Interim Deficiency Rept Re Lack of QA Program for RCI Control Rod Drive Hangers,Initially Reported on 820510. Evaluation Underway to Determine Corrective Action to Be Taken.Next Rept Will Be Submitted by 820731
ML20054F794
Person / Time
Site: Zimmer
Issue date: 06/02/1982
From: Borgmann E
CINCINNATI GAS & ELECTRIC CO.
To: James Keppler
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III)
References
10CFR-050.55E, 10CFR-50.55E, NUDOCS 8206170334
Download: ML20054F794 (2)


Text

-

o

-=

=.

THE CINCINNATI GAS & ELECTRIC COMPANY sW ~

CINCINN ATI.OMIO 4r201 E. A. BORGM AN N stNeon vict entsiotut June 2, 1982 QA-1798 U. S. Nuclear Regulatory Ccumission Pagion III 799 It:osevelt Road Glen Ellyn, Illinois 60137 Attention: Mr. J. G. Keppler Regional Administrator RE: 1@i. H. ZIbHER NUCLEAR POWER STATION UNIT I 10CFR50.55(e) - ITDi S-3, IACK OF QA PROGPRI IVR RCI CRD HANGEPS, DOCKET NO. 50-358, CONSTRUCTION PERMIT NO. CPPR-88,. W. O.

  1. 57300, JOB E-5590, FILE NO. NIC-9, ITDi S-3 Genticmen:

'Ihis letter constitutes an interim report concerning the subject deficiency, initially reported to the Ccmnission on May 10, 1982, under the requirmrants of 10CFR50.55(e).

Catalytic Inc., a contractor at the Zimner Plant, was preparing to initiate field modifications which resulted frca a reanalysis of the Control Rod Drive (CRD) System. 'Ihis reanalysis was required by the lack of consideration of hydrodynamic transient loads in the original design. '1his particular deficiency was previously reported to the Ccmnission as Item M-32 under 10CFR50.55(e).

Catalytic discovered and subsequently notified CG&E of nonconforming conditions on the supports for the CRD piping. CU&E performed a field walkdown of approximately 10% of the installed supports and found the fab-rication and welding to be in nonempliance with the requirments of the Sargent & Lundy design specification H-2832. CG&E also reviewed the fabri-cation and installation records supplied by Reactor Controls Inc. and dis--

covered that the supports were not fabricated or installed under a Quality Assurance Program conforming to the 18 point criteria of 10CFR50 Appendix B or the requirements of Sargent & Lundy Design Specification H-2832. CG&E is currently evaluating this dei Lency and determining the necessary corrective action to be taken. she next report will be filed on or before July 31, 1982.

8206170334 820602 PDR ADOCK CS000358 S

PDR 3% h -7

f Mr. J. G. Keppler Begional Administrator June 2, 1982,QA-1798 Page 2 We trust the above will be found acceptable as an interim respcnse under 10 T R50.55(e).

t Very truly yours, 7EE CINCINNATI GAS & ELECTRIC COMPANY f'

By E. A. BOICMANN SENIOR VICE PRESIDENT FKP:cc cc: - NBC Senior Resident Inspector.