Submits Third Progress Rept for Dismantling Plan.Fuel Will Not Be Unloaded Until Sept 1982 Due to Absence of Radiation Safety Officer & Vendor Inability to Supply Certified Shipping Containers.Shipping Instructions Requested
ML20054G886
Person / Time
Site: 05000394
Issue date: 06/17/1982
From: Adamson R
CALIFORNIA POLYTECHNIC STATE UNIV., SAN LUIS OBISPO
To: Stolz J
Office of Nuclear Reactor Regulation
References
NUDOCS 8206220383
Download: ML20054G886 (2)


Text

_ __ - _ _ _ - - - _ - - _ _ _ - _ _ _ _ - _ _ - _ - - _ - _ _ _ _ . _ - _ _

CALIFORNI A POLYTEGINIC FTATE UNI \'ERSITY SAN U~1HOit191'0.CAIK JRN!A W W/ x, t & i p W lil p g_j' =r

,-  ; Ox

+M$$p$$$gGRgregaMe<~

June 17, 1982 Director Division of Operating Reactors Office of Nuclear Reactor Regulation U.S. Nuclear Regulatory Comnission Washington, D.C. 20555 Attn: Mr. John F. Stolz, Chief, Operating Reactors Branch 44

Subject:

Docket NO. 50-394, License No. R-121 Third Progress Report for Dismantling Plan With the close of the academic year last week, and the fact that I will not be on campus on a regular basis until Septenber 18, 1982, this Progress Report will serve to keep the various parties concerned informed of our plans and schedule. At this time it would appear that we would not be able to unload fuel until Septenber of this year for several reasons.

The campus Radiation Safety Committee is now in the process of interviewing candidates for the position of Radiation Safety Officer, which we hope to have filled with the appropriate person who can help us in the dismantling procedure and shipment of spent fuel about August 1st. Another setback involves our notificatica last week that the vendor who was to supply us with certified shipping containers would not be able to supply them. I am now in the process of locating a new supplier, hopefully on the West Coast and have made several inquiries already.

I am still in need of your help in getting shipping instructions for the spent fuel once we have gotten it packaged. I would refer you to my letter of March 2,1982, addressed to Malcolm Theisen (Director, Weapons Division, DOE, Oak Ridge, Tennessee) since I have still have had no response to this letter from that office.

On June lith, I attempted to call Peter B. Erickson of your office, but was unsuccessful, since I did not have his correct phone number and would appreciate your including it in your response.

I IIE C \1.ll'ORN! \ ST\ l 1: I 'Ni\'ERHITT & C01.1.lMES 8206220383 820617 PDR ADOCK 05000394 W PDR .

Docket No. 50-394, License No. R-121 Third Progress Report for Dismantling Plan June 17, 1982 Page 2 On June 21, 1982, I will begin a temporary assignment for Pacific Gas and Electric Company at their Diablo Canyon Power Plant and do not know yet where I can be reached by telephone at that location.

Your best procedure would be to correspond by mail at this time as I will be in to the campus office several times each week to check on such matters.

Sincerely,

'k,(L1[(.0.0b aavll Robert W. Adamson, Reactor Administrator and Professor Aeronautical and Mechanical Engineering Department Office: 805/546-1115 Residence: 805/544-5957 cc: Peter B. Erickson, Operating Reactors Branch #4, USNRC R.H. Engelken, Director, Region V, UXNRC 1990 N. California Boulevard, Suite 202 Walnut Creek Plaza, Walnut Creek, CA 94596 Attn: Phil Johnson and Amelio Garcia Director for Operating Reactors Division of Licensing, USNRC Washington, D.C. 20555 Malcolm Theisen, Weapons Division, DOE P.O. Box E, Oak Ridge, TN 37830 R.L. Fisher, SRO Unit #1, Diablo Canyon Pacific Gas and Electric Company P.O. Box 56 Avila Beach, CA 93424 Bill Cromwell, Vice President Southwest Nuclear Company 7066-A Comerce Circle Pleasanton, CA 94566 John Pickering, Radiation Safety Officer University of Southern California University Park, Los Angeles, CA 90007 A.Z. Rosen, Professor, Physics Department, CPSU/SID R.G. Gordon, Head, Aero/ME Department, CPSU/SID M.E. Weber, Technician, Aero/ME Department, CPSU/ SLO