Nuclear Power PLANTS-CONSTRUCTION Status Report.Data as of December 31,1981.(Yellow Book)
ML20054D287
Person / Time
Issue date: 04/30/1982
From:
NRC OFFICE OF MANAGEMENT AND PROGRAM ANALYSIS (MPA)
To:
References
NUREG-0030, NUREG-0030-V05-N04, NUREG-30, NUREG-30-V5-N4, NUDOCS 8204220533
Download: ML20054D287 (400)


Text

-

sa8 NUREG-0030 Vol. 5, No. 4 8

NUCLEAR POWER PLANTS CONSTRUCTION STATUS REPORT DATA AS OF 12/31/81 1

UNITED STATES NUCLEAR REGULATORY COMMISSION I

fa arcuy hfY

?

Available from l

HRC/GPO Sales Program 1

Superintendent of Documents Government Printing Office Washington, D.C. 20402 A year's subscription consists of 4 issues for this publication.

Single copies of this publication are available from National Technical Information Service, Springfield, VA 22161 Microfiche of single copies are available from HRC/GPO Sales Program Washington, D.C. 20555

~

=

NUREG-0030 Vol. 5, No. 4 NUCLEAR POWER PLANTS CONSTRUCTION STATUS REPORT DATA AS OF 12/31/81 l

Manuscript Completed: April 1982 Date Published: April 1982 0FFICE OF MANAGEMENT AND PROGRAM ANALYSIS U.S. NUCLEAR REGULATORY COMMISSION WASH lNGTON, D.C. 20555 l

p..

s l

AUTil0RIZATION AND CLEAR ANCE l

ON JULY 3.

1931 THE U. S. NUCLEAR REGULATORY COMMISSION REQUESTED APPROVAL FOR COLLECTION OF DATA AND PUBLICATION OF THE CONSTRUCTION STATUS REPORT G;U R EG-C C 30 )

FROM Tile OFFICE OF MANAGEMENT AND BUDGET.

BY ACTION DATED AUGUST 3, 1931, THE OFFICE OF MAtlAGEMEllT AND BUD 3ET GRA!!TED APFROVAL OF Ti!E REQUEST.

Tile FOLLOUING It; FUR:1ATION IS TO APPEAR ON THE FIRST PAGE OF Tile REPORT:

APPROVED 2Y OM3 0:iB NO. 3150-0030 EXPIRES 12-31-S2 i

I

h FOREWORD This report is compiled by the Nuclear Regulatory Commission's Office of Manancmont and Program Analysis to provide information necessary for-monitoring progress of all nuclear power plants which have Construc-

-tion' Permits.

The report includes data from utilitios sponsoring the construction, as well as frca NRC's Office of Inspection and Enforecment.

This data is used to synchroniae the licensing process with pro-dicted fuel load dates for this central Federal Government presentation of commercial reactor construction.

UPDATES FOR THIS EDITION WERE NOT RECEIVED FROM THE FOLLOWING PLANTS:

COMANCHE PEAK 1 LIMERICK 2 CCMANCHE PEAK 2 MILLSTONE 3 DIABLO CANYOH 1 SAH ONOFRE 2 DIABLO CANYON 2 SAN ONOFRE 3 FERill 2 SUMMER 1 LIMERICK 1 WOLF CREEK 1

TABLE OF CONTENTS I

SECTION 1

SUMMARY

OF FUEL LOADING CHANGES 1-001 FACILITY STATUS

SUMMARY

1-002 THRU 1-004 PLANTS AND STAGES OF CONSTRUCTION DY REGION 1-005 AVERAGE CONSTRUCTION DUPATIONS 1-006 THRU 1-012 SECTION 2 PLANT DATA / CONSTRUCTION STATUS 2-002 THRU 2-151 SECTION 3_

SCHEDULE FOR UPDATES - CALENDAR YEAR 1982 3-001 BLANK CONSTRUCTION STATUS REPCRT FORMS 3-002 THRU 3-003

E O

C)

LaJ M

C0NST RUCT ION STATUS REPORT PAGE ND:

1-001 NUCLEAR POWER PLANTS S U M t1 A R Y 0F FUEL L 0ADING CHAHGES DURING Tile PERIOD FRCri 10-01-31 TO 12-31-81, THE FOLLOWING LICENSING ACTIONS WERE AUTiiORIZED:

NO LICENSING ACTIONS WERE AUTHORIZED.

l l

THE FOLLOWING PL ANTS REPORTED ClitNGES IN THEIR ESTIt1ATED FUEL LOADING DATES l

DURING THE ABOVE REPORTIllG PERIOD:

FLD LAST FLD THIS SLIPPAGE /

f]I1Pj!p_,J M E N T )

V ELANT NAME X RJ_0D_

_LERLO D__

BELLEFONTE 2 12-00-82 09-00-84 21.00 MONTHS DIABLO CANYON 1 w

03-00-81 03-00-82 12.00 tt0NTils HARRIS 2 06-01-87 06-01-88 12.00 t10 Nills LASALLE 1 w

12-00-81 03-15-82 3.50 MONIHS PERRY 1 05-00-83 11-00-83 6.00 MONTHS SUSQUEllANNA 1 w

04-15-82 07-01-82 2.53 MONTHS SUSQUEHANNA 2 07-15-83 01-00-84 5.5 0 tiotiTils WASilltiGTON NUCLEAR 1 w

08-01-35 12-00-85 3.97 fl0HTHS l

l l

w FIRST OF A MULTI-UNIT OR A SINGLE UNIT APPLICATION.

FACIL ITY STATUS

SUMMARY

PAGE NO:

1-002 NUCLEAR POWER PLANTS DATE APPLICANT'S APPLICANT'S PIFCENT DOCKET REACTOR DESIGN IE CONSTRUCTION FLD AT CP CUCKENT CCNSTFUCTION PttNT N Af1E

.N_t)l}lEl TYPE

_J,3JL R F_ROJ STARTFD 1550 A N C_F F1 D C OTT I, F I F L

m 1.

BEAVER VALLEY 2 05000412 PWR 852 1

05-04-74 02-00-79 12-31-85 51%

2.

BELLEFONTE 1 05000438 PWR 1235 2

01-00-74 06-00-79 09-00-83 79%

3.

BELLEFONTE 2 05000439 PWR 1235 2

09-00-74 03-00-80 09-00-84 64%

4.

BRAIDWOOD 1 05000456 PWR 1920 3

08-00-75 05-00-81 04-00-85 61%

5.

BRAIDWOOD 2 05000457 PWR 1120 3

08-00-75 05-10-82 04-00-86 48%

6.

BYRON 1 05000454 PWR 1120 3

04-00-75 05-00-80 04-00-83 79%

l 7.

BYRON 2 05000455 PWR 1120 3

04-00-75 05-00-81 04-00-84 63%

8.

CALLAWAY 1 05000483 PWR 1190 3

09-03-15 06-01-81 06-01-83 78%

l 9.

CATAWBA 1 05000413 PWR ti45 2

05-16-74 12-00-78 08-19-83 80%

10.

CATAWBA 2 05000414 PWR 1145 2

05-16-74 12-00-79 02-11-85 39%

11.

CHEROKEE 1 05000491 PWR 1280 2

07-09-76 05-00-83 UNKNOWN 18%

12.

CHEROKEE 2 05000492 PWR 1280 2

07-09-76 05-00-85 UNKNOUN 00%

13.

CHEROKEE 3 05000493 PWR 1280 2

07-09-76 05-00-88 UNKNOWN 00%

14.

CLINTON 1 05000461 BWR 950 3

10-06-75 10-00-80 01-03-83 83%

15.

CLINTON 2 05000462 BWR 950 3

10-06-75 10-00-83 UNKNOWN 01%

16.

COMANCHE PEAK 1 05000445 PWR 1150 4

10-00-74 06-00-79 06-CO-83 89%

17.

COMANCHE PEAK 2 05000446 PWR 1150 4

10-17-74 06-00-81 UNKNOWN 57%

18.

DIABLO CANYOH 1 05000275 PWR 1084 5

06-14-68 04-00-72 03-00-82 99%

19.

DIABLO CANYON 2 05000323 PWR 1106 5

06-14-68 11-00-74 07-00-82 98%

20.

ENRICO FERMI 2 05000341 BWR 1093 3

05-00-69 08-00-73 11-30-82 88%

21 GRAND GULF 1 05000416 BWR 1250 2

05-03-74 03-00-79 02-01-82 95%

22.

GRAND GULF 2 05000417 BWR 1250 2

05-03-74 03-00-81 UNKNOWN 22%

23.

HARRIS 1 05000400 PWR 915 2

01-14-74 09-00-80 12-00-84 55%

24.

HARRIS 2 05000401 PWR 915 2

01-14-74 06-01-85 06-01-CS 04%

25.

HARTSVILLE A-1 05000518 BWR 1205 2

04-22-76 06-00-81 01-01-90 42%

FACIL ITY ST ATUS

SUMMARY

PAGE NO:

1-003 NUCL EAR POWER PLANTS DATE APPLICANT'S APPLICANT'S PERCENT DOCKET REACTOR DESIGN IE CONSTRUCTION FLD AT CP CURRENT CONSTRUCTION PLANT NAME EF R F R TYPE TWE REGION STARTED ISSUANCE FLD C njiP Lf,LF_

26.

HARTSVILLE A-2 05000519 EWR 1205 2

04-22-76 06-00-82 01-01-91 32%

27.

HARTSVILLE B-1 05000520 EUR 1205 2

04-22-76 12-00-81 UNKNOWN 17%

28.

HARTSVILLE B-2 050'0521 EWR 1205 2

04-22-76 12-00-82 UNKNOWN 07%

29.

HOPE CREEK 1 05000354 EWR 1067 1

03-00-76 06-00-81 06-00-86 40%

30.

LASALLE 1 05000373 EUR 1078 3

10-00-73 03-01-75 03-15-82 99%

31 LASALLE 2 05000374 BWR 1078 3

10-00-73 08-01-75 12-00-82 84%

32.

LIMERICK 1 05000352 BWR 1065 1

05-00-70 04-00-79 10-00-84 68%

33.

LIMERICK 2 05000353 BWR 1065 1

05-00-70 09-00-80 04-00-87 30%

34 MARBLE HILL 1 05000546 PWR 1130 3

08-00-77 04-00-82 06-00-86 31%

35.

MARBLE HILL 2 05000547 PWR 1130 3

12-00-77 07-00-83 06-00-87 15%

36.

MCGUIRE 2 05000370 PWR 1180 2

04-01-71 10-01-76 04-01-83 94%

37.

MIDLAND 1 05000329 PWR 492 3

03-00-73 11-00-79 12-00-83 74%

38.

MIDLAND 2 05000330 PWR 818 3

03-00-73 11-00-78 07-00-83 74%

39.

MILLSTONE 3 05000423 PWR 1159 1

05-00-74 12-01-78 12-01-85 43%

i 40.

NINE MILE POINT 2 05000410 PWR 1080 1

08-25-75 05-01-78 03-00-86 37%

l 41.

NORTH ANNA 3 05000404 PWR 907 2

07-00-72 07-00-78 04-00-89 08%

42.

PALO VERDE 1 05000528 PWR 1304 5

05-00-76 11-00-81 11-01-82 95%

43.

PALO VERDE 2 05000529 PWR 1304 5

06-00-76 11-00-83 11-00-83 75%

44.

PALO VERDE 3 05000530 PWR 1304 5

06-00-76 11-00-85 11-00-85 30%

45.

PERRY 1 05000440 BWR 1205 3

10-00-74 05-30-81 11-00-83 81%

1 46.

PERRY 2 05000441 BWR 1205 3

10-00-74 12-30-82 05-00-87 41%

47.

PHIPPS BEND 1 05000553 BWR 1220 2

10-19-77 01-00-83 01-00-93 29%

1 48.

PHIPPS BEND 2 05000554 EWR 1220 2

UNKNOWN 01-00-83 UNKNOWN 05%

49.

RIVER BEND 1 05000458 BWR 934 4

04-08-79 10-00-81 04-00-85 43%

50.

RIVER BEND 2 05000459 BWR 934 4

UNKNOWN UNKNOWN UNKNOWN 01%

FACILITY STATUS

SUMMARY

. PACE.HO:

1-004 NUCLEAR POWER PLANTS DATE APPLICANT'S APPLICANT'S PERCENT DOCKET REACTOR DESIGN IE CONSTRUCTION FLD AT CP CURRENT CONSTPliCTION PLANT NAME NUMBER TYPE MWE REGION

__ START _ED ISSUANCfm FLD Cntli'!y,J_E_

51.

SAN ONOFRE 2 05000361 PWR 1140 5

02-04-74 02-00-79 10-15-81 99%

52.

SAN ONOFRE 3 05000362 PWR 1140 5

02-07-74 05-00-80 11-01-82 87%

53.

SEABROOK 1 05000443 PWR 1198 1

07-00-76 08-01-81 11-30-83 59%

54.

SEABROOK 2 05000444 PWR 1998 1

07-00-76 10-01-83 02-28-86 11%

55.

SHOREHAM 05000322 BWR 849 1

11-00-72 03-00-77 09-00-82 88%

56.

SOUTH TEXAS 1 05000498 PWR 1250 4

09-00-75 05-01-80 UNKNOWN 45%

I 57.

SOUTH TEXAS 2 05000499 PWR 1250 4

09-00-75 10-01-81 UNKNOWN 18%

58.

ST LUCIE 2 05000389 PWR 842 2

05-02-77 05-13-83 10-28-82 81%

59.

SUMMER 1 05000395 PWR 900 2

04-00-73 10-01-77 02-00-82 98%

60.

SUSQUEHANNA 1 05000387 BWR 1052 1

11-00-73 05-01-79 07-08-82 92%

61 SUSQUEHANNA 2 05000388 BWR 1052 1

11-00-73 11-01-80 01-00-84 65%

62.

V0GTLE 1 05000424 PWR 1100 2

08-01-76 10-01-79 09-01-86 24%

63.,V0GTLE 2 05000425 PWR 1100 2

08-01-76 10-01-30 03-01-88 08%

64.

WASHINGTON NUCLEAR 1 05000460 PWR 1267 5

08-01-75 03-00-80 12-00-85 53%

65.

WASHINGTON NUCLEAR 2 05000397 EUR 1103 5

08-00-72 04-00-77 03-30-83 an%

66.

WASHINGTON NUCLEAR 3 05000508 PWR 1242 5

04-00-77 07-00-83 08-00-85 43%

67.

WASHINGTON NUCLEAR 4 05000513 PWR 1267 5

08-00-75 09-00-81 UNKNOWN 24%

68.

WASHINGTON NUCLEAR S 05000509 PWR 1242 5

04-00-77 01-00-85 UNKNOWN 03%

69.

WATERFORD 3 05000382 PWR 1151 4

11-14-74 06-00-78 10-00-82 94%

70.

WATTS BAR 1 05000390 PWR 1165 2

12-26-72 05-00-77 08-00-82 80%

71.

WATTS BAR 2 05000391 PWR 1165 2

12-26-72 11-00-76 06-00-83 60%

72.

WOLF CREEK 1 05000482 PWR 1150 4

01-24-77 10-01-82 12-16-83 80%

73.

YELLOW CREEK 1 05000566 PWR 1285 2

02-09-78 02-01-84 07-01-89' 33%

74.

YELLOW CREEK 2 05000567 PWR 1285 2

UNKNOWN UNKNCUN UNKNOWN 03%

75.

ZIMMER 1 05000358 BWR 810 3

03-03-71 01-00-77 07-00-82 97%

L

-- - - ~ -

C0NSTRUCT ION STA TUS REPOR T PAGE NO: 1-005 NUCLEAR POWER PLANTS PLAH T S BY IE REGION T'OTAL -

75 IE REGION 1 (11)

LFlEfiON 2 (27)

IE REGIGH 3

( 17 )

IE REGION 4

( 3)

LF,_ILFGI n!L)

(IR1 BEAVER VALLEY 2 LELLEF0HTE 1 BRAIDWOOD 1 COMANCilE PEAK 1 DIALLO cal (YOH 1 HOPE CREEK 1 EELLEF0 tite 2 BRAIDWOOD 2 COMAtitilE PEAK 2 DIABLO CANYON 2' LIMERICK 1 CATAUSA 1 BYRON 1 RIVER BEND 1 PALO VERDE 1 LIMERICK 2 CATAUSA 2 BYRON 2 RIVER BEND 2 PALO VET:DE 2 MILLSTONE 3 CHLROKEE 1 CALLAMAY 1 SOUTH TEXAS 1 PALO VIRDE 3 HINE MILE POINT 2 CHEROKEE 2 CLINT3N 1 SOUTH TEXAS 2 SAN 0110 IRE 2 SEABROOK 1 CHEROKEE 3 CLINIGH 2 WATERFORD 3 SAN OHOIRE 3 SEACR03K 2 GRAND GULF 1 EMRICO FERMI 2 WOLF CREEK 1 WASilINGT014 NUCLEAR 1 SHOREHAM GRAND GULF 2 LASALLE 1 WASilINGTON NUCLEAR 2 SUSQUEHANNA t HARRIS 1 LASALLE 2 UASilINGION NUCLEAR 3 SUSQUEllAHliA 2 HARRIS 2 (1ARBLE HILL 1 WASHINGTON HUCLEAR 4 HARTSVILLE A-1 MARBLE ilILL 2 WASHINGTON liUCLEAR 5 HARTSVILLE A-2 HIDLAND 1 HARTSVILLE B-1 f11DLAND 2 IIARTSVILLE B-2 PERRY 1 t:CGUIRE 2 PERRY 2 NORTH AN!iA 3 ZIi: PIER 1 PilIPPS LEHD 1 PHIPPS EEND 2.

ST LUCIE 2 l

SU'.MER 1 V0GTLE 1 l

V0GTLE 2 WATTS BAR 1 WATTS Bt.R 2 YELLOW CREEK 1 YELLOW CREEK 2

~

l STAGES 0F PLANT C0NSTRUCT ION BY IE REGION RJ_G T_0 H 0% TO 24%

PS% TO 49%

10 % TG 74%

75% TO 99%

T 01A l, 1

1 4

4 2

11 2

12 5

3 7

27 3

2 3

4 3

17 4

2 2

1 3

8 5

__R

_2 1

7 p

TOTAL 19 16 13 27 75

A VERAGE C0NST RUCTION DURA T IONS PAGE NO:

1-006 NUCL EAR POWER PLANTS PRIOR TO 1970 - ACTUAL DURATIONS START FLD FERCENT TYPE DESICH CONSTRUCTION dd PLANT NAME CONSTRUCTION f_S T I t: ATE C 0t1P_L_FIC R E A_C_T 0 R I:U F_

DURATION DRESDEN 1 w

05-01-56 09-23-59C 100%

DUR 200 40 9 YANKEE-ROWE 1 w

03-01-58 07-09-60C 100%

PUR 175 23.3 INDIAN POINT 1 12-01-56 03-26-62C 100%

PUP 265 63.3 NUMLOLDT BAY d

11-01-60 03-2a-62C 100%

Bui:

65 21.9 BIG ROCK POINT 1 W

03-01-60 03-30-62C 100%

EUR 72 30.0 SAN ONOFRE 1 d

07-01-64 03-27-67C 100%

PUR 436 32.9 HADDAM NECK d

04-01-64 05-30-67C 100%

PUR 532 39.0 l

LA CROSSE 06-01-62 07-03-67C 100%

DUR 50 61.1

~

OYSTER CREEK 1 w

09-01-63 04-09-6tc 100%

EUR 650 67.3 NINE MILE POINT 1 w

07-01-63 03-22-60C 100%

CUR 620 73.7 GINNA 04-01-66 09-19-69C 100%

PUR 470 41.6 DRESDEN 2 w

09-01-65 12-22-69C 100%

BUR 794 51.7 AVE: 365 AVE:

46.0 CALENDAR YEAR 1970 - ACTUAL DURATIONS START FLD PERCENT TYPE DESIGN CONSTRUCTION dw PLANT NAME CfdLST RitCT Lol{

f_S1Ilf A TE rnria Elf REACTOR f"J F

_DURATTON ROBINSON 2 02-01-67 07-31-70C 100%

PWR 700 42.0 MONTICELLO w

09-01-66 09-08-70C 100%

BUR 545 43.2 POINT BEACH 1 01-01-67

'0-05-70C 100%

FUR 497 45.1 MILLSTONE t 03-01-66 10-co-79C 10r%

BUR 660 55.2 AVE: 601 AVE:

47.6 j

CALENDAR YEAR 1971 - ACTUAL DURATIONS START FLD PERCENT TYPE DESIGN CONSTRUCTION **

PLANT NAME

$_0NS T P UC T IOfj f_S_T_J r t A T E COMPLETE PEACTOR MUE DUPATION DRESDEN 3 w

03-01-66 01-12-71C 100%

EUR 794 58.4 PALISADES W

03-01-68 03-24-71C 100%

PUR 205 31.8 CUAD CITIES 1 w

10-01-66 10-01-71C 100%

LUR 789 60.0 INDTAN POINT 2 w

01-01-66 10-19-71C 100%

rWR 373 69.6 POINT BEACN 2 01-01-67 11-16-71C 100%

PWR 497 58.5 AVE: 752 AVE:

55.7 THE DURATION FCR NUCLEAR PCUER PLAHi CUNSIRUCTION IS DEFINED AS THE ELAPSED TITE FROM ACTUAL GROUND BREAKING UNTIL THE PLANT IS CONSIDERED READY FOR HOTf:

FUEL LOADING.

