Summarizes Const Activities Scheduled for Completion Nov 1983 & May 1987 for Units 1 & 2,respectively
ML20054E110
Person / Time
Site: Perry  FirstEnergy icon.png
Issue date: 04/13/1982
From: Davidson D
CLEVELAND ELECTRIC ILLUMINATING CO.
To: Schwencer A
Office of Nuclear Reactor Regulation
References
NUDOCS 8204260146
Download: ML20054E110 (2)


Text

.

' T H ,E C'L E V E L A N D E L E C T R I C I L L U M I N AT I N G C O M P A N Y P O Box 5000 m CLEVEL AND. oHlo 44101 e TEL EPHoNE (216) 622-9800 e ILLUMINATING BLOG e 55 PUBlic SoVARE Servmg The Best Location j !ation Dalwyn R. Davidson b ect rmrsiot Nr f b y5if M ENG;NE ERING ANO CONSTRUCTION 1- ys -

h

. O," $y 51 April 13, 1982 - N,M. W

[. . ': ,79 5?

9. %.'

</

Mr. A. Schwencer /

Chief, Licensing Branch No. 2 v c/jj, /

Division of Licensing N U. S. Nuclear Regulatory Commission Washington, D. C. 20555 Perry Nuclear Power Plant Docket Nos. 50-440; 50-441 Construction Completion to Support Unit 1 Operation

Dear Mr. Schwencer:

The present schedule for completion of Perry Nuclear Power Plants Units 1 and 2 is November 1983 and May 1987. This thne interval between the completion of Units 1 and 2 will involve ongoing construction activities for Unit 2 while Unit 1 is in operation. This letter is provided to address the require-ment of 10 CFR 50.34(b)(6)(vii), for "an evaluation of the potential hazards to the structures, systems and components important to safety of operating units resulting from construction activities, as well as a description of the managerial and adminstrative controls to be used to provide assurance that the limiting conditions for operation are not exceeded as a result of construction activities at the multi-unit sites."

Major aspects of the PNPP review included physical isolation of Unit 1 from Unit 2 from both a system and security barrier standpoint. Further, the exposures of Unit 2 construction and testing personnel in varying locations were evaluated and estimated doses are provided in FSAR Section 12.4.

Specific security provisions during Unit 2 construction are discussed in Section 10 of the PNPP Security Plan. In add-ition, a comprehensive evaluation of the systems required to support Unit 1 operation was done to provide system isolation for common and cross-tied plant systems. Temporary mod-ifications are being implemented for the Emergency Closed Cooling System, Fire Protection seismic water supplies to common area hose stations, and various common components originally gQ/

designed with a Unit 2 power supply. V, Io 820426014(o

'Mr.=A. Schwencer- '

April 13, 198.6 Page 2 1

All common facilities and systems, as well as necessary portions of Unit 2 systems, that are required to support operation will be complete and operational by Unit 1 fuel load. Those -

portions not necessary for operation will be appropriately isolated'auch that they will not affect the safe operation of Unit 1.

It is our intention to incorporate a simenary of this evaluation-and a description of the administrative controls in a.sub-sequent amendment to the Final-Safety Analysis Report.

Very Truly Yours, i

Dalwyn R. Davidson System Engineering and Construction DRD: mlb cc: John Stefano, Pro, ject Manager Max Gildner, URC Resident Inspector -