOUISIANA / 142 ORARONDE START POWE R & LiG H T/ P O BOX 6008. NEW ORLEANS. LOUIS 1ANA 70174. (504) 366 2345 u$?Ss s*vsYIO June 17, 1982 G. D. McLENDON Senior Vice President W3K82-0353 Q-3-A35.07.40 Mr. John T. Collins, Regional Administrator, Region IV l
]g))pg U. S. Nuclear Regulatory Commission
- ~,
611 Ryan Plaza Drive, Suite 1000 M22g Arlington, Texas 76012
SUBJECT:
Waterford SES Unit No. 3 3 d' Docket No. 50-382 Significant Construction Deficiency No. 40 "ITE-Gould Starter Coil Failure in Containment Cooling Fans" Fourth Interim Report
Reference:
- 1) LP&L Letter W3K82-0320 to NRC dated June 3, 1982
- 2) Telecon - L. Martin (NRC) to L. Bass (LP&L) on June 16, 1982
Dear Mr. Collins:
In reference (1) LP&L committed to submit a final report on the subject Significant Construction Deficiency on June 15, 1982.
The final review of installation documents is now in process and is expected to be completed by June 30, 1982. A final report will be submitted on or before July 12, 1982.
Very truly yours,
. h. h GDMcL/LLB/ncd
~ +g cc:
1)
Director Office of Inspection & Enforcement U. S. Nuclear Regulatory Commission Washington, D. C. 20555 2)
Director Office of Management Information and Program Control U. S. Nuclear Regulatory Commission Washington, D. C. 20555
[
F206250200 820617 PDR ADOCK 05000382 S
PDR 1