THIS DOES NOT INCLUDE AN AVERAGE W

FIRST OF A MULTI UNIT OR A SINGLE UNIT APPLICATION.

DURATION OF SIX (6) MONTHS FOR POWER ASCENSION TO aw IN CALENDAR fiONTHS.

COMT:ERCIAL OPERATION.

I

A VERAGE C0NSTRUCT I CH DURA T IONS PAGE NO:

1-007 NUCLEAR POWER PL AN TS CALENDAR YEAR 1972 - ACTUAL DURATIONS START FL D PERCENT TYPE DESIGN CONSTRUCTION

  • W PLANT NAME CONSTPUCTION ESTIM EE C ortP L_FE REACTOR IMI;_

D'lRATLn!4_

w VERMONT YANKEE 1 w

12-12-67 03-21-72C 100%

SUR 514 51.3 QUAD CITIES 2 10-01-66 03-31-72C 100%

DUR 789 66.0 SURRY I W

12-01-66 05-25-72C 103%

FUR 780 65.8 PILCRIM 1 02-01-67 06-08-72C 100%

EUR 655 64.2 TURKEY POINT 3 01-08-67 07-19-72C 100%

PUR 693 66.6 MAINE YANKEE 06-01-68 09-15-72C 100%

FW1 825 51.5 AVE: 711 AVE:

60.9 CALENDAR YEAR 1973 - ACTUAL DURATIONS START FLD PERCENT TYPE DESIGN CONSTRUCTION ew PLANT NAME C O N S_T_Rij C T IO N E_1T_I t. lit _F, C nf tP L QE RFACIOR TNF Dijpa r f 0N SURRY 2 12-01-66 01-29-73C 100%

PUR 780 73.9 OCONEE 1 03-01-67 02-06-73C 100%

PMR 837 71.2 ZION 1 W

04-01-68 04-06-73C 100%

PWR 1040 60.2 TURKEY POINT 4 01-01-67 04-10-73C 100%

PUR 693 75.3 FCRT CALHOUN 1 W

02-01-68 05-23-73C 100%

PUR 470 63.7 BRGWNS FERRY 1 d

09-01-66 06-26-73C 100%

EUR 1065 81.8 PEACH BOTTOM 2 w

02-01-67 08-08-73C 100%

EUR 1065.

78.2 PRAIRIE ISLAND 1 w

06-01-60 08-09-73C 100%

PUR 530 62.3 OCONEE 2 03-01-67 10-06-73C 100%

PUR 087 71.2 1

ZION 2 04-01-68 11-14-73C 100%

PUR 1040 67.4 FORT ST VRAIN w

05-01-68 12-21-73C 100%

NTCR 330 67.7 KEWAUNEE w

12-01-67 12 7 3 C 100%

PWR 535 72.7 i

AVE: 778 AVE:

71.1 l

_ _ _.. _ _ _ _ - -. _. _. _ _. _ _. - - - - _. _ - _ _ _ _ _ _ _ _ _ _ _ _ - _ _ _ _ ~ _ - -

Ili 3

0 0

1 O

N E

C A

u d

W P

d d

d N

N N

O O

O I:

IN IN 4

TO TO TO tT.

UT UT 3

. /

CI 0514409 CI 67679060255899 1

CI 074 Rt 11553908149762 2

RA 983 L

RA 0403247 4

TR 74769887766676 7

TR 669 7

TR 8810079 5

SU SU Sh 111 ND ND ND_

O O

O C

E C

E C

E V

V V

A A

A m

N N

N G

G G

IE 33905575731401 1

IF 005 8

IF 2250515 0

73156684712532 4

SN 736 8

S!

Et 5065422 0

SU 8800886 9

S Ef 7588008379805C 8

EI 819 9

DJ 11 D

1 D

11 1

N O

E E

E R

V R

V R

V I

O A

O A

O A

ET ET ET T

PC PC PC S

YA RRRRRRRRR22R2R S YA RRR S

YA RRRR2RR A S N

TF UNUUUUuUUUMUUW N

TF UWU N

TE UUUUUUU O

R ECPPBErPEFLPFL O

R PPP O

P PPLPILP R

T I

I I

T T

T U N A

A A

R g

(_

R E

R Tl_%%4%%%%

D A U

TT U

T T_

U D NE D

NE D

NE L

EL 00000000000000 EL 000 EL 0000000 L

CP 00000000000000 L

CP 000 L

CP 0000000 111111' i

R 'C 11111111111111 A

Rt 111 A

N P A

RM U E0 U Ef U

E O

T P C.

T PS T

PC C

C C

I R

A A

A CCCCCCCCCCCCCC CCC CC0CCCC i

T E

E 44444444444444 E 555 f

6666666 T

77777777777777 T

777 T

7777777 7

Lt 82918291667597 7

Lr 1

t 6

DA C W 4

DA 5

DA1 112 7

L:

0123312 2122013011222 9

Fi 021 9

FI 3001102 U O 9

Fi 1

1 T

1 T

1 T

R P S

12456777880002 S

812 S

1378391 R

E 00000000001111 R

E 011 R

E 0000001 T

A A

A E

E E

S R Y

Y Y

N N

N N A R

O R

O R

O A

I 80886778399939 A

I 907 A

I 9968808 0 E D

T 67666666666666 D

T 676 D

T 6666676 N

TC N

TC N

TC 11111111111111 E

RU 111 E

RU 1500005 C

L E

RU L

AP 00000000000000 L

iR 000 L

A R_

0100002 T1 291 C

A TT A

TT A

C SS 29129212941360 C SS 130 C

SS 6

279 E U N

00010010000001 N

101 N

0000000 O

O O

G N C

C C

A wwwM wwwww w

www wwww w

R E

1 V

D A

N 1

2 2

E A

E E

1 3

1 3 S M

N L

23 S D

M 3

t A

O S

F 1

N A

A Y

F R

N IDI YM F

A N

T N

E Y F

E TL RO I

OK L2 2 N L

R I1V T

AOE1RT L

CC S

T I

T L1R L

I N

TNL ET C

EI IK N

E O N

A E

CKR A

SRISFO3 SR C

A N

P A

VEF C

L AMA B

T1 T

EI L

O L

I 1TIL P

R SS ER OA1IW P

TNN P

RCS RWA EEENNHEEHHP RS SAA EUNMEST PNEAWCNVCCZKIN LJI VLWEVNS OAPKCAOLTNTCAU LOD A

OLLUY OUHRRECAAAIORR IRN ETRAARR CDTABPDCHRFCPB MTI BSBSCEC lllll l

AV ERAGE C0NSTRUCT ION DURA T IONS PAGE NO:

1-009 NUCLEAR P O IJ E R PL ANTS CALENDAR YEt.R 1977 - ACTUAL DURATIUNS START FLD PERCENT TYPE CESIGN CONSTRUCTION dd PLANT NAME CONSTRNCTIOJ]

f.S T il1 A,_i_E r_njjP_1 f E REACTOP f:'!E DNATTON DAVIS-BESSE 1 w

09-10-70 04-18-77C 100%

FUR 906 79.3 FARLEY t w

10-00-70 C6-25-77C 100%

Pl!R 0?9 6 0. r.

NORTH ANNA 1 d

12-08-69 10-31-77C 100%

PU7 907 94.8 COOK 2 03-25-69 12-21-77C 100%

PUR 1100 104.9 AVE: 936 AVE:

90.0 CALENDAR YEAR 1978 - ACTUAL DURATIONS START FLD PERCElli TYPE DESIGN CONSTRUCTION ew PLANT NAME C ONS T r? UCT T O N FST If1 A T_(

Cr@lE1F, RfAC103 F L!F Dl!R P. T I O N THREE MILE ISLAND 2 d

02-01-69 01-01-78C 100%

PWR 906 107.0 HATCH 2 W

09-01-63 05-01-7tC 100%

r>! 'R 784 116.0 ARKANSAS 2 d

05-15-71 06-19-7CC 100%

PWR 912 85.1 AVE: 267 AVE: 102.7 CALENDAR YEAR 1979 - ACTUAL DUR A T I(;NS I

S T t.R T FLD PERCENT TYPE DESICl4 CONSTPUCTION **

PLANT NAME CONSTRUCTION f S T i t1 A T E C0riPlli.E RfACTOR lit!F l'.N M if0H NO PLANTS LOADED FUEL DURING CALENDt.R YEAR 1979.

CALENDAR YEAR 1580 - ACTUAL DURATIONS START FLD PERCENT TYPE DESIGN CONSTRUCTICH ed PLANT NAME

[0NSTRUCTION ESTir1 ATE

_CCf;PI EE PEACT07 f t'!L Dif P t. T T ON SEQUOYAH 1 05-05-69 02-29-20C 100%

PUR 1123 129.3 NORTH ANNA 2 12-08-69 G4-11-30C 100%

Tl:2 907 124. I SALEf1 2 01-01-60 04-10-30C 100%

r t:*t 1115 147.6 FARLEY 2 10-00-70 10-00-0CC 100%

FWR 62) 120.0 i

l l

AVE: 995 AVE: 130.4 CALENDAR YEAR 1981 - ACTUAL DURATIONS START FLD PERCLNT TYPE DESIGN CONSTRUCTION ew PLANT NAME C a t!S T Rl!C T I_0 N FST Ti; A T F C0f:"lFTE RFACTOR I"JE DUR?.TTCH MCGUIRE 1 04-01-71 01-00-Olc 100%

Pl!R 1100 117.0 SEQUC(AH 2 05-05-69 07-00-Olc 100%

Pl!S t i r.a 144.0 SAN ONCFRE 2 02-04-74 10-15-A1 99%

PUR 1140 92.4 AVE: 1156 AVE: 113.4

{m._

AV ERAGE C0NSTRUCT ION DURAT IONS PAGE NO 1-010 NUCLEAR POWER PLANTS CALENDAR YEAR 1982 - PROJECTED DURATIONS START FLD PERCENT TYPE DESIGN CONSTRUCTION **

P L t.NT N M1E CONSTRUCTION ESTIMATE CollPJ E_T_E REACTOR E F;__

DtlR A TJ ON SUMMER 1 w

04-00-73 02-00-82 98%

PWR 900 106.0 GRAND CULF 1 d

05-03-74 02-01-82 95%

CWR 1250 92.9 DIABLO CANYON 1 m

06-14-68 03-00-82 99%

PWR 1084 164.5 LASALLE 1 w

10-00-73 03-15-82C 100%

EUR 1078 101.5 DIABLO CANYON 2 06-14-68 07-00-02 98%

FWR 1106 168.5 ZIM1ER 1 03-00-71 07-00-32 97%

BUR 813 136.0 SUSQUEHANNA 1 11-00-73 07-01-82 92%

BUR 1052 104.0 WATTS BAR 1 12-26-72 08-00-82 80%

PWR 1165 115.1 SHCREHAf1 d

11-00-72 09-00-82 88%

BWR 8 ~, 9 118.0 WATERFORD 3 d

11-14-74 10-00-82 94%

PWR 1151 94.5 ST LUCIE 2 05-02-77 10-28-82 81%

PWR 842 65.9 SAN ONOFRE 3 02-07-74 11-01-82 87%

PWR 1140 104.8 PALO VERDE 1 a

05-00-76 11-01-82 95%

PWR 1504 78.0 ENRICO FERMI 2 d

05-00-69 11-30-82 88%

CWR 1093 16 3.0 LASALLE 2 10-00-73 12-00-82 84%

LWR 1078 110.0 AVE: 1060 AVE: 114.8 CALENDAR YEAR 1983 - PROJECTED DURATIONS START FLD PERCENT TYPE DESIGN CCHSTRUCTION WW

_() ij A TJ_QL J

PLANT NAME CO N S T R U_C,IJ 0JJ ESTIMATE C_011P_1_F;T E REACTOR

_11QF CLINTON f M

10-06-75 01-03-83 83%

BUR 950 86.9 WASHINGTON NUCLEAR 2 w

08-00-72 03-30-83 88%

bur 1103 128.0 BYRON 1 w

04-00-75 04-00-83 79%

PUR 1120 96.0 f*CGUIRE 2 04-01-71 04-01-83 94%

PUR 1180 144,0 WATTS BAR 2 12-26-72 06-00-83 60%

PUR 1165 125.1 COMANCHE PEAK 1 W

10-00-74 06-00-83 89%

PWR 1150 104.0 CALLAWAY 1 W

09-03-75 06-01-83 78%

PUR 1150 92.9 MIDLAND 2 w

03-00-73 07-00-83 74%

PWR 818 124.0 CATAWDA I N

05-16-74 08-19-83 8C%

PUR 1145 111.1 BELLEFONTE 1 09-00-74 09-00-83 79%

PWR 1235 108.0 PERRY 1 W

10-00-74 11-00-83 81%

BWR 1205 109.0 PALO VERDE 2 06-00-76 11-00-83 75%

PWR 1304 89.0 SEAER00K 1 07-00-76 11-30-83 59%

PWR 1198 89.0 MIDLAND 1 03-00-73 12-00-83 74%

PWR 492 129.0 WOLF CREEK 1 01-24-77 12-16-83 80%

PWR 1150 82.7 AVE: 1091 AVE: 107.9

AVERAGE C0N5TRUCT ION DURAT IONS PAGE NO:

1-011 NUCLEAR POWER PLANTS CALENDAR YEAR 1984 - PROJECTED DURATIONS START FLD PERCENT TYPE DESIGN CONSTRUCTION dW PLANT HAME CONSTRilCTION ESTIMATE COMP L E_T.E REA_CTOR l'U F._

DURATIOP j

SUSQUEHANNA 2 11-00-73 01-00-84 65%

BWR 1052 122.0 BYRON 2 04-00-75 04-00-84 63%

PWR 1120 108.0 BELLEFCNTE 2 09-00-74 09-00-84 64%

PUR 1235 120.0 LIMERICK 1 w

05-00-70 10-00-34 68%

LWR 1065 173.0 HARRIS 1 w

01-14-74 12-00-84 55%

FWR 915 130.5 l

AVE: 1077 AVE: 130.7 CALENDAR YEAR 1985 - PROJECTED DURATIONS START FLD PERCENT TYPE DESIGN CONSTRUCTION wd PLANT NAME g)NSTRUCTIDH FSTIMATE COMPtJ_TE

,PfACTOR f;UE DilR A T LO N___

CATAWBA 2 05-16-74 02-11-85 39%

PWR 1145 128.8 BRAIDWOOD 1 W

08-00-75 04-00-85 31%

PWR 1120 116.0 RIVER BEND 1 W

04-08-79 04-00-85 43%

BWR 934 71.7 WASHINGTCN NUCLEAR 3 w

04-00-77 08-00-85 43%

PWR 1242 100.0 PALO VERDE 3 96-00-76 11-00-85 30%

PlJR 1304 113.0 WASHINGTON NUCLEAR 1 M

08-01-75 12-00-85 53%

PWR 1267 124.0 f1ILLSTONE 3 05-00-74 12-01-85 43%

PWR 1159 139.0 BEAVER VALLEY 2 05-04-74 12-31-85 51%

PWR 852 139.9 AVE: 1123 AVE: 116.6 CALENDAR YEAR 1986 - PROJECTED DURATIONS START FLD PERCENT TYPE DESIGN CONSTRUCTION du PLANT NAME CONSTRUCTION FST It1 A T E C or1P Lf,,11 REACTOR

_1" ! F_

__ DURATION SEABROOK 2 07-00-76 02-28-86 11%

PWR 1198 115.9 NINE MILE POINT 2 w

08-25-75 03-00-36 37%

CWR 1000 126.2 BRAIDWOOD 2 08-00-75 04-00-86 48%

PWR 1120 12L.0 MARBLE HILL 1 w

08-00-77 06-00-86 31%

PWR 1130 106.0 HOPE CREEK 1 03-00-76 06-00-86 40%

BWR 1067 123.0 V0GTLE 1 w

08-01-76 09-01-86 24%

PWR 1100 121.0 AVE: 1116 AVE: 120.0

2 A

AVERAGE C0NSTRUCTION DURATIONS.

PAGE N0s 1-012

.N U C L'E A R P0WER PLAHTS CALENDAR YEAR 1987 - PROJECTED DURATIONS START FLD PERCENT TYPE DESIGN CONSTRUCTION dd

.. PLANT HAML p_0yS T RllCT (DJ LST IJJ AT_R f0tjIiETfE RfA_QJ_02

_tjilE___.

_DjlRA_T10]J_

LIttERICK 2.

05-00-70 C4-00-87 30%

BUR 1065 203.0 PERRY 2 10-00-74 05-00-87 41%

BUR 1205 151.0 MARDLE HILL 2 12-00-77 04-00-87 15%

PUR 1830 114.G AVE: 1133 AVE: 156.0 CALENDAR YEAR 1988 - PROJECTED DURATIONS START FLD PERCENT TYPE DESIGN CONSTRUCTION Md

- PL At T NAJjf CONSTRilCTJ08 LSlJJ1 A_T E LOUP _L_(T_[

EL&C_T 03

_JJ!jF.

J U RTJ_0N___

VOCTLE 2 00-01-76 03-01-83 08%

PUR 1100 139.0 llARRIS 2 01-14-74 06-01-83 04%

PWR 915 172.6 AVE: 1008 AVE: 155.8 CALENDAR YEAR 1989 - PROJECTFD DURATIONS START FLD PERCENT TYPE DESIGH C0tiSTRUCTInti ww PLAtti NAM _E COJMJRQCJ_I_Off

[ST_Itt_A_T_F, G0JJPLffE EfFAC_TJ13 ft!,!E bilRATJJ1 L I

.HORTH ANNA 3 07-00-72 04-00-89 08%

PWR 907 201.0

. YELLOW CREEK 1 W

02-09-78 07-01-89 33%

PWR 1285 136.7 AVE: 1096 AVE: 16A.9 CALENDAR YEARS'1990 THRU 1999 - PROJECTED DURATIONS START FLD PERCENT TYPE DESIGN CONSTRUCTION dW Pt. ANT fi.Atj,F, CONST Rij_QlT_0H fSTItJ E E CuitP L ETE REACTOR tipf_

JJLR A T ION HARTSVILLE A-1 w

04-22-76 01-01-90 42%

EUR 1205 164.3 HARTSVILLE A-2 04-22-76 01-01-11 32%

EUR 1205 176. 3 PHIPPS BEND 1

.M 10-19-77 01-00-93 29%

LUR 1220

.182.4 AVE: 1210 AVE: 174.3 s--

.. g

l N

Z O

t,,3 LaJ M

t h.

...-..i.......-..i-.

C0NSTRUCTION STATUS REP 0RT PAGE NO: 2-002 BEAVER VALLEY 2 NUCLEAR POWER PLANTS STATUS AS OF:

12-31-81 PL ANT CHARACTER I S T I C 5:

KEY PERS0HH E L:

DOCKET NO:

05000412 CORPORATE CONTACT:

E. J. WOOLEVER, VICE PRESIDENT CP HO & DATE ISSUED: CPPR-105/ 05-03-74 CP EXPIRATION DATE:

02-01-80 CORPORATE ADDRESS:

436 SIXTH AVENUE PITTSBURGH, PENNSYLVAHIA 15219 APPLICANT:

DUQUESHE LIGHT PLANT LOCATION:

5 MI E OF E.

LIVERPOOL, OH CORPORATE PHONE HO:

(412) 471-4300, EXT. 6430 IE REGION:

1 AE:

STONE & WEBSTER NSSS:

WESTIHGHOUSE CONSTRUCTOR:

STONE & WEBSTER HRC LPM:

E. DOOLITTLE IE PROJECT INSPECTOR:

REACTOR TYPE:

PWR DER (MWE):

0852 IE RESIDENT INSPECTCR:

GLENH A. WALTON IN5PECT ION S T A T U S:

FUEL L0AD DATE CHANGES TIME PERIOD AS R EPQRTED BY UTIL I T Y:

OCT, 1981 - DEC, 1981 REPORT HEW REASON FOR CHANGE REPORT BEG DATE END DATE DATE SCHEDULE REPORTED BY UTILITY NUMBf8 0F INSP.

