Submits Monthly Status Completion Rept for Apr 1982. Scheduled Commercial Operation Date for Unit 1 Remains Dec 1986.Unit 2 Const Abandoned Dec 1981.Const Progress Approx 48% Complete
ML20054G921
Person / Time
Site: Hope Creek PSEG icon.png
Issue date: 06/09/1982
From: Landrieu P H
Public Service Enterprise Group
To: Lester Tripp
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION I)
References
M-P82-81-06, M-P82-81-6, NUDOCS 8206220411
Download: ML20054G921 (1)


Text

-

7~

Public Service b

I Electric and Gas E

Cornpany 80 Park Plaza, Newark, NJ 07101/ 201430-7000 MAILING ADDRESS / P.O. Box 570, Newark, NJ 07101 June 9, 1982

-5 Mh.,Lowell E. Tripp '

Chief-Reactor Projects-Section 2A U.S. Regulatory Commission Division of Resident and Project Inspection Region 1 631 Park Avenue King of Prussia, Pennsylvania 19406 P

Dear Mr. Tripp:

HOPE CREEK GENERATING STATION DOCKET NO. 50-354 LICENSE NO. CPPR-120 MONTHLY STATUS COMPLETION REPORT The scheduled commercial operation date for Unit No. 1 remains at December 1986.

Unit 2 construction was abandoned in December 1981.

At the etd of April 1982 construction progress of the unit was approximately 48% complete.

Very truly yours, fM P.

R.

H. Landrieu Project Manager - Hope Creek Engineering and Construction Jh:gs M P82 81/06 f