OF INSP.

09-27-74 02-00-81 FINANCING PROBLEMS.

81-08 10-01-81 11-30-81 04-01-76 08-00-81 NO REASON GIVEN BY THE UTILITY.

81-09 12-01-81 12-31-81 07-14-76 12-00-81 SITE SOIL FOUNDATION PROBLEMS.

09-13-78 10-00-82 NO REASON GIVEN BY THE UTILITY.

11-15-78 12-00-83 FINANCIAL CONSIDERATIONS AND REDUCED LOAD FORECASTS.

Inspection Reports are available at local PDRs.

06-19-80 12-00-85 REDUCTION IN LEVEL OF CONSTRUCTICH ACTI'!ITY DUE TO FINANCI AL CONSIDERATIONS.

L0 CAL PUBL IC D0CUMENT R 0 0 M:

B. F. JONES MEMORIAL LIBRARY 663 FRAHKLIN AVENUE ALIQUIPPA, PENNSYLVANIA 15001

C0NSTRUC TION STATUS REP 0RT PAGE NO: 2-003 BEAVER VALLEY 2 NUCLEAR POWER PLANTS STATUS AS OF:

12-31-81 C0N$TRUCTION

$ T A T U 5:

APPLICANT'S CURRENT ESTIMATED FUEL LOADING DATE:

12-31 *5 APPLICANTS CONSTRUCTION COMPLETION ESTIMATE AS APPLICANT'S PREVIOUS ESTIMATED FUEL LOADING DATE:

12-31-83 DEFIHED IN CP: (EARLIEST)

AP'LICANT'S ESTIMATED FUEL LOADING DATE AT CP ISSUANCE:

02-00-79 (LATEST) 12-31-84 Ah 4.ICANT'S CURRENT ESTIMATED COMMERCIAL OPERATION DATE: 05-31-86 CURRENT 9STIMATED PERCENT CONSTRUCTION COMPLETE: 51%

COMMEN'S REGAkDING CURRENT CONSTRUCTIDH STATUS: ST ATl'S AS OF 03-01-82.

ESTIMATED ACTUAL ESTIMATED ACTUAL ESTIMATED START START C O M P t,f_T_I.C N

,C_OJPJ QM LCOMPlFTE MOBILIZE AND PREPARE SITE:

05-04-74 05-04-74 07-31-74 07-31-74 100%

PLACE STRUCTURAL CONCRETE:

11-22-76 11-22-76 09-03-84 85%

INSTALL REACTOR PRESSURE VESSEL:

11-30-81 11-16-81 03-25-85 6%

INSTALL LARGE BORE PROCESS PIPE:

06-12-78 06-12-78 05-01-84 58%

INSTALL LARGE BORE PIPE HANGERS, RESTRAINTS AND SNUBSERS:

07-17-78 07-17-78 05-01'-84 43%

INSTALL SMALL BORE PIPE:

12-01-81 01-04-82 04-18-85 4%

It: STALL CABLE TRAY:

03-28-77 03-28-77 04-18-83 76%

INSTALL EXPOSED METAL CONDUIT:

03-13-78 03-13-78 06-03-85 40%

INSTALL POWER, CONTROL, INSTRUMENTATION AND SECURITY CABLE:

06-22-81 06-22-81 04-22-85 4%

INSTALL ELECTRICAL TERMINATIONS:

03-08-82 06-24-85 0%

CONDUCT REACTOR COLD HYDROSTATIC TEST:

01-28-85 03-25-85 c%

CONDUCT HOT FUNCTIONAL TEST:

04-01-85 09-09-85 0%

CCNDUCT PREOP AND ACCEPTANCE TESTS NECESSARY FOR FUEL LOAD:

12-12-85 12-31-85 0%

C0NSTRUCTION STATUS REPQRT PAGE NO: 2-004 BELLEFONTE 1 NUCLEAR POWER PLANTS STATUS AS OF:

12-31-81 PLA NT C H A R A C T E R I S T I C S:

KEY P E R S 0 N N E L:

DOCKET NO:

05000438 CORPORATE CONTACT:

G.

KIMMONS, MANAGER 0FFICE OF ENG. DESIGN 8 CONST.

CP NO. 8 DATE ISSUED:

CPPR-122/ 12-24-74 CP EXPIRATION DATE:

03-01-82 CORPORATE ADDRESS:

400 COMMERCE AVENUE KNOXVILLE, TENNESSEE 37902 APPLICANT:

TENNESSEE VALLEY AUTHORITY PLANT LOCATION:

6 MI NE OF SCOTTSBORD, ALA CORPORATE PHONE NO:

(615) 632-2911 IE REGION:

2 AE:

TENNESSEE VALLEY AUTHORITY NSSS:

CABCOCK & WILCOX CONSTRUCTOR:

TENNESSEE VALLEY AUTHORITY NRC LPM:

R.

HERNAN IE PROJECT INSPECTOR:

R.

V.

CRLENJAK REACTOR TYPE:

PWR IE RESIDENT INSPECTOR:

J. WILCOX DER (MWE):

1235 INSPECTION S T A T U S:

FUEL L0A D DATE CHANGES TIME PERIOD A S REPOR T ED BY UT IL I T Y:

OCT. 1981 - DEC. 1981 REPORT NEW REASON FOR CHANGE REPORT BEG DATE END DATE DATE SCHEDULE REPORTED BY UTILITY NyMBg8 0F INSP.

OF INSP.

04-11-75 12-00-79 NO REASON NOTED.

8126 08-31-81 10-01-81 09-06-78 03-00-81 NO REASON NOTED.

8127 10-13-81 10-16-81 08-16-79 09-00-82 NO REASON NOTED.

8128 10-19-81 10-23-81 09-10-80 03-00-83 NO REASON NOTED.

8129 10-01-81 10-31-81 12-01-81 09-00-83 NO REASON NOTED.

8130 11-17-81 11-25-81 8131 11-01-81 11-30-81 8132 12-08-81 12-11-81 8133 12-01-81 12-31-81 INSPECTION REPORTS ARE AVAILABLE AT LOCAL PDR'S.

L0 CAL PUBL IC D0CUMENT R 0 0 M:

SCOTTSBORD PUBLIC LIBRARY 1002 SOUTN BROAD STREET SCOTTSBORO, ALABAMA 35768

C0NSTRUCTION STATUS REP 0RT PAGE NO: 2-005 BELLEFONTE I NUCL EAR POWER PLANTS STATUS AS OF:

12-31-81 C0NST RUCT ION S T A T U S:

APPLICANT'S CURRENT ESTIMATED FUEL LOADING DATE:

09-00-83 APPLICANTS CONSTRUCTION COMPLETION ESTIMATE AS APPLICANT'S PREVIOUS ESTIMATED FUEL LOADING DATE:

03-00-83 DEFINED IN CP: (EARLIEST) 06-01-79 APPLICANT'S ESTIMATED FUEL LOADING DATE AT CP ISSUANCE:

06-00-79 (LATEST) 12-01-79 APPLICANT'S CURRENT ESTIMATED COMMERCIAL OPERATION DATE: 08-00-84 CURRENT ESTIMATED PERCENT CONSTRUCTION COMPLETE: 79%

COMMENTS REGARDING CURRENT CONSTRUCTION STATUS:

ESTIMATED ACTUAL ESTIMATED ACTUAL ESTIMATED START LTART COMPLETION COMPLETION Y COMPLETE MOBILIZE AND PREPARE SITE:

09-00-74 07-00-75 100%

PLACE STRUCTURAL CONCRETE:

06-00-75 10-00-75 100%

INSTALL REACTOR PRESSURE VESSEL:

08-00-76 11-00-76 100%

INSTALL LARGE BORE PROCESS PIPE:

10-00-75 01-00-83 97%

INSTALL LARGE BORE PIPE HANGERS, RESTRAINTS AND SNUBBERS:

05-00-77 01-00-83 77%

INSTALL SMALL BORE PIPE:

01-00-76 01-00-83 86%

INSTALL CABLE TRAY:

02-00-77 07-00-82 99%

INSTALL EXPOSED METAL CONDUIT:

04-00-75 07-00-82 93%

INSTALL POWER, CONTROL, INSTRUMENTATION AND SECURITY CABLE:

11-00-77 01-00-83 73%

INSTALL ELECTRICAL TERMINATIONS:

03-00-78 01-00-83 65%

CONDUCT REACTOR COLD HYDROSTATIC TEST:

12-00-82 12-0C-82 0%

CONDUCT HOT FUNCTIONAL TEST:

01-00-83 04-00-83 0%

CONDUCT PRECP AND ACCEPTANCE TESTS NECESSARY FOR FUEL LOAD:

02-00-82 09-00-83 0%

4

C0NSTRUCTION STATUS REPORT

. PAGE NO: 2-006-EELLEFONTE 2 HUCLEAR P0WER P-LANTS STATUS AS OF 12-31-81 j

PLANT CHARACTERI5TICSt KEY PERS0NNELa DOCKET NO:

05000439 CORPORATE CONTACT:

G. KIMMONS, MANAGER CP NO. 8 DATE ISSUED: CPPR-123/ 12-24-74 0FFICE OF ENG. DESIGN 3 CONST.

CP EXPIRATIDH DATE:

12-01-83 CORPORATE ADDRESS:

400 COMMERCE AVENUE APPLICANT:

TENNESSEE VALLEY AUTHORITY KNOXVILLE, TENNESSEE 37902 PLANT LOCATION:

6 MI NE OF SCOTTSBORD, ALA IE REGION:

2 CORPORATE PHONE NO:

(615) 632-2911 AE TENNESSEE VALLEY AUTHORITY NS$$8 BABCOCK & WILCOX CONSTRUCTOR:

TENNESSEE VALLEY AUTHORITY NRC LPM:

R. HERNAN REACTOR TYPE:

PWR IE PROJECT INSPECTOR:

R. V. CRLENJAK DER (MWE):

1235 IE RESIDENT INSPECTOR:

J. WILCOX IN5PECTION S T A T U 5:

FUEL L0AD DATE CHANGES TIME PERIOD AS REPORTED 8Y U T I L I T Y:

OCT, 1981 - DEC. 1981 REPORT NEW REASON FOR CHANGE REPORT BEG DATE END DATE DATE SCHEDULE REPORTED BY UTILITY HUMBER OF INSP.

OF INSP.

04-11-75 12-00-79 HO REASON HOTED.

8126 08-31-81 10-01-81 09-06-78 03-00-81 NO REASON NOTED.

8127 10-13-81 10-16-81 08-16-79 09-00-82 NO REASON NOTED.

8128 10-19-81 10-23-81 09-10-80 12-00-83 NO REASON NOTED.

8129 10-01-81 10-31-81 01-20-82 09-00-84 NO REASON NOTED.

8130 11-17-81 11-25-81 8132 12-08-81 12-11-81 8133 12-01-81 12-31-81 INSPECTION REPORTS ARE AVAILABLE AT LOCAL PDR'S.

~

L'O C A L PUBLIC D0CUMENT R 0 0 Mr i

SCOTTSBORO PUBLIC LIBRARY 1002 SOUTH BROAD STREET SCOTTSBORD, ALABAMA 35768

??

e 4

^

?.

-4 C0NSTRUCTION STATUS REP 0RT PAGE ND: 2-007

->+

h BELLEFONTE 2 NUCLEAR POWER PLAHT$

STATUS AS OF:

12-31-81 C0NSTRUCT ION S T A T U 5:

APPLICANT'S CURRENT ESTIMATED FUEL LOADING DATE:

09-00-84 APPLICANTS CONSTRUCTION CCMPLETION ESTIMATE AS APPLICANT'S PREVIOUS ESTIMATED FUEL LOADING DATE:

12-00-82 DEFINED IN CP: (EARLIEST) 03-01-80 APPLICANT'S ESTIMATED FUEL LOADING DATE AT CP ISSUANCE:

03-00-80 (LATEST) 09-01-30 APPLICANT'S CURRENT ESTIMATED COMMERCIAL OPERATION DATE: 08-00-85

3.,. ~

5 CURRENT ESTIMATED PERCENT CONSTRUCT,_d COMPLETE: 64%

E COMMENTS REGARDING CURRENT CONSTRUCTI)N STATUS:

f.

i ESTIMATED ACTUAL ESTIMATED ACTUAL ESTIMATED START START COMPLETION COMPtETION % COMPLETE MDBILIZE AND PREPARE SITE:

09-00-74 07-00-75 100%

PLACE STRUCTURAL CONCRETE:

06-00-75 09-00-75 100%

INSTALL REACTOR PRESSURE VESSEL:

02-00-77 02-00-77 100%

INSTALL LARGE BORE PROCESS PIPE:

10-00-75 10-00-83 60%

INSTALL LARGE BORE 'IPE HANGERS, RESTRAINTS AND SNUBBERS:

07-00-78 11-00-83 35%

4 INSTALL SMALL BORE PIPE:

09-00-77 12-00-83 37%

@M g

INSTALL CABLE TRAY:

05-00-77 11-00-82 95%

INSTALL EXPOSED METAL CONDUIT:

10-00-75 04-00-83 68%

INSTALL POWER, CONTROL, INSTRUMENTATION AHD SECURITY CABLE:

03-00-78 11-00-83 54%

[. - *<

INSTALL ELECTRICAL TERMINATIONS:

04-00-78 11-00-83 49%

E e

CONDUCT REACTOR COLD NYDR0 STATIC TEST:

12-00-83 12-00-83 0%

.p a CONDUCT HOT FUNCTIONAL TEST 01-00-84 04-00-24 0%

CONDUCT PREOP AND ACCEPTANCE TESTS NECESSARY FOR FUEL LOAD:

02-00-83 09-00-84 0%

EM 1

C0N5TRUCTION 5TATUS REP 0RT PAGE NO: 2-008 BRAIDWOOD 1 NUCLEAR P0WER PLANTS STATUS AS OF 12-31-81 PLANT CHARACTERISTICSt KEY PERS0NNELa DOCKET NO:

05000456 CORPORATE CONTACT:

B. LEE, VICE PRESIDENT CP NO. & DATE ISSUED: CPR-132 / 12-31-75 CP EXPIRATION DATE:

11-01-82 CORPORATE ADDRESS:

P. O. BOX 767 APPLICANT:

COMMONWEALTH EDISDN CHICAGO, ILLINDIS 6C690 PLANT LOCATION:

24 MI SSW OF JOLIET, ILL IE REGION:

3 CORPORATE PHONE NO:

(312) 294-3103 AE SARGENT 4 LUNDY NSSS:

WESTINGHOUSE CONSTRUCTOR:

COMMONWEALTH EDISON NRC LPM:

K. KIPER REACTOR TYPE:

PWR IE PROJECT INSPECTOR:

J. NEISLER DER (MWE):

1120 IE RESIDENT INSPECTOR:

L. MC GREGOR INSPECTION STATU5:

FUEL L0AD DATE CHANGE 5 TIME PERIOD AS REP 0RTED BY U T I L I T Y:

OCT. 1981 - DEC. 1981 REPORT NEW REASON FOR CHANGE REPORT BEG DATE END DATE DATE SCHEDULE REPORTED BY UTILITY NUMBER OF INSP.

OF INSP.

01-08-80 04-00-82 NO REASON REPORTED.

8113 11-04-81 11-05-81 05-14-80 04-00-83 DELAY DUE TO FINANCIAL CONSIDERATIONS.

09-15-80 04-00-85 NO REASON REPORTED.

Inspection Reports are available at local PDRs.

L0 CAL PUBLIC D0CUMENT R00M WILMINGTON TOWNSHIP PUBLIC LIBRARY 201 S. KANKAKEE STREET WILMINGTON, ILLINDIS 60481 k

1 C0NSTRUCTION STATUS REP 0RT PAGE NO: 2-009 9RAIDWOOD 1 NUCLEAR POWER PLANTS STATUS AS OF:

12-31-81 C0N5TRUCT ION

$TA T U S:

APPLICANT'S CURRENT ESTIMATED FUEL LOADING DATE:

04-00-85 APPLICANTS CONSTRUCTION COMPLETION ESTIMATE AS APPLICANT'S PREVIOUS ESTIMATED FUEL LOADING DA*.E:

04-00-85 DEFINED IN CP: (EARLIEST) 11-01-80 APPLICANT'S ESTIMATED FUEL LOADING DATE AT CP ISSUANCE:

05-00-81 (LATEST) 11-02-82 APPLICANT'S CURRENT ESTIMATED COMMERCIAL OPERATION DATE: 10-00-85 CURRENT ESTIMATED PERCENT CONSTRUCTION COMPLETE: 61%

CCMMENTS REGARDING CURRENT CONSTRUCTION STATUS:

ESTIMATED ACTUAL ESTIMATED ACTUAL F.STIMATED START START COMPLETION COMPLETION % COMPLETE MOBILIZE AND PREPARE SITE:

08-e0-75 03-00-76 100%

't >4 PLACE STRUCTURAL CONCRETE:

03-00-76 07-00-84 98%

5 w

d INSTALL REACTOR PRESSURE VESSEL:

04-00-79 04-00-79 100%

INSTALL LARGE BORE PROCESS PIPE:

04-00-76 02-00-83 68%

INSTALL LARGE BORE PIPE HANGERS, RESTRAINTS AND SHUBBERS:

08-00-77 09-00-84 36%

INSTALL SMALL BORE PIPE:

08-00-76 11-00-83 18%

INSTALL CABLE TRAY:

12-00-76 12-00-82 95%

INSTALL EXPOSED METAL CONDUIT:

08-00-78 05-00-84 28%

INSTALL POWER, CONTROL, INSTRUMENTATION AND SECURITY CABLE:

11-00-78 06-00-84 12%

INSTALL ELECTRICAL TERMINATIONS:

11-00-78 07-00-84 10%

CONDUCT REACTOR COLD HYDROSTATIC TEST:

09-00-82 09-00-82 0%

CONDUCT HOT FUNCTIONAL TEST:

08-00-84 04-00-85 0%

CONDUCT PREOP AND ACCEPTANCE TESTS NECESSARY FOR FUEL LOAD:

10-00-82 04-00-85 0%

4~.n m

.A A

C0N5TRUCTION STATUS REP 0RT PAGE NO: 2-010 BRAIDWOOD 2 NUCLEAR POWER PLANTS STATUS AS OF 12-31-81 PLANT CHARACTERISTICSt KEY PERS0NNELa DOCKET NO:

'05000457 CORPORATE CONTACT:

B. LEE, VICE PRESIDENT CP NO. 8 DATE ISSUED: CPR-133 / 12-31-75 CP EXPIRATION DATE:

11-01-83 CORPORATE ADDRESS:

P. O. BOX 767 APPLICANT:

COMMONWEALTH EDISON CHICAGO. ILLINDIS 60690 PLANT LOCATION:

24 MI SSW OF JOLIET, ILL IE REGION:

3 CORPORATE PHONE NO:

(312) 294-3103 AE SARCENT & LUNDY NSSS:

WESTINGHOUSE CONSTRUCTOR:

COMMONWEALTH EDISDN NRC LPM:

K. KIPER REACTOR TYPE:

PWR IE PROJECT INSPECT 07:

J. NEISLER DER (MWE):

1120 IE RESIDENT INSPECTOR L. MC GREGOR INSPECTION STATUSt FUEL L0AD DATE CHANGES TIME PERIOD AS REPQRTED BY U T I L I T Y:

OCT. 1981 - DEC. 1981 REPORT NEW REA50H FOR CHANGE REPORT BEG DATE END DATE DATE SCHEDULE REPORTED BY UTILITY NUMBER OF INSP.

OF INSP.

01-08-80 04-00-83 NO REASON REPORTED.

8113 11-04-81 11-05-81 05-14-80 04-00-84 DELAY DUE TO FINANCIAL CONSIDERATIONS.

09-15-80 04-00-86 NO REASOM REPORTED.

Inspection Reports are available at local PDRs.

L0 CAL PUBLIC D0CUMENT R 0 0 Ms WILMINGTON TOWNSHIP PUBLIC LIBRARY 201 S. KANKAKEE STREET WILMINGTON, ILLINDIS 60481

.. _ _ _ _ =.

= _ -,

_.m__

C0NSTRUCTION

$TATUS REPQRT PAGE N3 2-011 BRAIDWOOD 2 NUCLEAR P0WER PLANTS STATUS AS OF:

12-31-81 C0NSTRUCTION S T A T U S:

APPLICANT'S CURRENT ESTIMATED FUEL LOADING DATE:

04-00-86 APPLICANTS C0hSTRUCTIDH COMPLETION ESTIMATE AS APPLICANT'S PREVIOUS ESTIMATED FUEL LOADING DATE:

04-00-84 DEFINED IN CP: (EARLIEST) 11-01-81 APPLICANT'S ESTIMATED FUEL LOADING DATE AT CP ISSUANCE:

05-00-82 (LATEST) 11-01-83 APPLICANT'S CURRENT ESTIMATED COMMERCIAL OPERATION DATE: 10-31-86 CURRENT ESTIMATED PERCENT CONSTRUCTION COMPLETE: 48%

COMMENTS REGARDING CURRENT CONSTRUCTION STATUS:

ESTIMATED ACTUAL ESTIMATED ACTUAL ESTIMATED START START COMPLETION COMPLETlq3 E_ COMPLETE MOBILIZE AND PREPARE SITE:

08-00-75 03-00-76 100%

PLACE STRUCTURAL CONCRETE:

03-00-76 07-00-84 98%

INSTALL REACTOR PRESSURE VESSEL:

11-00-80 11-00-80 100%

INSTALL LARGE BORE PROCESS PIPE:

05-00-76 02-00-83 22%

INSTALL LARGE BORE PIPE HANGERS, RESTRAINTS AND SHUBBERS:

08-00-77 09-00-85 16%

-INSTALL SMALL BORE PIPE:

08-00-76 12-00-84 10%

INSTALL CABLE TRAY:

12-00-76 12-00-83 52%

INSTALL EXPOSED METAL CONDUIT:

01-00-79 05-00-85 7%

INSTALL POWER, CONTROL, INSTRUMENTATION AND SECURITY CABLE:

12-00-78 06-00-85 2%

INSTALL ELECTRICAL TERMINATIONS:

12-00-78 07-00-85 1%

CONDUCT REACTOR COLD HYDROSTATIC TEST 09-00-83 09-00-83 0%

CONDUCT NOT FUNCTIONAL TEST:

08-00-85 04-00-86 0%

7 CONDUCT PREOP AND ACCEPTANCE TESTS NECESSARY FOR FUEL LOAD:

10-00-83 04-00-86 0%

i

..$O C0NSTRUCTION

$TATUS REP 0RT PAGE NO: 2-012 BYROM 1 NUCLEAR POWER PLANTS STATUS AS OF 12-31-81 F LANT C H A R A C T E R I S T I C S:

KEY-P E R S 0 N N E La DOCKET NO:

..,*s a "a &c4454 CORPORATE CONTACT:

B. LEE, VICE PRESIDENT CP NO. 8 DATE ISSUED: CPR-130 / 12-31-75 CP EXPIRATION DATE:

CORPORATE ADDRESS:

P. O. BOX 767 APPLICANT:

COMMONWEALTH EDISDN CHICAGO, ILLINDIS 60690 PLANT LOCATION:

17 MI SW OF ROCKFORD, ILL IE REGION:

3 CORPORATE PHONE NO:

(312) 294-3103 AE CARGENT 8 LUNDY NSSS*

WESTINGHOUSE CONSTRUCTOR:

CONSOLIDATED EDISON NRC LPM:

S. CHESTNUT REACTOR TYPE:

PWR IE PROJECT INSPECTOR:

J. NEISLER

. DER (MWE):

1120 IE RESIDENT INSPECTOR:

W. FORNEY INSPECTION S T A T U S:

FUEL L0AD DATE CHANGES TIME PERIOD AS REPORTED BY UTILITY OCT, 1981 - DEC. 1981 REPORT HEW REASON FOR CHANGE REPORT BEG DATE END DATE DATE SCHEDULE REPORTED BY UTILITY NUMBER OF INSP.

OF INSP.

01-05-77 10-00-80 NO REASON GIVEN.

8117 10-21-81 10-23-81 03-01-78 03-01-81 REVISED LOAD DEMAND FORECAST.

8118 10-05-81 10-31-81 01-08-80 04-00-82 NO REASON REPORTED.

09-15-80 04-00-83 NO REASON REPORTED.

Inspection Reports are available at local PDRs.

L0 CAL PUBLIC D0CUMENT R 0 0 M:

BYROM PUBLIC LIBRARY THIRD AND WASHINGTON STREET BYRON, ILLINDIS 61010 o

C0NSTRUCTION 5TATUS REP 0RT PAGE ND* 2-013 BYRON 1 NUCLEAR POWER PLANTS STATUS.AS OF:

12-31-81 C0NSTRUCTION S T A T U S:

APPLICANT'S CURRENT ESTIMATED FUEL LOADING DATE '

04-00-83 APPLICANTS CONSTRUCTION COMPLETION ESTIMATE AS APPLICANT'S PREVIOUS ESTIMATED FUEL LOADING DATE:

04-00-82 DEFINED IN CP: (EARLIEST) 0S-01-80 APPLICANT'S ESTIMATED FUEL LOADING DATE AT CP ISSUANCE:

05-00-80 (LATEST) 06-01-82 APPLICANT'S CURRENT ESTIMATED C0f1 MERCI AL OPERATION DATE: 02-28-84 CURRENT ESTIMATED PERCENT CONSTRUCTION COMPLETE: 79%

COMMENTS REGARDING CURRENT CONSTRUCTION STATUS:

ESTIMATED ACTUAL ESTIMATED ACTUAL SSTIMATED START START COMPLETION COMPLETION % COMPLETE MOBILIZE AND PREPARE SITE:

04-00-7S 12-00-7S 100%

PLACE STRUCTURAL CONCRETE:

12-00-7S 07-00-82 59%

INSTALL REACTOR PRESSURE VESSEL:

09-00-78 11-00-78 100%

INSTALL LARGE BORE PROCESS PIPE:

01-00-76 07-00-82 99%

INSTALL LARGE BORE PIPE HANGERS, RESTRAINTS AND SNUBBERS:

0S-00-77 03-00-83 67%

INSTALL SMALL BORE PIPE:

08-00-76 06-00-82 99%

INSTALL CABLE TRAY:

12-00-76 11-00-81 11-00-81 100%

INSTALL EXPOSED METAL CONDUIT:

02-00-78 11-00-82 73%

INSTALL POWER, CONTROL, INSTRUMENTATION AND SECURITY CABLE:

08-00-78 12-00-82 72%

INSTALL ELECTRICAL TERMINATIONS:

08-00-78 02-00-83 S2%

CONDUCT REACTOR COLD HYDROSTATIC TEST:

07-00-81 07-00-81 100%

CONDUCT HOT FUNCTIONAL TEST:

11-00-82 04-00-83 0%

CONDUCT PREOP AND ACCEPTANCE TESTS NECESSARY FOR FUEL LOAD:

06-00-80 04-00-83 10%

C0NSTRUCTION STATUS REP 0RT PAGE NO: 2-014 BYRON 2 NUCLEAR POWER PLANTS STATUS AS OF:

12-31-81 PLANT CHARACTERISTICSt KEY PERS0NNEL DOCKET NO:

05000455 CORPORATE CONTACT:

B. LEE, VICE PRESIDENT CP NO. & DATE ISSUED: CPR-131 / 12-31-75 CP EXPIRATION DATE:

CORPORATE ADDRESS:

P. O. BOX 767 APPLICANT:

COMMONWEALTH EDISON CHICAGO. ILLINDIS 60690 PLANT LOCATION:

17 MI SW OF ROCKFORD, ILL IE REGION:

3 CORPORATE PHONE NO:

(312) 294-3103 AE2 SARGENT 8 LUNDY NSSS:

WESTINGHOUSE CONSTRUCTOR:

CONSOLIDATED EDISON NRC LPM:

S. CHESTNUT REACTOR TYPE:

PWR-IE PROJECT INSPECTOR:

J. NEISLER DER (MWE):

1120 IE RESIDENT INSPECTOR:

W. FORNEY INSPECTION 5 T A T.U S:

FUEL L0AD DATE CHANGES TIME PERIOD AS REPORTED BY UTILITYa OCT. 1981 - DEC. 1981 REPORT NEW REASON FOR CHANGE REPORT BEG DATE END DATE 1'

DATE SCHEDULE REPORTED BY UTILITY NUMBER OF INSP.

OF INSP.

01-14-76 05-00-82 NO REASON NOTED.

8113 10-21-81 10-23-81 01-08-80 03-00-83 NO REASON REPORTED.

8114 10-05-81 10-31-81 09-15-80 04-00-84 NO REASON REPORTED.

Inspection Reports are available at local PDRs.

L-0 C A L PUBLIC D0CUMENT R 0 0 M:

i BYRON PUBLIC LIBRARY THIRD AND WASHINGTON STREET i

BYRON, ILLINDIS 61010 l

~..__...__.m

__m C0NSTRUCTION STATUS REPORT PAGE NO: 2-015 BYRON 2' NUCLEAR POWER PLANTS STATUS AS OF:

12-31-81 C0NSTRUCTION STATUSi i

APPLICANT'S CURRENT ESTIMATED FUEL LOADING DATE:

04-00-84 APPLICANTS CONSTRUCTION COMPLETION ESTIMATE AS APPLICANT'S PREVIOUS ESTIMATED FUEL LOADING DATE:

03-00-83 DEFINED IN CP: (EARLIEST) 11-01-81 APPLICANT'S ESTIMATED FUEL LOADING DATE AT CP ISSUANCE:

05-00-81 (LATEST) 11-01-83 APPLICANT'S CURRENT ESTIMATED COMMERCIAL OPERATION DATE: 02-28-85 i

CURRENT ESTIMATED PERCENT CONSTRUCTION COMPLETE: 63%

COMMENTS REGARDING CURRENT CONSTRUCTION STATUS:

ESTIMATED ACTUAL ESTIMATED ACTUAL ESTIMATED START START COMPLETION COM*LETION % COMPLETJ MO3ILIZE AND PREPARE SITE:

04-00-75 02-00-76 100%

PLACE STRUCTURAL CONCRETE:

02-00-76 07-00-82 98%

INSTALL REACTOR PRESSURE VESSEL:

07-00-79 10-00-79 100%

INSTALL LARGE BORE PROCESS PIPE:

05-00-76 04-00-83 45%

INSTALL LARGE BORE PIPE HANGERS, RESTRAINTS AND SNUBBERS:

05-00-77 11-00-83 25%

4 INSTALL SMALL BORE PIPE:

08-00 07-00-83 18%

INSTALL CABLE. TRAY:

12-00-76 06-00-82 93%

INSTALL EXPOSED METAL CONDUIT:

02-00-78 09-00-83 29%

f INSTALL POWER, CONTROL, INSTRUMENTATION AND SECURITY CABLE:

11-00-78 10-00-83 22%

- INSTALL ELECTRICAL TERMINATIONS:

11-00-78 11-00-83 23%

CONDUCT REACTOR COLD HYDROSTATIC TEST:

03-00-83 03-00-83 0%

CONDUCT NOT FUNCTIONAL TEST 09-00-83 04-00-84 0%

CONDUCT PREOP AND ACCEPTANCE TESTS NECESSARY FOR FUEL LOAD 06-00-82 04-00-84 0%

I I

L i

f e

I

C0NSTRUCTION STATUS REP 0RT PAGE NO: 2-016 CALLAWAY 1 NUCLEAR P0WER PLANTS STATUS AS OF:

12-31-81 PLANT C H A R A C T E R I S T I C S:

KEY PERS0NNEL:

DOCKET NO:

05000483 CORPORATE CONTACT:

D. F. SCHNELL, VICE PRESIDENT CP NO. & DATE ISSUED: CPPR-139/ 04-16-76 NUCLEAR CP EXPIRATION DATE:

02-28-82 CORPORATE ADDRESS:

P. O. BOX 149 APPLICANT:

UNION ELECTRIQs ST. LOUIS, MISSCURI 63166 PLANT LOCATION:

10 MI SE OF FULTON, M0' IE REGION:

3 CORPORATE PHONE NO:

(314) 621-3222 AE:

BECHTEL NSSS:

WESTINGHOUSE CONST?.JCTOR:

DANIEL INTERNATIONAL HRC LPM:

G.

EDISON REACTOR TYPE:

PWR IE PROJECT INSPECTOR:

J. KONKLIN DER (MWE):

1150 IE RESIDENT INSPECTOR:

HDHE ZHSPECTION STATUS:

FUEL L0AD DATE CNANGES TIME PERIOD AS REPQRTED BY U T I L I T Y:

OCT, 1981 - DEC. 1981 REPORT NEW REASON FOR CHANGE REPORT BEG DATE END DATE DATE SCHEDULE REPORTED BY UTILITY NUMBf8 0F INSP.

OF INSP.

02-14-77 12-01-81 FINANCING IMPACT OF PROPOSITION 1 PASSAGE BY STATE OF MISSOURI VOTERS.

8121 10-07-81 10-09-81 8123 11-04-81 11-06-81 03-02-78 04-01-82 NO REASON PROVIDED BY THE UTILITY.

8124 11-04-81 11-06-81 09-21-80 10-01-82 NO REASON PROVIDED.

8125 11-10-81 11-13-81 10-09-81 06-01-83 THE DELAY RESULTED PRIMARILY FROM PROBLEMS 8126 11-16-81 11-20-81 WITH MEETING CONSTRUCTION SCHEDULES AND A REAPPRAISAL OF THE WORK REMAINING TO BE COMPLETED.

Inspection Reports are available at local PDRs.

L0 CAL PUBLIC D0CUMENT R 0 0 M:

FULTON CITY LIBRARY OLIN LIBRARY OF WASHINGTON 709 MARKET STREET UNIVERSITY FULTON, MISSOURI 65251 SKINKER & LINDELL BLVD.

ST. LOUIS, MISSOURI 63130

C0NSTRUCTION STATUS REP 0RT PAGE NO: 2-017 CALLAWAY 1 NUCLEAR POWER PLANTS STATUS.AS OF 12-31-81 C0NSTRUCTION STATUSt APPLICANT'S CURRENT ESTIMATED FUEL LOADING DATE:

06-01-83 APPLICANTS CONSTRUCTION COMPLETION ESTIMATE AS APPLICANT'S PREVIOUS ESTIMATED FUEL LOADING DATE:

10-01-82 DEFINED IN CP: (EARLIEST) 06-30-81 APPLICANT'S ESTIMATED FUEL LOADING DATE AT CP ISSUANCE:

06-01-81 (LATEST) 02-28-82 APPLICANT'S CURRENT ESTIMATED COMMERCIAL OPERATION DATE: EARLY 1984 CURRENT ESTIMATED PERCENT CONSTRUCTION COMPLETE: 78%

COMMENTS REGARDING CURRENT CONSTRUCTION STATUS:

ESTIMATED ACTUAL ESTIMATED ACTUAL ESTIMATED START START COMPLETION COMPLETION % COMPLETE MOBILIZE AND PREPARE SITE:

09-03-75 05-01-76 100%

PLACE STRUCTURAL CONCRETE:

04-01-76 10-01-82 99%

INSTALL REACTOR PRESSURE VESSEL:

03-15-79 06-01-82 72%

INSTALL LARGE BORE PROCESS PIPE:

01-12-78 03-20-83 91%

INSTALL LARGE BORE PIPE HANDERS, RESTRAINTS AND SNUBBERS:

01-10-78 04-25-83 68%

INSTALL SMALL BORE PIPE:

01-19-78 03-20-83 77%

INSTALL CABLE TRAY:

07-09-78 12-02-82 99%

INSTALL EXPOSED METAL CONDUIT:

07-01-78 01-02-83 80%

INSTALL POWER CONTROL. INSTRUMENTATION AND SECURITY CABLE:

08-08-79 02-14-83 73%

INSTALL ELECTRICAL TERMINATIONS:

04-04-80 03-29-83 59%

CONDUCT REACTOR COLD HYDROSTATIC TEST:

07-23-82 07-23-82 0%

CONDUCT NOT FUNCTIONAL TEST 12-06-82 01-19-33 0%

CONDUCT PREOP AND ACCEPTANCE TESTS NECESSARY FOR FUEL LOAD:

12-31-81 10-30-81 04-07-83 11%

I l

C0N5TRUCTION 5TATUS REPQRT PAGE NO: 2-018 CATAWBA 1 NUCLEAR POWER PLANTS STATUS AS OF 12-31-81 PLANT CHARACTERISTICS KEY PERS0NNELa DOCKET NO:

05000413 CORPORATE CONTACT:

W. H. OWEN, SR. VICE PRESIDENT

.CP NO. 8 DATE ISSUED: CPR-116 / 08-07-75 DESIGN ENGINEERING DEPARTMENT CP EXPIRATION DATE:

06-01-81 CORPORATE ADDRESS:

POWER BUILDING /422 SOUTH CHURCH ST.

APPLICANT:

DUKE POWER CHARLOTTE, NORTH CAROLINA 28201 PLANT LOCATION:

6 MI NNW OF ROCK HILL, SC IE REGION:

2 CORPORATE PHONE NO:

(704) 373-4120 AE DUKE POWER NSSS:

WESTINGHOUSE CONSTRUCTOR:

DUKE POWER NRC LPM:

K. JABBOUR REACTOR TYPE:

PWR IE PROJECT INSPECTOR:

DER (MWE):

1145 IE RESIDENT INSPECTOR:

K. VAN DOORN INSPECTION S T A T U S:

FUEL L0A7 DATE CHANGES TIME PERIOD AS REP 0RTED BY U T I L I T Y:

OCT, 1981 - DEC. 1981 REPORT HEW REASON FOR CHANGE i

REPORT BEG DATE END DATE DATE SCHEDULE REPORTED BY UTILITY NUMBER OF INSP.

OF INSP.

09-27-74 08-00-80 CONSTRUCTION DELAYS DUE TO CRITICAL 8123 10-13-81 10-16-81 CONDITIONS EXISTING IN THE FINANCIAL 8124 09-26-81 10-25-81 MARKETS.

8125 11-02-81 11-06-81 05-00-77 09-00-80 REVISED LOAD FORECASTS.

8126 11-02-81 11-06-81 03-00-78 02-00-81 PROJECTED LOAD FORECAST.

8127 10-26-81 11-25-81 01-00-80 06-00-83 NO REASON REPORTED.

I 8128 11-26-81 12-25-81 05-01-80 04-00-83 NO REASON REPORTED.

08-00-80 08-00-83 MAJOR UNIT RESCHEDULE.

i INSPECTION REPORTS ARE AVAILABLE AT LOCAL PDR'S.

i i

5 L0 CAL PUBLIC DOCUMENT R O O M:

1 I

YORK COUNTY LIBRARY 325 SOUTH OAKLAND AVENUE ROCK HILL, SOUTH CAROLINA 29730 f

i

?

i

.m...

C0NSTRUCTION 5TATUS REPQRT PAGE NO 2-019 CATAWBA 1 NUCLEAR P0WER PLANTS STATUS AS OF:

12-31-81 CDH$TRUCTION S T A T U S:

APPLICANT'S CURRENT ESTIMATED FUEL LOADING DATE:

08-19-83 APPLICANTS CONSTRUCTION COMPLETION ESTIMATE AS.

APPLICANT'S PREVIOUS ESTIMATED FUEL LOADING DATE:

04-00-83 DEFINED IN CP: (EARLIEST)

APPLICANT'S ESTIMATED FUEL LOADING DATE AT CP ISSUANCE:

12-00-78 (LATEST)

APPLICANT'S CURRENT ESTIMATED COMMERCIAL OPERATION DATE: 07-03-84 CURRENT ESTIMATED PERCENT CONSTRUCTION COMPLETE: 88%

COMMENTS REGARDING CURRENT CONSTRUCTION STATUS: STATUS IS NOT REPORTED FOR PIPING ON THE BASIS OF PIPE SIZE.

STATUS IS NOT RECORDED FOR CABLE TRAY OR EXPOSED METAL CONDUIT.

RESCHEDULING EFFORT IS CURRENTLY IN PROGRESS. WILL BE FINISHED BY APRIL, 1982.

ESTIMATED ACTUAL ESTIMATED ACTUAL ESTIMATED START START COMPLETION COMPLETION % COMPLETE

' MOBILIZE AND PREPARE SITE:

05-16-74 05-16-74 10-01-76 04-01-76 100%

PLACE STRUCTURAL CONCRETE:

04-01-76 04-05-76 08-01-82 100%

INSTALL REACTOR PRESSURE VESSEL:

06-01-78 06-09-78 07-13-78 07-13-78 100%

INSTALL LARGE BORE PROCESS PIPE:

04-01-77 04-08-77 08-27-82 98%

INSTALL LARGE BORE PIPE HANGERS, RESTRAINTS AND SHUBBERS:

11-01-78 11-01-78 11-01-82 62%

INSTALL SMALL BORE PIPE:

N/A N/A N/A N/A N/A i

INSTALL CABLE TRAY:

N/A N/A N/A N/A N/A i

INSTALL EXPOSED METAL CONDUIT:

N/A N/A N/A N/A N/A INSTALL PGWER, CONTROL, INSTRUMENTATION AND SECURITY CABLE:

08-01-78 08-21 08-13-82 85%

INSTALL ELECTRICAL TERMINATIONS:

09-01-78 10-06-78 11-29-82 66%

CONDUCT' REACTOR COLD HYDROSTATIC TEST:

02-18-83 03-01-83 0%

CONDUCT HOT FUNCTIONAL TEST:

05-09-83 06-08-83 0%

CONDUCT PREOP AND ACCEPTANCE TESTS NECESSARY FOR FUEL LOAD:

09-04-83 12-12-83 0%

t l

C0NSTRUCTION STATUS REPORT PAGE NO: 2-020 NUCLEA'R POWER PLANTS STATUS AS OF:

12-31-81 CATAWBA 2 PLANT CHARACTERISTICSt KEY PERS0NNEL DOCKET NO:

05000414 CORPORATE CONTACT:

W. H. OWEN, SR. VICE PRESIDENT CP HO. & DATE ISSUED:

CPR-117 / 08-07-75 DESIGN ENGINEERING DEPARTMENT CP EXPIRATION DATE:

06-01-82 CORPORATE ADDRESS:

POWER BUILDING /422 SOUTH CHURCH ST.

APPLICANT:

DUKE POWER CHARLOTTE, NORTH CAROLINA 28201 PLANT LOCATION:

6 MI HHW OF ROCK HILL, SC IE REGION:

2 CORPORATE PHONE NO:

(704) 334-4120 AE:

DUKE POWER NSSS:

WESTINGHOUSE CONSTRUCTOR:

DUKE POWER NRC LPM:

K. JABBOUR REACTOR TYPE:

PWR IE PROJECT INSPECTOR:

DER (MWE):

1145 IE RESIDENT INSPECTOR:

K. VAN DOORN INSPECTION 5 T A T U S:

FUEL L0AD DATE CHANGES TIME PERIOD AS REP 0RTED BY UTILITY OCT. 1981 - DEC. 1981 REPORT HEW REASON FOR CHANGE REPORT BEG DATE END DATE DATE SCHEDULE REPORTED BY UTILITY HUMBER OF INSP.

OF INSP.

09-27-74 08-00-81 CONSTRUCTION DELAYS DUE TO CRITICAL 8123 10-13-81 10-16-81 CONDITIONS EXISTING IN THE FINANCIAL 8124 09-26-81 10-25-81 MARKETS.

8125 11-02-81 11-06-81 05-00-77 08-00-82 REVISED LOAD FORECASTS.

8126 11-02-81 11-06-81 03-05-80 10-00-84 HD REASON GIVEN.

8127 10-26-81 11-25-81 08-00-80 02-00-85 MAJOR UNIT RESCHEDULE.

8128 11-26-81 12-25-81 INSPECTION REPORTS ARE AVAILABLE AT LOCAL PDR'S.

L0 CAL PUBLIC D0CUMENT R00M YORK COUNTY LIBRARY 325 SOUTH DAKLAND AVENUE ROCK HILL, SOUTH CAROLINA 29730

.m C 0 N S T R U C T I.0 N 5TATUS REP 0RT PAGE NO: 2-021 CATAWBA 2 NUCLEAR POWER PLANTS STATUS AS OF 12-31-81 C0NSTRUCTION STATUSt APPLICANT'S CURRENT ESTIMATED FUEL LOADING DATE:

02-11-85 APPLICANTS CONSTRUCTION COMPLETIDH ESTIMATE AS APPLICANT'S PREVIOUS ESTIMATED FUEL LOADING DATE:

10-00-84 DEFINED IN CP (EARLIEST)

APPLICANT'S ESTIMATED FUEL LOADING DATE AT CP ISSUANCE:

12-00-79 (LATEST)

APPLICANT'S CURRENT ESTIMAiED COMMERCIAL OPERATION DATE: 08-09-85 CURRENT ESTIMATED PERCENT CONSTRUCTION COMPLETE: 39%

COMMENTS REGARDING CURRENT CONSTRUCTION STATUS: STATUS IS NOT REPORTED FOR PIPING ON THE BASIS OF PIPE SIZE.

STATUS IS NOT RECORDED FOR CABLE TRAY OR EXPOSED METAL CONDUIT.

RESCHEDULING EFFORT IS CURRENTLY IN PROGRESS. WILL BE FINISHED BY APRIL, 1982.

ESTIMATED ACTUAL ESTIMATED ACTUAL ESTIMATED START START COMPLETION COMPLETION % COMPLETE MOBILIZE AND PREPARE SITE:

05-16-74 05-16-74 10-01-76 04-01-76 100%

PLACE STRUCTURAL CONCRETE:

08-01-76 08-01-76 10-01-84 97%

INSTALL REACTOR PRESSURE VESSEL:

01-05-80 01-18-80 04-15-80 04-15-80 100%

INSTALL LARGE BORE PROCESS PIPE:

01-05-77 01-05-77 01-27-84 50%

INSTALL LARGE BORE PIPE HANGERS, RESTRAINTS AND SHUBBERS:

07-01-81 02-05-84 4%

INSTALL SMALL BORE PIPE:

N/A N/A N/A N/A N/A INSTALL CABLE TRAY:

N/A N/A N/A N/A N/A INSTALL EXPOSED METAL CONDUIT:

N/A N/A N/A N/A N/A INSTALL POWER, CONTROL, INSTRUMENTATION AND SECURITY CABLE:

11-01-79 11-01-79 03-09-84 18%

INbi.*l.L ELECTRICAL TERMINATIONS:

11-15-79 11-19-79 03-23-84 9%

CONDUCT REACTOR COLD NYDR0 STATIC TEST 04-27-84 C5-08-84 0%

CONDUCT NOT FUNCTIONAL TEST:

09-13-8' 10-13-84 0%

CONDUCT PREOP AND ACCEPTANCE TESTS NECESSARY FOR FUEL LOAD:

10-15-84 01-18-85 0%

C0NSTRUCTION 5TATUS REPQRT PAGE NO: 2-022 CHEROKEE 1 NUCLEAR POWER PLANTS STATUS AS OF:

12-31-81 PLANT C H A R A C T E R I S T I C 5:

KEY P E R S 0 N N E L:

DOCKET NO:

05000491 CORPORATE CONTACT:

W. H. OWEN. SR. VICE PRESIDENT CP HO. 4 DATE ISSUED: CPPR-167/ 12-30-77 DESIGN ENGINEERING DEPARTMENT CP EXPIRATION DATE:

CORPORATE ADDRESS:

POWER BUILDING /422 SOUTH CHURCH ST.

APPLICANT:

DUKE POWER CHARLOTTE, NORTH CAROLINA 28201 PLANT LOCATION:

21 MI E OF SPARTANBURG, SC IE REGION:

2 CORPORATE PHONE NO:

(704) 373-4120 AE:

DUKE POWER HSSS:

COMBUSTION ENGINEERING CONSTRUCTOR:

DUKE POWER NRC LPM:

UNASSIGNED REACTOR TYPE:

PWR IE PROJECT INSPECTOR:

DER (MWE):

1283 IE RESIDENT INSPECTOR:

INSPECTION S T A T U S:

FUEL L0AD DATE CHANGES TIME PERIOD AS REPORTED BY U T I L I T Y:

OCT, 1981 - DEC. 1981 REPORT NEW REASON FOR CHANGE REPORT BEG DATE END DATE DATE SCHEDULE REPORTED BY UTILITY NUMBER OF INSP.

OF INSP.

05-09-78 05-00-84 REVISED LOAD FORECAST.

8104 11-02-81 11-06-81 03-05-80 07-00-89 NO REASON GIVEN.

09-30-81 N/S CONSTRUCTION STOPPED.

INSPECTION REPORTS ARE AVAILABLE AT LOCAL PDR'S.

S L0 CAL PUBLIC D0CUMENT R 0 0 M:

CHEROKEE COUNTY LIBRARY 300 E.

RUTLEDGE AVENUE GAFFNEY, SOUTH CAROLINA 29340

_ = _ _ _ _ _ _ _.. _ _ _ _.

C0NSTRUCTION STATUS REP 0RT PAGE NO: 2-023 CHEROKEE.1 NUCLEAR POWER PLANTS STATUS AS OF:

12-31-81 C0NSTRUCTION S T A T U S:

APPLICANT'S CURRENT ESTIMATED FUEL LDADING DATE:

N/S APPLICANTS CONSTRUCTIDH COMPLETION ESTIMATE AS APPLICANT'S PREVIOUS ESTIMATED FUEL LOADING DATE:

07-00-89 DEFINED IN CP: (EARLIEST)

APPLICANT'S ESTIMATED FUEL LOADING DATE AT CP ISSUANCE:

05-00-83 (LATEST)

APPLICANT'S CURRENT ESTIMATED COMMERCIAL OPERATION DATE: N/S CURRENT ESTIMATED PERCENT CONSTRUCTION COMPLETE:

18%

COMMENTS REGARDING CURRENT CONSTRUCTION STATUS: CONSTRUCTION STOPPED.

ESTIMATED ACTUAL ESTIMATED ACTUAL ESTIMATED START START COMPLETION COMPLETION % COMPLETE MOBILIZE AND PREPARE SITE:

07-09-76 03-01-78 100%

PLACE STRUCTURAL CONCRETE:

03-01-78 48.3%

INSTALL REACTOR PRESSURE VESSEL:

INSTALL LARGE BORE. PROCESS PIPE:

L INSTALL LARGE BORE PIPE NANGERS, RESTRAINTS AND SNUBBERS:

INSTALL ~SMALL BORE PIPE:

INSTALL CABLE TRAY:

05-30-76 1%

INSTALL EXPOSED METAL CONDUIT INSTALL POWER, CONTROL, INSTRUMENTATION AND SECURITY CABLE:

INSTALL ELECTRICAL TERMINATIONS:

CONDUCT REACTOR COLD NYDR0 STATIC TEST:

CONDUCT NOT FUNCTIONAL TEST:

CONDUCT PREOP AND ACCEPTANCE TESTS NECESSARY FOR FUEL LOAD:

1 i

s i

r

CDNSTRUCTION STATUS REPORT PAGE NO: 2-024 CHEROKEE 2 NUCLEAR POWER PLANTS STATUS AS OF 12-31-81 PLANT CHARACTERISTICSt KEY P E R S O N N E L:

DOCKET NO:

05000492 CORPORATE CONTACT:

W. H. OWEN, SR. VICE PRESIDENT CP NO. 8 DATE ISSUED: CPPR-168/ 12-30-77 DESIGN ENGINEERING DEPARTMENT CP EXPIRATION DATE:

CORPORATE ADDRESS:

POWER BUILDING /422 SOUTH CHURCH ST.

APPLICANT:

DUKE POWER CHARLOTTE, NORTH CAROLINA 28201 PLANT LOCATION:

21 MI E OF SPARTANBURG, SC IE REGION:

2 CORPORATE PHONE NO:

(704) 373-4120 AE:

DUKE POWER NSSS:

COMBUSTION ENGINEERING CONSTRUCTOR:

DUKE POWER NRC LPM:

UNASSIGNED REACTOR TYPE:

PWR IE PROJECT INSPECTOR:

DER (MWE):

1280 IE RESIDENT INSPECTOR:

INSPECTION 5 T A T U 5:

FUEL L0AD DATE CHANGES TIME PERIOD AS REPQRTED BY UTILITY OCT. 1981 - DEC. 1981 REPORT NEW REASON FCR CHANGE REPORT BEG DATE END DATE DATE SCHEDULE REPORTED BY UTILITY NUMBER OF INSP.

OF INSP.

01-25-78 11-00-85 1

LOWER FORECASTS FOR GROWTH IN DEMAND.

8104 11-02-81 11-06-81 2.

UNCERTAINTY REGARDING THE PERKINS UNITS.

04-31-78 05-00-86 PROJECTED LOAD GROWTH.

INSPECTION REPORTS ARE AVAILABLE AT LOCAL PDR'S.

03-05 07-00-91 NO REASON GIVEN.

09-30-81 N/S CONSTRUCTION STOPPED.

l l

l l

L3 CAL PUBLIC D0CUMENT R 0 0 M:

CHEROKEE COUNTY LIBRARY 300 E. RUTLEDGE AVENUE GAFFNEY, SOUTH CAROLINA 29340 l

C0N5TRUCTION STATUS REPORT PAGE NO: 2-025 CHEROKEE 2 NUCLEAR POWER PLANTS STATUS AS OF:

12-31-81 CDN5TRUCTION S T A T U 5:

APPLICANT'S CURRENT ESTIMATED FUEL LOADING DATE:

N/S APPLICANTS CONSTRUCTION COMPLETION ESTIMATE AS APPLICANT'S PEEVIOUS ESTIMATED FUEL LOADING DATE:

07-00-91 DEFINED IN CP (EARLIEST)

APPLICANT'S ' i'T;tATED FUEL LO ADING DATE AT CP ISSUANCE:

05-00-85 (LATEST)

APPLICANT'S C0: RtNT ESTIMATED COMMERCI AL OPERATION DATE: N/S CURRENT ESTIMATED PERCENT CONSTRUCTION COMPLETE:

0%

COMMENTS REGARDING CURRENT CONSTRUCTION STATUS: CONSTRUCTION STOPPED.

ESTIMATED ACTUAL ESTIMATED ACTUAL ESTIMATED START START COMPLETION COMPLETION % COMPLETE MOBILIZE AND PREPARE SITE:

07-09-76 50%

I PLACE STRUCTURAL CONCRETE:

INSTALL REACTOR PRESSURE VESSEL:

INSTALL LARGE BORE PROCESS PIPE:

INSTALL LARGE BORE PIPE HANGERS. RESTRAINTS AND SNUBBERS:

INSTALL SMALL BORE PIPE:

INSTALL CABLE TRAY:

INSTALL EXPOSED METAL CONDUIT INSTALL POWER, CCNTROL, INSTRUMENTATION AND SECURITY CABLE:

INSTALL ELECTRICAL TERMINATIONS:

CONDUCT REACTOR COLD HYDROSTATIC TEST:

CONDUCT HOT FUNCTIONAL TEST:

CONDUCT PREOP AND ACCEPTANCE TESTS NECESSARY FOR FUEL LOAD:

. _ _ ~ _ _

C0NSTRUCTION STATUS REPQRT PAGE NO: 2-026 CHEROKEE 3 NUCLEAR POWER PLANTS STATUS AS OF 12-31-81 PLANT CHARACTERISTICS KEY P E R S 0 N N E L:

DOCKET NO:

05000495 CORPORATE CONTACT:

W. H. OWEN. SR. VICE PRESIDENT CP MO. 8 DATE ISSUED: CPPR-169/ 12-30-77 DESIGN ENGINEERING DEPARTMENT CP EXPIRATION DATE:

CORPORATE ADDRESS:

POWER BUILDING /422 SOUTH CHURCH ST.

APPLICANT:

DUKE POWER CHARLOTTE, NORTH CAROLINA 28201 PLANT LOCATION:

21 MI-E OF SPARTANBURG, SC IE REGION:

2 CORPORATE PH0!!E NO:

(704) 373-4120

-AE:

DUKE POWER NSSS:

COMBUSTION ENGINEERING CONSTRUCTOR:

DUKE POWER HRC LPM:

UNASSIGNED REACTOR TYPE:

PWR IE PROJECT INSPECTOR:

DER (MWE):

1280 IE RESIDENT INSPECTOR:

[

INSPECTION STATUSt FUEL L0AD DATE CHANGE 5 TIME PERIOD AS REPORTED BY UTILITY OCT. 1981 - DEC. 1981 REPORT NEW REASON FOR CHANGE REPORT BEG DATE END DATE DATE SCHEDULE PEPORTED BY UTILITY NUMBER OF INSP.

OF INSP.

i 04-00-80 N/S CONSTRUCTION STOPPED.

8104 11-02-81 11-06-81 i

INSPECTION REPORTS ARE AVAILABLE AT LOCAL PDR'S.

i i

i L0 CAL P'U B L I C D0CUMENT R 0 0 M:

CHEROKEE COUNTY LIBRARY 300 E. RUTLEDGE AVENUE GAFFNEY, SOUTH CAROLINA 29340 l

l 1

C0N5TRUCTION STATUS REPQRT PAGE NO: 2-027 CHEROKEE 3 HUCLEAR POWER PLANTS STATUS AS OF:

12-31-81 C0NSTRUCTION S T A T U S:

APPLICANT'S CURREhT ESTIMATED FUEL LDADJNG PA7E N/S APPLICANTS CONSTRUCTION CGMPLETION ESTIMATE AS APPLICANT'S PREVIOUS ESTIMATED FUEL LOADING DATE:

05-00-88 DEFINED IN CP: (EARLIEST)

APPLICANT'S ESTIMATED FUEL LOADING DATE AT CP ISSUANCE:

05-00-88 (LATEST)

APPLICANT'S CURRENT ESTIMATED COMMERCIAL OPERATION DATE: N/S CURRENT ESTIMATED PERCENT CONSTRUCTION COMPLETE:

0%

COMMENTS REGARDING CURRENT CONSTRUCTION STATUS: CCMSTRUCTION STOPPED.

ESTIMATED ACTUAL ESTIMATED ACTUAL ESTIMATED START START COMPLETION COMPLETION % COMPLETE MOBILIZE AND PREPARE SITE:

07-09-76 50%

PLACE STRUCTURAL CONCRETE:

INSTALL REACTOR PRESSURE VESSEL:

INSTALL LARGE BORE PROCESS PIPE:

INSTALL LARGE BORE PIPE HANGERS, RESTRAINTS AND SNUBBERS:

INSTALL SMALL BORE PIPE:

INSTALL CABLE TRAY:

INSTALL EXPOSED METAL CONDUIT:

INSTALL PCWER, CONTROL, INSTRUMENTATIDH AND SECURITY CABLE:

INSTALL ELECTRICAL TERMINATIONS:

CONDUCT REACTOR COLD HYDROSTATIC TEST:

CONDUCT HOT FUNCTIONAL TEST:

CONDUCT PREOP AND ACCEPTANCE TESTS NECESSARY FOR FUEL LOAD:

C0NSTRUCTION STATUS REPORT PAGE NO: 2-028 CLINTON 1 NUCLEAR POWER PLANT $

STATUS AS OF:

12-31-81 PLANT C H A R A C T E R I S T I C S:

KEY P E R S 0 N N E L:

DOCKET NO:

05000451 CORPORATE CONTACT:

W. C. GERSTNER, EXEC VICE PRESIDENT CP NO. & DATE ISSUED: CPPR-137/ 02-24-76 CP EXPIRfTION DATE:

CORPORATE ADDRESS:

500 SOUTH 27TH STREET APPLICANT:

ILLINDIS POWER DECATUR, ILLINDIS 62525 PLANT LOCATION:

6 MI E OF CLINTON, ILL IE REGION:

3 CORPORATE PHONE NO:

(217) 937-1111. EXT. 2811 AE:

SARGENT & LUNDY NSSS:

GENERAL ELECTRIC CONSTRUCTOR:

BALDWIN ASSOCIATES NRC LPM:

J. M. WILLIAMS REACTOR TYPE:

BWR IE PROJECT INSPECTOR:

H. M. WESCOTT DER (MWE):

0950 IE RESIDENT INSPECTOR:

H. LIVERMORE INSPECTION STATU5:

FUEL L0AD D.A T E CHANGES TIME PERIOD AS REPORTED BY U T I L I T Y:

OCT. 1981 - DEC. 1981 REPORT NEW REASON FOR CHANGE REPORT BEG DATE END DATE DATE SCHEDULE REPORTED BY UTILITY NUMBER OF INSP.

OF INSP.

05-09-77 04-00-81 REEVALUATION OF CONSTRUCTION SCNEDULE.

8125 10-01-81 11-09-81 06-23-78 04-00-82 TIME LOST DUE TO SEVERE WEATNER 8126 10-19-81 10-21-81 CONDITIONS.

8127 10-20-81 10-23-81 01-21-81 01-00-83 REEVALUATION OF CONSTRUCTION SCHEDULE.

8128 10-26-81 10-29-81 8129 11-05-81 11-13-81 8131 11-10-81 11-30-81 Inspection Reports are ava(lable at local PDRs.

L0 CAL PUBLIC DDCUMENT R 0 0 M:

VESPASIAN WARNER PUBLIC LIBRARY 120 WEST JOHNSON STREET CLINTON, ILLINDIS 61727

.. _ ~ _ _ _ _ _ _.

C0N$TRUCTION STATUS REPQRT PAGE NO: 2-029 CLINTON 1 NUCLEAR POWER PLANTS STATUS AS OF:

12-31-81 C0NSTRUCTION 5 T A T U S:

i APPLICANT'S CURRENT ESTIMATED FUEL LOADING DATE:

01-03-83 APPLICANTS CONSTRUCTION COMPLETION ESTIMATE AS APPLICANT'S PREVIOUS ESTIMATED FUEL LOADING DATE:

04-01-82 DEFINED IN CP: (EARLIEST) 10-01-80 APPLICANT'S ESTIMATED FUEL LOADING DATE AT CP ISSUANCE:

10-00-80 (LATEST) 10-01-83 APPLICANT'S CURRENT ESTIMATED C0fiMERCIAL OPERATION DATE: 03-31-85

+

CURRENT ESTIMATED PERCENT CONSTRUCTION COMPLETE: 83%

COMMENTS REGARDING CURRENT CONSTRUCTION STATUS: CRITICAL PATH ACTIVITIES ARE ESTIMATED TO BE 115 DAYS BEHIND SCHEDULE.

ESTIMATED ACTUAL ESTIMATED ACTUAL ESTIMATED START SVART COMPLETION COMPLETION % COMPLETE h0BILIZE AND PREPARE SITE:

10-06-75 03-16-76 100%

PLACE STRUCTURAL CONCRETE:

02-25-76 10-01-82 100%

INSTALL REACTOR PRESSURE VESSEL:

10-06-79 10-15-79 100%

INSTALL LARGE BORE PROCESS PIPE:

05-01-76 07-16-82 92%

INSTALL LARGE BORE FIPE HANGERS, RESTRAINTS AND SNUBBERS:

05-01-76 11-30-82 80%

INSTALL SMALL BORE PIPE:

06-01-77 09-01-82 85%

INSTALL CABLE TRAY:

06-01-78 02-19-82 93%

INSTALL EXPOSED METAL CONDUIT:

06-01-78 04-30-82 78%

INSTALL POWER, CONTROL, INSTRUMENTATION AND SECURITY CABLE:

12-12-79 10-01-82 51%

INSTALL ELECTRICAL TERMINATIONS:

04-01-80 11-05-82 49%

CONDUCT REACTOR COLD HYDROSTATIC TEST:

03-02-82 03-08-82 0%

CONDUCT HOT FUNCTIONAL TEST:

N/A N/A N/A N/A N/A CONDUCT PREOP AND ACCEPTANCE TESTS HECESSARY FOR FUEL LOAD:

03-06-81 11-30-82 4%

i

~

-r----

>--r-

C0NSTRUCTION STATUS REP 0RT PAGE N0s,2-030 CLINTON 2 NUCLEAR POWLR P L A II T S STATUS AS OF:

12-31-81 PLANT-CHARACTERISTICS:

KEY PERS0NNELe DOCKET NO:

05000462 CORPORATE CONTACT:

W. C. GERSTNER, EXEC VICE PRESIDENT CP NO. & DATE ISSUED: CPPR-138/ 02-24-76 CP EXPIRATION DATE:

CORPORATE ADDRESS:

500 SOUTH 27TH STREET DECATUR, ILLINDIS 62525 APPLICANT:

ILLINDIS POWER PLANT LOCATION:

6 MI E OF CLINTON, ILL IE REGION:

'3 CORPORATE PHONE NO:

(217) 937-1111, EXT. 2811 AE SARGENT & LUNDY NCSS:

GENERAL ELECTRIC CONSTRUCTOR:

BALDWIN ASSOCIATES NRC LPM:

J. M. WILLIAMS REACTOR TYPE:

BWR IE PROJECT INSPECTOR:

H. M. WESCOTT DER (MWE):

0950 IE RESIDENT INSPECTOR:

H. LIVERMORE INSPECTION STATUS:

FUEL L0AD DATE CHANGES TIME PERIOD AS REP 0RTED BY UTILITY OCT. 1981 - DEC. 1981 REPORT NEW REASON FOR CHANGE REPORT BEG DATE END DATE DATE SCHEDULE REPORTED BY UTILITY 1

NUMBER OF INSP.

OF INSP.

03-24-77 10-00-87 FINANCIAL CONSIDERATIONS AND UNCERTAINTY NO INSPECTIONS FOR THIS PERIOD.

OVER FEDERAL NUCLEAR GENERATION AND FUEL POLICIES.

Inspection Reports are availrble at local PDRs.

11-20-81 N/S REDUCED LOAD GROWTH RATE.

L0 CAL PUBLIC D0CUMENT R 0 0 M:

VESPASIAN WARNER PUBLIC LIBRARY 120 WEST JOHNSON STREET CLINTON, ILLINDIS 61727

C0NSTRUCTION STATUS REPQRT PAGE NO: 2-031 CLINTON 2 NUCLEAR POWER PLANTS STATUS AS OF:

12-31-81 C0NSTRUCTION STATUSt APPLICANT'S CURRENT ESTIMATED FUEL LOADING DATE:

N/S APPLICANTS CONSTRUCTION COMPLETION ESTIMATE AS APPLICANT'S PREVIOUS ESTIMATED FUEL LOADING DATE:

10-00-87 DEFINED IN CP (EARLIEST) 10-01-33 APPLICANT'S ESTIMATED FUEL LOADING DATE AT CP ISSUANCE:

10-00-83 (LATEST) 10-01-85 APPLICANT'S CURRENT ESTIMATED COMMERCIAL OPERATION DATE: N/S CURRENT ESTIMATED PERCEHi CONSTRUCTION COMPLETE:

1%

COMMLHTS REGARDING CURRENT CONSTRUCTION STATUS: UNIT 2 CONSTRUCTION DEFERRED INDEFINITELY.

ESTIMATED ACTUAL ESTIMATED ACTUAL ESTIMATED START START COMPLETION COMPLETION % COMPLETE MOBILIZE AND PREPARE SITE:

10-06-75 03-16-76 100%

1 PLACE STRUCTURAL CONCRETE:

INSTALL REACTOR PRESSURE VESSEL:

INSTALL LARGE BORE PROCESS PIPE:

INSTALL LARGE BORE PIPE HANGERS. RESTRAINTS AND SNUBBERS:

INSTALL SMALL BORE PIPE:

INSTALL CABLE TRAY:

IHSTALL EXPOSED METAL CONDUIT:

INSTALL POWER, CONTROL, INSTRUMENTATION AND SECURITY CABLE:

INSTALL ELECTRICAL TERMINATIONS:

CONDUCT REACTOR COLD HYDROSTATIC TEST:

CONDUCT HOT FUNCTIONAL TEST:

CONDUCT PREOP AND ACCEPTANCE TESTS HECESSARY FOR FUEL LOAD:

C0NSTRUCTION STATUS REPQRT PAGE NO: 2-032 CCMANCHE PEAK l'

NUCLEAR POWER PLANTS STATUS AS OF 12-31-81

-P L A N T-C H A R A C T E R I S T I C S:

KEY PERS0NNEL I

'D3CKET NO:

05000445 CORPORATE CONTACT:

R. J. GARY, EXEC. VICE PRESIDENT a CP NO. & DATE ISSUED: CPPR-126/ 12-19-74 GENERAL MANAGER-- TUGO '

CP EXPIRATION DATE:

08-01-81 CORPORATE ADDRESS:

2001 BRYAN TOWER APPLICANT:

TEXAS UTILITIES GENERATING DALLAS, TEXAS 75201 PLANT LOCATION:

4 MI N OF GLEN ROSE, TEX IE REGION:

4 CORPORATE PHONE NO:

(214) 653-4600 AE:

GIBBS & HILL INC.

NSSS:

WESTINGHOUSE CONSTRUCTOR:

BROWN & ROOT NRC LPM:

S. BURWELL REACTOR TYPE:

PWR IE PROJECT INSPECTOR:

DER (MUE):

1150 IE RESIDENT INSPECTOR:

R. G. TAYLOR INSPECTION S T A T U S:

FUEL L0AD DATE CHANGES TIME PERIOD AS REPORTED BY UTILITY:

OCT. 1981 - DEC. 1981 KEPORT HEW REASON FOR CHANGE REPORT BEG DATE END DATE DATE SCHEDULE. REPORTED BY UTILITY NUMBER OF INSP.

OF INSP.

05-00-76 05-01-79 NO REASON REPORTED.

8115 10-13-81 10-23-81 07-00-77 08-00-80 RESCHEDULED COMMERCIAL OPERATION DATE.

3116 10-01-81 10-30-81 11-00-79 03-15-81 NO REASON REPORTED.

8117 11-02-81 11-06-81 08-00-80 12-00-81 NO REASON REPORTED.

11-01-81 06-00-83 NO REASON REPORTED.

Inspection reports are available at local PDRs.

!i.

i 3

L0 CAL PUBLIC D 0 C U M E N T-R 0 0 M:

SCMERVELL COUNTY PUBLIC LIBRARY ON TiiE SQUARE P. D.

BOX 417 -

CLEN ROSE, TEXAS 76043 i

I i

.~.

~, -

-~ -.

h C0NSTRUCTION STATUS REPQRT PAGE NO: 2-033 7

COMANCHE PEAK 1 NUCLEAR POWER PLANTS STATUS AS OF:

12-31-81

~

C0NSTRUCT ION S T A T U S:

APPLICANT'S CURRENT ESTIMATED FUEL LOADING DATE:

06-00-83 APPLICANTS CONSTRUCTION COMPLETION ESTIMATE AS APPLICANT'S PREVIOUS ESTIMATED FUEL LDADING DATE:

12-00-81 DEFINED IN CP: (EARLIEST)

APPLICANT'S ESTIMATED FUEL LOADING DATE AT CP ISSUANCE:

06-00-79 (LATEST)

APPLICANT'S CURRENT ESTIt!ATED COMMERCIAL J?ERATION DATE: 03-00-84 CURRENT ESTIMATED PERCENT CONSTRUCTION COMPLETE: 89%

COMMENTS REGARDING CURRENT CONSTRUCTION STATUS:

4 ESTIMATED ACTUAL ESTIMATED-ACTUAL SSTIMATED START START COMPLETION COMPLETIQM % COMPLETE MOBILIZE AND PREPARE SITE:

08-00-74 10-00-74 100%

PLACE STRUCTURAL CONCRETE:

05-00-75 07-00-75 01-00-82 94%

INSTALL REACTOR PRESSURE VESSEL:

07-00-77 05-00-78 05-00-78 05-00-78 100%

INSTALL LARGE BORE PROCESS PIPE:

05-00-76 07-00-76 12-00-81 99%

INSTALL LARGE BORE PIPE HANGERS, RESTRAINTS AND SNUBBERS:

03-00-76 08-00-82 79%

INSTALL SMALL BORE PIPE:

'11-00-76 12-00-81 94%

INSTALL CABLE TRAY:

08-00-77 12-00-81 99%

INSTALL EXPOSED METAL CONDUIT:

08-00-77 08-00-82 90%

INSTALL POWER, CONTROL, INSTRUMENTATION AND SECURITY CABLE:

02-00-79 12-00-82 78%

INSTALL ELECTRICAL TERMINATIONS:

04-00-79 12-00-82 76%

i CONDUCT REACTOR COLD HYDROSTATIC TEST:

06-00-82 06-00-82 0%

i CONDUCT HDT FUNCTIONAL. TESTS 11-00-82 12-00-82 0%

CONDUCT PREOP AND ACCEPTANCE TESTS NECESSARY FOR FUEL LOAD:

06-00-83 0%

l t

i i

m

)

C0NSTRUCTION STATUS REP 0RT PAGE NO: 2-034 COMANCHE PEAK 2 NUCLEAR POWER PLANTS STATUS AS OF:

12-31-81 PLANT C H A R A C T E R I S T I C 5:

KEY P E R S 0 N N E L:

DOCKET NO:

05000446 CORPORATE CONTACT:

R. J. GARY, EXEC. VICE' PRESIDENT &

GENERAL MANAGER - TUGO CP NO. 8 DATE ISSUED: CPPR-127/ 12-19-74

'CP EXPIRATION DATE:

08-01-83 CORPORATE ADDRESS:

2001 BRYAN TOWER APPLICANT:

TEXAS UTILITIES GENERATING DALLAS, TEXAS 75201 PLANT LOCATION:

4 MI N OF GLEN ROSE, TEX IE REGION:

4 CORPORATE PHONE NO:

(214) 653-4600 AE:

GIBBS & HILL INC.

NSSS:

WESTINGHOUSE CONSTRUCTOR:

BROWN & ROOT HRC-LPM:

S. BURWELL REACTOR TYPE:

PWR IE PR3 JECT INSPCCTOR:

DER (MWE):

1150 IE RESIDENT INSPECTOR:

R. G. TAYLOR IN$PECTION S T A T U S:

FUEL L0AD DATE CHANGES TIME PERIOD AS REP 0RTED BY U T I L I T Y:

OCT. 1981 - DEC. 1981 REPORT NEW REASON FOR CHANGE REPORT BEG DATE END DATE DATE SCHEDULE REPORTED BY UTILITY HUMBER OF INSP.

UtiL 05-00-76 05-01-81 NO REASON REPORTED.

8115 10-13-81 10-23-81 07-00-77 08-00-82 RESCHEDULED COMt1ERCI AL OPERATION DATE.

8116 10-01-81 10-30-81 11-01-81 N/S SCHEDULE UNDER REVIEW.

8117 11-02-81 11-06-81 Inspection reports are available at local PDRs.

L0 CAL PUBLIC D 0 C U M E N T 'R 0 0 M:

SOMERVELL COUNTY PUBLIC LIBRARY ON THE SQUARE P. O. BOX 417

. GLEN ROSE, TEXAS 76043

.C0NSTRUCTION STATUS REP 0RT PAGE NO: 2-035 CCMANCHE PEAK 2 NUCLEAR POWER P L'A N T S STATUS AS OF:

12-31-81 C0NSTRUCTION-STATUSt APPLICANT'S CURRENT ESTIMATED FUEL LOADING DATE:

N/S APPLICANTS CONSTRUCTION COMPLETION ESTIMATE AS APPLICANT'S PREVIOUS ESTIMATED FUEL LOADING DATE:

08-00-82 DEFINED IN CP: (EARLIEST)

APPLICANT'S ESTIMATED FUEL LOADING DATE AT CP ISSUANCEr, 06-00-81 (LATEST)-

APPLICANT'S CURRENT ESTIMATED CCMMERCIAL OPERATION DATE: N/S CURRENT ESTIMATED PERCENT CONSTRUCTION COMPLETE: 57%

COMMENTS REGARDING CURRENT CONSTRUCTION STATUS: SCHEDULE UNDER REVIEW.

ESTIMATED ACTUAL ESTIMATED ACTUAL ESTIMATED START START COMPLETION COMPLETION % COMPLETE

. MOBILIZE AND PREPARE SITE:

10-17-74 04-18-75 100%

PLACE STRUCTURAL CONCRETE:

04-18-75 INSTALL REACTOR PRESSURE VESSEL:

06-00-79 08-15-79 100%

i INSTALL LARGE BORE PROCESS PIPE:

INSTALL LARGE BORE PIPE HANGERS. RESTRAINTS AND SNUBBERS:

4

  • INSTALL SMALL BORE PIPE:

I!! STALL CABLE TRAY:

1 INSTALL EXPOSED METAL CONDUIT:

INSTALL POWER, CONTROL,INSTRUMENTATIDH AND SECURITY CABLE:

INSTALL ELECTRICAL TERMINATIONS:

CONDUCT REACTOR COLD HYDROSTATIC TEST:

CONDUCT HOT FUNCTIONAL TEST:

CONDUCT PREOP AND ACCEPTANCE TESTS NECESSARY FOR FUEL LOAD:

_ _.~

m I

e C0N5TRUCTION 5TATUS REPORT PAGE NO: 2-036 DIABLO CANYON 1 NUCL EAR POWER PLANTS STATUS AS OF 12-31-81 l

PLANT C H A R A C T E R I S T I C S:

KEY PERS0NNEL

.j DOCKET NO:

05000275 CORPORATE CONTACT:

PHILIP A.

CRANE. JR., ASSISTANT CP NO. & DATE ISSUED: CPPR-39 / 04-23-68 GENERAL COUNSEL CP EXPIRATIDH DATE:

04-30-79 CORPORATE ADDRESS:

77 BEALF STREET APPLICANT:

PACIFIC GAS & ELECTRIC SAN FRANCISCO, CALIFORNIA 94106 FLANT LOCATION:

12 MI WSW OF SAN LUIS OBISPO IE REGICH:

5 CORPORATE PHONE NO:

(415) 781-4211 AE:

PACIFIC GAS & ELECTRIC NSSS:

WESTINGHOUSE CONSTRUCTOR:

PACIFIC GAS & ELECTRIC NRC LPM:

B. BUCKLEY

. REACTOR TYPE:

PWR IE PROJECT INSPECTOR:

DER (MWE):

1084 IE RESIDENT INSPECTOR:

M. J. BAGAGLIO IN5PECTION S T A T U S:

FUEL L0AD DATE CHANGES TIME PERIOD AS REP 0RTED BY UTILITY OCT. 1981 - DEC. 1981 REPORT NEW-REASON FOR CHANGE REPORT BEG DATE END DATE DATE SCHEDULE REPORTED BY UTILITY NUMBER OF INSP.

OF INSP.

04-00-74 01-00-75 SLOW DOWN IN WORK RESULTING FROM WILDCAT 81-25 11-03-81 11-06-81 STRIKE BY ELECTRICIANS WHEN SECOND SWIFT 81-26 10-05-81 10-09-81 WAS ADDED INSTEAD OF 0VERTIME. INEXPERI-10-30-81 ENCED NEW HIRES IN ADDITION TO REDUCED 81-27 10-02-81.

06-03-81 ELECTRICIAN WORK FORCE CAUSED THE DELAY.

81-28 05-27-81 81-29 10-14-81 10-23-81 09-00-74 04-00-75 A STRIKE BY PIPEFITTERS IS STILL IN EFFECT 81-30 10-30-81 11-17-81 AT THE SITE.

THE LICENSEE ESTIMATES AT 81-31 12-01-81 12-30-81 LEAST A 48 DAY FUEL LOAD SLIP AT THIS 81-32 12-16-81 12-28-81 TIME BUT WILL EVALUATE THE EFFECT ON THE 81-33 12-07-81 12-17-81 OVERALL SCHEDULE AT COMPLETION OF STRIKE.

10-00-74 10-00-75 LICENSEE'S EVALUATION OF STRIKE EFFECTS.

Inspection Reports are available at local PDRs.

08-00-75 02-00-76 RETUBING OF MAIN CONDENSER WITH TITANIUM TUBES.

I 10-00-76 03-00-77 DECISION TO PARTIALLY REBLADE PORTIONS OF THE LOW PRESSURE TURBINES.

01-07-77 05-00-77 REBLADING OF THE LOW PRESSURE TURBINES.

04-04-78 08-00-78 REVIEW OF PREOPERATIONAL TEST PROGRAM AND COMPLETION AND APPROVAL OF SEISMIC NODIFICATION PROGRAM.

02-00-79 ESTIMATED DATE.

NRC CONTROLLING.

08-00-80 01-00-81 ESTIMATED DATE.

NRC CONTROLLING.

09-00-81 03-00-81 NO REASON KNOWN.

12-00-81 03-00-82 ESTIMATED DATE.

L0 CAL PUBLIC D0CUMENT R 0 0 M:

SAN LUIS OBISPO COUNTY FREE LIBRARY 888 MORRO STREET SAN LUIS OBISPD, CALIFORNIA 93406 i

C0N5TRUCTION STATUS REPORT PAGE NO: 2-037 DIABLO CANYON 1 NUCLEAR POWER PLANTS STATUS AS OF:

12'-31-81' C0NSTRUCTION STATUSt APPLICANT'S CURRENT ESTIMATED FUEL LOADING DATE:

03-00-82 APPLICANTS CONSTRUCTION COMPLETION ESTIMATE AS APPLICANT'S PREVIOUS ESTIMATED FUEL LOADING DATE:

03-00-81 DEFINED IN CP: (EARLIEST)

APPLICANT'S ESTIMATED FUEL LOADING DATE AT CP ISSUANCE:

04-00-72 (LATEST)

APPLICANT'S CURRENT ESTIMATED COMMERCIAL OPERATION DATE: 09-00-82 CURRENT ESTIMATED PERCENT CONSTRUCTION COMPLETE: 99%

COMMENTS REGARDING CURRENT CONSTRUCTION STATUS: FUEL LOADING LICENSE SUSPENDED BY THE NRC.

NO UPDATE RECEIVED.

4 ESTIMATED ACTUAL ESTIMATED ACTUAL ESTIMATED START START COMPLETION COMPLETION % COMPLETE MOBILIZE AND PREPARE SITE:

06-14-68 12-00-69 100%

PLACE STRUCTURAL CONCRETE:

12-00-69 100%

j INSTALL REACTOR PRESSURE VESSEL:

02-00-73 03-00-73 100%

INSTALL LARGE BORE PROCESS PIPE:

INS.ALL LARGE. BORE PIPE HANGERS, RESTRAINTS AND SNUBBERS:

INSTALL SMALL BORE PIPE:

INSTALL CABLE TRAY:

INSTALL EXPOSED METAL CONDUIT:

INSTALL PCWER CONTROL INSTRUMENTATION AND SECURITY CABLE:

INSTALL ELECTRICAL TERMINATIONS:

CONDUCT REACTOR COLD HYDROSTATIC TEST:

06-00-75 08-00-75 100%

CONDUCT NOT FUNCTIONAL TEST:

11-00-75 02-00-76 100%

CONDUCT PREOP AND ACCEPTANCE TESTS NECESSARY FOR FUEL LOAD:

~

.o C0NSTRUCTION STATUS REPQRT

-PAGE NO: 2-038 DIABLO CANYON 2 NUCLEAR POWER PLANTS STATUS AS OF:

12-31-81 PLANT C H A R A C T E R I S T I C S:

KEY P E R S 0 N N E La DOCKET NO:

05000323 CORPORATE CONTACT PHILIP A.

CRANE, JR., ASSISTANT CP HO. 8 DATE ISSUED: CPPR-69 / 12-09-70 GENERAL COUNSEL CP EXPIRATION DATE:

10-31-79 CORPORATE ADDRESS:

77 BEALE STREET APPLICANT:

PACIFIC GAS 8 ELECTRIC SAN FRANCISCO. JALIFORNIA 94106

' PLANT LOCATION:

12 MI WSW OF SAN LUIS OBISPD IE REGION:

S CORPORATE PHONE ND:

(415) 781-4211 AE PACIFIC GAS 8 ELECTRIC NSSS:

WESTINGHOUSE CONSTRUCTOR:

PACIFIC GAS 8 ELECTRIC NRC LPM:

B. BUCKLEY REACTOR TYPE:

PWR IE PROJECT INSPECTOR:

DER (MWE):

1106 IE RESIDENT INSPECTOR:

M. J. BAGAGLIO IN5PECTION S T A T U S:

FUEL L0AD DATE CHANGES TIME PERIOD AS REPORTED BY U T I L I T Y:

OCT. 1981 - DEC. 1981 REPORT HEW REASON FOR CHANGE REPORT BEG DATE END DATE DATE SCHEDULE REPORTED BY UTILITY NUMBER OF INSP.

OF INSP.

09-00-74 02-00-76 A STRIKE BY THE PIPEFITTERS IS STILL IN 81-18 10-14-81 10-23-81 EFFECT AT THE SITE.

THE LICENSEE 81-19 12-07-81 12-17-81 ESTIMATES AT LEAST A 48 DAY FUEL LOAD SLIP AT THIS TIME BUT WILL EVALUATE THE EFFECT Inspection Reports are available at local PDRs.

ON THE OVERALL SCHEDULE AT THE COMPLETION OF THE STRIKE.

10-00-74 07-00-76 STRIKE.

08-11-75 02-00-77 1 RETUBING OF MAIN CONDENSER WITH TITANIUM TUBES (2-3 MONTHS).

2. INSTALLATION OF ADDITIONAL MAIN STREAM l

I RUPTURE RESTRAINTS (4 MONTHS).

10-15-76 08-00-77 ELECTRICAL INSTALLATION PROBLEMS.

01-07-77 12-00-77 A GENERAL REEVALUATION OF THE PROJECT SCHEDULE.

01-04-78 01-00-78 NO REASON GIVEN.

02-07-78 03-00-79 GENERAL REEVALUATION OF PROJECT SCHEDULE.

04-14-78 02-00-80 GENERAL REEVALUATION OF PROJECT SCHEDULE.

02-00-80 03-00-80 NO REASON REPORTED.

05-00-80 03-00-81 NO REASON PROVIDED.

09-00-81 07-00-82 NO REASON PROVIDED.

L0 CAL PUBLIC D0CUMENT R 0 0 M:

SAN LUIS OBISPD COUNTY FREE LIBRARY l

888 MORRO STREET SAN LUIS OBISPO, CALIFORNIA 93406 l

r

~

C0N5TRUCTION STATUS.REPQRT PAGE NO: 2-039 t

DfABLO CANYON 2,

NUCLEAR P0WER PLANTS STATUS AS OF:

12-31-81 C0NSTRUCTION S T A T U S:

APPLICANT'S CURRENT ESTIMATED FUEL LDADING DATE:

07-00-82 APPLICANTS CONSTRUCTION COMPLETION ESTIMATE AS APPLICANT'S PREVIOUS ESTIMATED FUEL LOADING DATE:

03-00-81 DEFINED IN CP: (EARLIEST)

APPLICANT'S ESTIMATED FUEL LOADING DATE AT CP ISSUANCE:

11-00-74 (LATEST)

APPLICANT'S CURRENT ESTIMATED COMMERCIAL OPERATION DATE: 12-00-82 CURRENT ESTIMATED PERCENT CONSTRUCTION COMPL.ETE: 98%

COMMENTS REGARDING CURRENT CONSTRUCTION STATUS: NO UPDATE RECEIVED.

b ESTIMATED ACTUAL ESTIMATED ACTUAL ESTIMATED START START COMPLETION

{pMPLETION % COMPLETE MOBILIZE AND PREPARE SITE:

06-14-68 0S-00-71 100%

PLACE STRUCTURAL CONCRETE:

05-00-71 100%

INSTALL REACTOR PRESSURE VESSEL:

INSTALL LARGE BORE PROCESS PIPE:

INSTALL LARGE BORE PIPE HANGERS, RESTRAINTS AND SNUBBERS:

INSTALL SMALL BORE PIPE:

J INSTALL CABLE TRAY:

\\

INSTALL EXPOSED METAL CONDUIT:

INSTALL POWER, CONTROL, INSTRUMENTATION AND SECURITY CABLE:

INSTALL ELECTRICAL TERMINATIONS:

CONDUCT REACTOR COLD HYDROSTATIC TEST:

CONDUCT HOT FUNCTIONAL. TEST:

CONDUCT PREOP AND ACCEPTANCE TESTS HECESSARY FOR FUEL LOAD:

p 4

0 1

4 8 0

Y C R 1

A I

OSS 2 3 S

LG M TET T

O

, EN A.CGN 2

R T

S DI NKANE O

1 O

E R YARAM GA DETHE N

N F

.K OS. D.

O FDR TPS OSNE RNCR S

I EEO MT.CEIH EBO I

E E

G F TT TW.EUNG DR N

CNU

. G A O NC 6

NA UPENNIAO IE OQ S A

P EU 2 OPE 0D MIOUET MPE E M T

.SEDIGH RIRDR E R S

DR 2 IID7 CRLT E EPUE

.L O

A IT 8

TCA-SS 4

CIR0GCIIIYLU

.T TSHSB H S

EN UTG1DEUUDRADDEDCATEO S U

ROE RNB L

QBDOT RDEUBIDR T

PCUN TAUOBRE ATNPA DR WIP R A

NA S

ST ORE AECOONTE U O

T E&EG NN RF TNLM BTESLYGG B

OAO0O CSOUNG UL N

.A S

C VI 6

IGAH 9

S Y CHD7TSEA GONSNEFDPYISL VN C 6 Y

T CLAWDERILGLOEMRCT 6

E T T

D O6AL DERINAIB HOONNT D

,IDI RNM R

EI NET 0EENAS VIESUNCCTAIF

.E REO 3

E E G

I GL AV RWIRADNAPEOOS ANAADD EEC, 7 H

L NI INM BNETPDDI OLIRREI BNET 2

T T

N L

AT GSOOFPEF A BA TFTUFTCTV UISI N

T HU NNIROEGOE LO LFAO G S AO AG O

)

I I

A I

C IETF EN TSA DAOZ MEOEOTR TN0R 3

K L

Y RTP NDANADNNNN INERTRTSP

.E0T H T RB EXMDG HGMROIAOSLOT 1

0E 3

O EEEEIGCIIAI ITIISWELENN H 2D

(

L B

C U FD N XYSN STDTYDTCBSYEUAUOO E

IEEAEITESNIARIEOISHDIDSS a

NT GR LDDEDEADLADFMV C AA L

E Y OR NOPEEDEEETDEODFEENFYNYEE SO EMCDRAMRRSADBAERRIOAAARR E

R T B AP LNL EIEOO T

RO EE OT A

RR 1

2 1

21 21 2

12 DFDNN N

R O

TC D

N T S

N CE D

0 C S EP E

E 4

5 5

6 6

80012 0 A E E

PS L

7 7

7 7

7 78888 P

T R

N SN D T U

S S N D O

NI WD 0

0 0

0 0

01100 E

O D H

I A R EE 0

0 0

0 0

00003 T

R C A P

T NH R

TN 0 O C

8 4

0 2

8 81651 N

E E E E

CE S

0 0

1 0

0 00001 T

T T

ED L P A

P A A

A MJI S

R R R

FOS E

0 1

2 2

3 45890 L

O O O

LRE L

7 7

7 7

7 77778 U

P P P

PR R T P

Y R R

R C

E R

0 0

0 0

0 79310 T

O O O

REE OE 0

0 0

0 0

21110 E C C C

NII U S PT A

EA 2

1 6

8 7

91078 R

K F A RD 1

1 0

0 0

01100 T

E S

W O

N P

O s

R I

D R

P

'T C.

A la E

c U

E.

11 o

L TP 88 l

R AS C

DN 21 t

M T

I 23 a

U L

D 0

S A

NF 00 e

N 2

H N

EO 11 l

0 N

7 C

O b

S I

CI a

R 0

7 M YIT 1

l C

2 N DRA 8

i C

O, NTN 9

a T

E.

11 v

I 9

SH UCR 1

0 IC LEE D

TP 88 a

N T

DA LT O.

DN 91 e

E AS

/

EE &EN IC S

1 2 B I

RE I

10 r

478T TL ED G

a M

I 38 IA NAL S P EF 00 0- 1ON ERE BO 11 s

U M R

0R0RU GEI 3

U E t

E 0P TG RNNR9 M1 r

C T E

SP1EA AEAW0 T

I8 o

S 0C0DL3SGDB1 T9 p

0 Y e

S 1

T A

1 TR R

D D6 C

T RE 67 YA1 D

T OB 11 n

RO8 1

A E-S C

Pt 11 o

C AR4 UE O

EU 88 i R

R ST RN t

I BR SA N

c IEN e

L LTA A

ID N

O p

SG H

EN O s

B YUI TO I

E I

n TCH C

AI T

RP I

U N C

DT:A:

OY:

T UHI 2

O ATCN TT)

P OTM N8RNOO C E C

CU

.IALI URU O,

I T

PC G ROM E

L ESE M

T R

N EOXITE

TT(

O O E

KHELNR SSC P

A R0R F

A C

PA

SNAR N0N OPPPLEESOEE S

C O7O O

L DCCAPIANCRD M3M C

N 0

I P

R I

L NE ill1 lll lllt(

llll ll

.____m__

-.. - _. ~

C0NSTRUCTION STATUS REPQRT PAGE NO: 2-041 ENRICO FERMI 2 NUCLEAR POWER PLANTS STATUS AS OF:

12-31-81 CDN$TRUCTION

$ T.A T U S:

APPLICANT'S CURRENT ESTIMATED FUEL LOADING DATE:

11-30-82 APPLICANTS CONSTRUCTION COMPLETION ESTIMATE AS APPLICANT'S PREVIOUS ESTIMATED FUEL LOADING DATE:

05-00-81 DEFINED IN CP: (EARLIEST) 11-00-82

. APPLICANT'S ESTIMATED FUEL LOADING DATE AT CP ISSUANCE:

08-00-73 (LATEST) 11-00-82 APPLICANT'S CURRENT ESTIMATED COMMERCIAL OPERATION DATCt 11-00-83 CURRENT ESTIMATED PERCENT CONSTRUCTION COMPLETE: 88%

COMMENTS REGARDING CURRENT CONSTRUCTION STATUS:

ESTIMATED ACTUAL ESTIMATED ACTUAL ESTIMATED START START COMPLETION COMPLETION % COMPLETE MOBILIZE AND PREPARE SITE:

05-00-69 10-00-70 100%

PLACE STRUCTURAL CONCRETE:

12-00-70 06-00-79 100%

INSTALL REACTOR PRESSURE VESSEL:

10-00-74 10-00-74 100%

INSTALL LARGE BORE PROCESS PIPE:

06-00-77 06-00-82 99%

INSTALL LARGE BORE PIPE HANGERS, RESTRAINTS AND SHUBBERS:

09-00-77 06-00-82 87%

INSTALL SMALL BORE PIPE:

07-00-77 06-00-82 86%

INSTALL CABLE TRAY:

02-00-74 06-00-82 99%

INSTALL EXPOSED METAL CONDUIT:

02-00-74 06-00-82 89%

INSTALL POWER, CONTROL, INSTRUMENTATION AND SECURITY CABLE:

04-00-74 05-00-82 87%

INSTALL ELECTRICAL TERMINATIONS:

06-00-74 06-00-82 86%

CONDUCT REACTOR COLD HYDROSTATIC TEST:

03-00-82 03-00-82 0%

CONDUCT HOT FUNCTIONAL TEST:

N/A N/A N/A N/A N/A

^

.CONCUCT PREOP AND ACCEPTANCE TESTS NECESSARY FOR FUEL LCAD:

10-00-81 11-00-82 0%

j l

C0N$TRUCTION STATUS REPORT PAGE NO: 2-042 GRAND GULF 1 NUCLEAR POWER PLANTS STATUS AS OF:

12-31-81 PLANT CHARACTERIST I C S:

KEY P E R S 0 N N E L:

DOCKET NO:

05000416 CORPORATE CONTACT:

N.

L. STAMPLEY, SEN.

V. PRESIDENT-CP NO. & DATE ISSUED:

CPPR-118/ 09-04-74 NUCLEAR CP EXPIRATION DATE:

03-01-82 CORPORATE ADDRESS:

P.

O.

BOX 1640 APPLICANT:

MISSISSIPPI POWER & LIGHT COMPANY JACKSON, MISSISSIPPI 39205 PLANT LOCATION:

25 MI S OF VICKSBURG, MISS IE REGION:

2 CORPORATE PHONE NO:

(601) 969-2335 AE:

BECHTEL NSSS:

GENERAL ELECTRIC CONSTRUCTOR:

BECHTEL NRC LPM:

D.

H. HOUSTON REACTOR TYPE:

BWR IE PROJECT INSPECTOR:

J.

K. RAUSCH DER (MWE):

1250 IE RESIDENT INSPECTOR:

A. WAGNER INSPECT ION STATUS:

FUEL L0AD DAT E CHANGES TIME PERIOD AS REP 0RTED BY UTI L I T Y:

OCT. 1981 - DEC. 1981 REPORT NEW REASON FOR CHANGE REPORT BEG DATE END DATE DATE SCHEDULE REPORTED BY UTILITY EUMBER OF INSP.

OF INSP.

01-07-77 10-00-80 CONSTRUCTION DELAY.

8142 10-06-81 10-09-81 09-04-79 11-00-80 NO REASON GIVEN.

8143 10-13-81 10-16-81 01-11-80 09-00-81 NO REASON REPORTED.

8144 11-03-81 11-06-81 05-12-80 08-00-81 NO REASON PROVIDED.

8145 09-16-81 10-13-81 01-16-81 12-00-81 NO REASON PROVIDED.

8146 10-19-81 10-30-81 12-31-81 02-01-82 REEVALUATION OF CONSTRUCTION PROGRESS.

8147 10-20-81 10-23-81 8148 10-20-81 10-23-81 8149 10-26-81 10-30-81 8150 10-27-81 10-30-81 8151 11-09-81 11-12-81 l

8152 10-16-81 11-12-81 8153 11-16-81 11-20-81 l

8154 12-15-81 12-19-81 8155 12-07-81 12-11-81 8156 11-16-81 12-15-81 i

l 8157 11-30-81 12-04-81 8158 12-08-81 12-11-81 1

8159 12-14-81 12-16-81 i

8160 12-15-81 12-18-81 8161 12-14-81 12-18-81 8162 12-30-81 12-31-81 INSPECTION REPORTS ARE AVAILABLE AT LOCAL PDR'S.

L0 CAL PUBLIC D0CUMENT R 0 0 M:

MS. GAYLE KEEF HINDS JUNIOR COLLEGE MCLENDON LIBRARY RAYMOND, MISSISSIPPI 39154 l

I.

C0NSTRUCTION STATUS REPORT PAGE NO: 2-043 GRAND GULF 1 NUCL EAR POWER PL ANTS STATUS AS OF:

12-31-81 T

C0NSTRUCT ION S T A T U S:

APPLICANT'S CURRENT ESTIMATED FUEL LOADING DATE:

02-01-82 APPLICANTS CCNSTRUCTION COMPLETION ESTIMATE AS APPLICANT'S PREVIOUS ESTIMATED FUEL LOADING DATE:

12-00-81 DEFINED IN CP: (EARLIEST) 09-01-80 AFPLICANT'S ESTIMATED FUEL LOADING DATE AT CP ISSUANCE:

03-00-79 (LATEST) 03-01-82 APPLICANT'S CURRENT ESTIMATED COMMERCIAL OPERATION DATE: 08-00-82 CURRENT ESTIMATED PERCENT CONSTRUCTION COMPLETE: 95%

CCMMENTS REGARDING CURRENT CONSTRUCTION STATUS: NDHE ESTIMATED ACTUAL ESTIMATED ACTUAL ESTIMATED START START COMPLETION COMPLETION % CQMPLETE MOBILIZE AND PREPARE SITE:

05-03-74 06-00-74 100%

PLACE STRUCTURAL CCNCRETE:

12-00-74 11-00-81 100%

INSTALL REACTOR PRESSURE VESSEL:

02-00-77 05-00-77 100%

INSTALL LARGE BORE PROCESS PIPE:

04-00-75 02-01-82 99%

INSTALL LARGE BORE PIPE NANGERS, RESTRAINTS AND SNUBBERS:

03-00-76 02-00-82 97%

INSTALL Sf1ALL BORE PIPE:

09-00-76 02-00-82 99%

INSTALL CASLE TRAY:

04-00-76 05-30-80 100%

INSTALL EXPOSED METAL CONDUIT:

01-00-77 02-00-82 97%

INSTALL POWER, CONTROL, INSTRUMENTATION AND SECURITY CABLE:

11-00-77 02-00-83 95%

INSTALL ELECTRICAL TERMINATIONS:

02-00-78 02-00-82 94%

CONDUCT REACTOR COLD HYDROSTATIC TEST:

12-00-80 12-00-80 100%

CONDUCT NOT FUNCTIONAL TEST:

N/A N/A N/A N/A N/A CONDUCT PREOP AND ACCEPTANCE TESTS NECESSARY FOR FUEL LOAD:

05-00-79 02-00-82 47%

C 0 N S T R U C.T I O N STATUS REPQRT PAGE NO: 2-044

. GRAND GULF 2 NUCLEAR P 0 W.E R PLANTS STATUS AS OF:

12-31-81 PLANT CHARACTERIS'TICSt KEY PERS0NNELa DOCKET NO:

05000417-CORPORATE CONTACT:

N.

L. STAMPLEY, SEN. V. PRESIDENT CP NO. 8 DATE ISSUED: CPPR-119/ 09-04-74 NUCLEAR CP EXPIRATION DATE:

10-01-84 CORPORATE ADDRESS:

P. O.

BOX 1640 APPLICANT:

MISSISSIPPI POWER 8 LIGHT COMPANY JACKSON, MISSISSIPPI 39205 PLANT LOCATICH:

25 MI S OF VICKS3URG, MISS IE REGION:

2 CORPORATE PHONE NO:

(601) 969-2335 AE:

BECHTEL NS$$

GENERAL ELECTRIC CONSTRUCTOR:

BECHTEL NRC LPM:

D. HOUSTON REACTOR TYPE:

BWR IE PROJECT INSPECTOR:

J. K. RAUSCH DER (MWE):

1250 IE RESIDENT INSPECTOR:

A. WAGNER IN5PECTION STATUS:

FUEL L0AD DATE CHANGES TIME PERIOD AS REP 0RTED BY UTILITY OCT. 1981 - DEC. 1981 REPORT BEG DATE END DATE DATE SCHEDULE REPORTED BY UTILITY NUMBER OF INSE.

OF INSP.

06-25-76 03-00-83 NO REASON REPORTED FOR THIS SLIPPAGE BY 8119 11-03-81 11-06-81 THE UTILITY.

8120 10-20-81 10-23-81 01-07-77 07-00-83 CONSTRUCTION DELAYS.

8121 10-20-81 10-23-81 01-11-80 09-00-84 NO REASON REPORTED.

8122 10-27-81 10-30-81 09-15-80 08-00-85 NO REASON REPORTED.

8124 12-07-81 12-11-81 12-31-81 N/S SCHEDULE UNDER REVIEW.

8125 12-15-81 12-18-81 INSPECTION REPORTS ARE AVAILABLE AT LOCAL PDR'S.

L0 CAL PUBLIC D0CUMENT R 0 0 M:

MS. GAYLE KEEF

-HINDS JUNIOR COLLEGE MCLENDON LIBRARY RAYMOND, f1ISSISSIPPI 39154

C0NSTRUCTICN STATUS REF0RT PAGE NO: 2-045 GRAND GULF 2 NUCLEAR POWER PLANT $

STATUS AS OF:

12-31-81 C0NSTRUCTION S T A T U S:

APPLICANT'S CURRENT ESTIMATED FUEL LOADING DATE:

N/S APPLICANTS CONSTRUCTION COMPLETION ESTIMATE AS APPLICANT'S PREVIOUS ESTIMATED FUEL LDADING DATE:

08-0C-85 DEFINED IN CP (EARLIEST) 04-01-83 APPLICANT'S ESTIt1ATED FUEL LOADING DATE AT CP ISSUANCE:

03-00-81 (LATEST) 10-01-84 APPLICANT'S CURRENT ESTIMATED COMMERCIAL OPERATION DATE: N/S f

CURRENT ESTIMATED PERCENT CONSTRUCTION COMPLETE: 22%

COMMENTS REGARDING CURRENT CONSTRUCTION STATUS: CONSTRUCTION HALTED ON UNIT 2 AS OF DECEMBER 31, 1979.

ESTIMATED ACTUAL ESTIMATED ACTUAL ESTIMATED START START COMPLETION COMPLETION % COMPLETE MOBILIZE AND PREPARE SITE:

05-03-74 06-00-74 100%

PLACE STRUCTURAL CONCRETE:

01-00-78 60%

INSTALL REACTOR PRESSURE VESSEL:

08-00-79 10%

INSTALL LARGE BORE PROCESS PIPE:

04-00-78 36%

INSTALL LARME BORE PIPE HANGERS, RESTRAINTS AND SHUBBERS:

10-00-79 15%

INSTALL SMALL BORE PIPE:

0%

INSTALL CABLE TRAY:

12-00-78 15%

INSTALL EXPOSED F.ETAL CONDUIT 0%

INSTALL POWER, CONTROL, INSTRUMENTATION AND SECURITY CABLE:

0%

INSTALL ELECTRICAL TERMINATIONS:

0%

CONDUCT REACTOR COLD HYDROSTATIC TEST:

0%

CONDUCT HOT FUNCTIONAL TEST:

N/A N/A N/A N/A N/A CONDUCT PREC? AND ACCEPTANCE TESTS NECESSARY FOR FUEL LOAD:

0%

e C0NSTRUCTION STATUS REPQRT PAGE NO: 2-046 NARRIS 1 NUCLEAR POWER PLANTS STATUS AS OF:

12-31-81

+

PLANT CHARACTERISTICSt KEY PERS0NNEL

-DOCKET NO:

05000400 CORPORATE CONTACT:

M. A. MCDUFFIE, SEN. V. PRESIDENT ENGINEERING & CONSTRUCTION CP NO. 8 DATE ISSUED: CPPR-158/ 01-27-78 CP EXPIRATION DATE:

06-01-84 CORPORATE ADDRESS:

411 FAYETTEVILLE STREET RALEIGH, NORTH CAROLINA 27602 APPLICANT:

CAROLINA POWER 8 LIGHT PLANT LOCATION:

20 MI SW OF RALEIGH, NC IE REGION:

2 CORPORATE PHONE NO:

(919) 836-6663 AE:

EBASCO NSSS:

WESTINGHOUSE CONSTRUCTOR:-

DANIEL INTERNATIONAL NRC LPM:

E. A.

LICITRA IE PROJECT INSPECTOR:

REACTOR TYPE:

PWR IE RESIDENT INSPECTOR:

G. F. MAXWELL DER (MWE):

0915 FUEL L0AD DATE CHANGES I N S P E C T I O N S T A T U S:

TIME PERIOD AS REPQRTED BY UTILITY OCT. 1981 - DEC. 1981 REPORT NEW REASON FOR CHANGE REPORT EEG DATE END DATE DATE SCHEDULE BEPORTED BY UTILITY HUMBER OF INSP.

OF INSP.

05-07-75 06-01-83 REVISED CURRENT ENERGY AND LOAD FORECAST.

8121 09-20-81 10-20-81 09-08-80 06-00-84 LOWER RATE GROWTH IN CUSTOMER DEMAND THAN 8122 17-81 11-20-81 PROJECTED.

8123 10-20-81 11-20-81 02-16-81 12-00-84 NO REASON PROVIDED.

8124 12-08-81 12-11-81 8125 11-20-81 12-20-81 INSPECTION REPORTS ARE AVAILABLE AT LOCAL PDR'S.

L0 CAL PUBLIC D0CUMENT R 0 0 M:

WAKE COUNTY PUBLIC LIBRARY 104 FAYETTEVILLE STREET RALEIGH, NORTH CAROLINA 27601

m..

4...

...m_.

~

i C0NSTRUCTION STA iUS REP 0RT PAGE NO: 2-047 HARRIS 1 NUCLEAR P0WER PLANTS STATUS AS OF:

12-31-81 i

C0NSTRUCTION 5 T A T U S:

APPLICANT'S CURRENT ESTIMATED FUEL LOADING DATE:

12-00-84 APPLICANTS CONSTRUCTION COMPLETION ESTIMATE AS APPLICANT'S PREVIOUS ESTIMATED FUEL LOADING DATE:

06-00-84 DEFINED IN CP: (EARLIEST)

APPLICANT'S ESTIMATED FUEL LOADING DATE AT CP ISSUANCE:

09-00-80 (LATEST)

APPLICANT'S CURRENT ESTIMATED COMMERCIAL OPERATION DATE: J9-01-85 CURRENT ESTIMATED PERCENT CONSTRUCTION COMPLETE: 55%

COMMENTS REGARDING CURRENT CONSTRUCTION STATUS: NRPV SET: EXCLUDE INTERNALS AND HEAD PACKAGE.

ESTIMATED ACTUAL ESTIMATED ACTUAL ESTIMATED START STAPT COMPLETION C0r1PLETION % CCMPLETE MOBILIZE AND PREPARE SITE:

01-14-74 01-1'-74 01-28-78 01-28-78 100%

PLACE STRUCTURAL CONCRETE:

01-28-78 01-28-78 02-01-84 78%

INSTALL REACTOR PRESSURE VESSEL M 12-01-79 04-15-80 04-01-80 08-29-80 100%

INSTALL LARGE BORE PROCESS PIPE:

04-01-79 04-01-79 08-01-84 45%

. INSTALL LARGE BORE PIPE NANGERS, RESTRAINTS AND SNUBBERS:

04-01-79 04-01-79 11-01-83 34%

INSTALL SMALL BORE PIPE:

04-01-79 04-01-79 08-01-84 32%

INSTALL CABLE TRAY:

n4-01-79 04-01-79 04-01-84 57%

INSTALL EXPOSED METAL CONDUIT:

04-01-79 04-01-79 04-01-84 58%

INSTALL POWER, CONTROL, INSTRUMENTATION AND SECURITY CABLE:

03-01-81 02-26-81 06-01-84 8%

INSTALL ELECTRICAL TERMINATIONS:

01-01-82 06-15-81 12-01-84 7%

CONDUCT REACTOR COLD HYDROSTATIC TEST:

05-01-84 06-01-84 0%

CONDUCT HOT FUNCTIONAL TEST:

08-01-84 10-01-84 0%

CONDUCT PREOP AND ACCEPTANCE TESTS NECESSARY FOR FUEL LOAD:

07-01-82 12-01-84 0%

t 4

2 1

+

w

'{

i l

C0NSTRUCTION STATUS REPQRT PAGE NO: 2-048 HARRIS 2 NUCLEAR P0WER PLANTS STATUS AS OF 12-31-81 PLANT CHARACTERISTICSt KEY P.E R S 0 N N F L:

DOCKET NO:

05000401 CORPORATE CONTACT:

M. A. MCDUFFIE, SEN. V. PRESIDENT.

CP NO. 4 DATE ISSUED: CPPR-159/ 01-27-78 ENGINEERING & CONSTRUCTION CP EXPIRATION DATE:

06-G1-86 CORPORATE ADDRESS:

411 FAYETTEVILLE STREET.

APPLICANT:

CAROLINA POWER 8 LIGHT RALEIGH, NORTH CAROLINA 27602.

1 PLANT LOCATION:

20 MI SW OF RALEIGH, NC IE REGION:

2 CORPORATE PHONE NO:

(919) 836-6663 1

AE:

EBASCO NSSS:

WESTINGHOUSE CONSTRUCTOR:

DANIEL INTERNATIONAL hRC LPM:

E. A. LICITRA 4

REACTOR TYPE:

PWR IE PROJECT INSPECiOR:

DER (MWE):

0915 IE RESIDENT INSPECTOR:

G. F. MAXWELL' i.

INSPECT ION STATUS FUEL L0A D DA T E CHANGES TIME PERIOD AS REP 0RTED BY U T I L I T Y:

OCT, 1981 - DEC. 1981 REPORT HEW REASON FOR CHANGE REPORT BEG DATE END DATE DATE SCHEDULE REPORTED BY UTILITY NVMBgg 0F INSP.

OF INSP.

05-07-75 06-01-85 REVISED CURRENT ENERGY AND LOAD FORECAST.

8121 N

09-20-81 10-20-81 01-00-80 06-01-86 NO REASON REPORTED.

8122 11-17-81 11-20-81 09-08-80 06-01-87 SLOWER RATE GROWTH IN CUSTOMER DEMAND i

8123 10-20-81 11-20-81 THAN PROJECTED.

8124 12-08-81 12-11-81 12-16-81 06-01-88 EXPANDED CONSERVATION AND LOAD MANAGEMENT 8125 11-20-81 12-20-81' PROGRAM.

INSPECTION REPORTS ARE AVAILABLE AT LOCAL PDR'S.

i t

i I

L0 CAL PUBLICD0CUMENT R00Mr WAKE COUNTY PUBLIC LIBRARY 104 FAYETTEVILLE STREET i

i RALEIGN, NORTH CAROLINA 27601 7

i i

.-..m..

_m m.

_.m

m. _. _

.~.

C0N5TRUCTI'0N STATUS REPQRT PAGE NJ: 2-049

'NARRIS 2 NUCLEAR P0WER PLANTS STATUS AS OF 12-31-81 C0N5TRUCTION S T A T-U S:

APPLICANT'S CURRENT ESTIMATED FUEL LOADING DATE:

06-01-88 APPLICANTS CONSTRUCTION COMPLETION ESTIMATE AS APPLICANT'S PREVIOUS ESTIMATED FUEL LOADING DATE:

06-01-87 DEFINED IN CP (EARLIEST)

APPLICANT'S ESTIMATED FUEL LOADING DATE AT CP ISSUANCE:

06-01-85 (LATEST)

~ APPLICANT'S CURRENT ESTIMATED COMMERCIAL OPERATION DATE: 03-01-89 i

CURRENT ESTIMATED PERCENT CONSTRUCTION COMPLETE:

4%

COMMENTS REGARDING CURRENT CONSTRUCTION STATUS:

u ESTIMATED ACTUAL ESTIMATED ACTUAL ESTINATED START START COMPLETION COMPLETION % COMPLETE MOBILIZE AND PREPARE SITE:

01-14-74 01-14-74 01-28-78 01-28-78 100%

j PLACE STRUCTURAL CONCRETE:

02-91-79 02-01-79 04-01-86 30%

- INSTALL REACTOR PRES $URE VESSEL:

09-01-85 01-01-85 0%

i INSTALL LARGE BORE PROCESS PIPE:

06-01-79 06-01-79 02-01-87 10%

INSTALL LARGE BORE PIPE HANOERS, RESTRAINTS AND SNUBBERS:

07-01-82 02-01-88 0%

i INSTALL SMALL BORE PIPE:

06-01-79 06-01-79 02-01-88 3%

INSTALL CABLE TRAY:

04-01-85 10-01-87 0%

INSTALL EXPOSED METAL CONDUIT:

04-01-85 10-01-87 0%

INSTALL POWER, CONTROL, INSTRUMENTATION AND SECURITY CABLE:

06-01-85 03-01-88 0%

INSTALL ELECTRICAL TERMINATIONS:

08-01-85 04-01-88 0%

CONDUCT REACTOR COLD HYDROSTATIC TEST:

11-01-87 12-01-87 0%

CONDUCT HOT FUNCTIONAL TEST 02-01-88 04-01-88 0%

CONDUCT PREOP AND ACCEPTANCE TESTS NECESSARY-FOR FUEL LOAD:

12-01-86 06-01-88 0%

1 s

1 C0NSTRUCTION STATUS REP 0RT PAGE NO: 2-050 HARTSVILLE A-1 NUCLEAR POWER PLANTS STATUS AS OF 12-31-81 PLANT CHARACTERI$ TICS:

KEY PERS0NNELa DOCKET NO.

-05000518 CORPORATE CONTACT:

G. KIMMONS, MANAGER CP NO. 8 DATE ISSUED: CPPR-150/ 05-09-77 0FFICE OF ENG. 8 CONSTRUCTION CP EXPIRATI3N DATE:

CORPORATE ADDRESS:

400 COMMERCE AVENUE i

APPLICANT:

TENNESSEE VALLEY AUTHORITY KNOXVILLE, TENNESSEE 37902 PLANT LOCATION:

40 MI E OF NASHVILLE, TN IE REGION:

2 CORPORATE PHONE NO:

(615) 632-2911 AE TENNESSEE VALLEY AUTHORITY NSSS:

GENERAL ELECTRIC CONSTRUCTOR:

TENNESSEE VALLEY AUTHORITY NRC LPM:

REACTOR TYPE:

BWR IE PROJECT INSPECTOR:

DER (MWE):

1205 IE RESIDENT INSPECTOR:

W. SWAN IN$PECTION STATUSt FUEL L0AD DATE CHANGE 5 TIME PERIOD AS REP 0RTED BY UTILITY:

OCT. 1981 - DEC. 1981 REPORT NEW REASON FOR CHANGE REPORT BEG DATE END DATE DAi! ___ SCHECULE EXPSRTED BY UTTLITY NUMBER 0F INSP.

OF INSP.

07-23-76 10-26-81 SLIPPAGE DUE TO REEVALUATION OF 8118 10-01-81 10-30-81 CONSTRUCTION SCHEDULE STATUS BY TVA.

8119 11-17-81 11-20-81 05-06-77 03-01-82 DELAY IN ISSUANCE OF LWA PART II.

8120 11-17-81 11-20-81 09-12-79 02-00-85 NO REASON NOTED.

8121 11-13-81 11-18-81 09-10-80 01-00-87 NO REASON REPORTED.

8122 11-02-81 11-30-81 08-14-81 01-00-90 NO REASON REPORTED.

8123 12-01-81 12-04-81 INSPECTION REPORTS ARE AVAILABLE AT LOCAL PDR'S.

L0 CAL PUBLIC D0CUMENT R00M:

STATE LIBRARY AND ARCHIVES 403 SEVENTH AVENUE, NORTH NASHVILLE, TENNESSEE 37219

C0NSTRUCTION STATUS REPQRT PAGE N08 2-051 HARTSVILLE A-1 NUCLEAR POWER PLANTS STATUS AS OF:

12-31-81 C0NSTRUCT ION STATUSt APPLICANT'S CURRENT ESTIMATED FUEL LOADING DATE:

01-01-90 APPLICANTS CONSTRUCTION COMPLETION ESTIMATE AS APPLICANT'S PREVIOUS ESTIMATED FUEL LOADING DATE:

01-00-87 DEFINED IN CP: (EARLIEST) 06-00-81 APPLICANT'S ESTIMATED FUEL LOADING DATE AT CP ISSUANCE:

06-00-81 (LATEST)

APPLICANT'S CURRENT ESTIMATED COMMERCIAL OPERATION DATE: 10-00-90 CURRENT ESTIMATED PERCENT CONSTRUCTION COMPLETE: 42%

CDP.MENTS REGARDING CURRENT CONSTRUCTION STATUS:

ESTIMATED ACTUAL ESTIMATED ACTUAL ESTIMATED START STARl_

ggMPLETION COMPLETION % COMPLETE MOBILIZE AND PREPARE SITE:

04-22-76 08-31-76 100%

PLACE STRUCTURAL CONCRETE:

08-15-77 12-18-85 80%

INSTALL REACTOR PRE 3SURE VESSEL:

12-17-79 02-28-80 100%

INSTALL LARGE BORE PROCESS PIPE:

08-27-79 10-08-87 34%

INSTALL LARGE BORE PIPE NANGERS, RESTRAINTS AND SHUBBERS:

08-01-79 11-08-87 14%

INSTALL SMALL BORE PIPE:

11-02-79 11-08-87 10%

INSTALL CABLE TRAY:

06-08-79 09-15-89 34%

INSTALL EXPOSED METAL CONDUIT:

03-24-80 01-23-87 3%

INSTALL POWER, CONTROL, INSTRUMENTATION AND SECURITY CABLE:

03-21-86 09-15-89 0%

INSTALL ELECTRICAL TERMINATIONS:

05-10-86 09-28-89 0%

CONDUCT REACTOR COLD NYDR0 STATIC TEST:

01-06-89 01-20-89 0%

CONDUCT NOT FUNCTIONAL TEST:

N/A N/A N/A CONDUCT PREOP AND ACCEPTANCE TESTS HECESSARY FOR FUEL LOAD:

12-18-87 01-00-90 0%

C0N$TRUCTI0N

$TATUS REPQRT PAGE NO: 2-052 NARTSVILLE A-2 NULLEAR POWER PLANTS STATUS AS OF:

12-31-81 PLANT CNARACTERISTICSt KEY P E R S 0 N N E L:

DOCKET NO:

05000519 CORPORATE CONTACT:

G. KIMMONS, MANAGER CP HO. 8 DATE ISSUED: CPPR-151/ 05-09-77 0FFICE OF ENG. 8 CONSTRUCTION CP EXPIRATION DATE:

CORPORATE ADDRESS:

400 COMMERCE AVENUE APPLICANT:

TENNESSEE VALLEY AUTHORITY KNOXVILLE, TENNESSEE 37902 PLANT LOCATION:

40 MI E OF NASNVILLE, TN IE REGION:

2 CORPORATE PHONE NO:

(615) 632-2911 AE:

TENNESSEE VALLEY AUTHORITY NSSS:

GENERAL ELECTRIC CONSTRUCTOR:

TENNESSEE VALLEY AUTHORITY NRC LPM:

REACTOR TYPE:

BWR IE PROJECT INSPECTOR:

DER (MWE):

1205 IE RESIDENT INSPECTOR:

W. SWAN INSPECTICH STATUS:

FUEL L0AD DATE CHANGES TIME PERIOD AS REPORTED BY U T I L.I T Y OCT, 1981 - DEC, 1981 REPORT NEW REASON FOR CHANGE REPGRT BEG DATE END DATE DATE SCHEDULE REPORTED BY UTILITY NUMBER OF INSP.

OF INSP.

07-23-76 10-25-82 SLIPPAGE DUE TO REEVALUATION OF 8118 10-01-81 10-30-81 CONSTRUCTION SCHEDULE STATUS BY TVA.

8119 11-17-81 11-20-81 05-06-77 03-01-83 DELAY IN ISSUANCE OF LWA PART II.

8120 11-17-81 11-20-81 09-12-79 02-00-86 NO REASON NOTED.

8121 11-13-81 11-18-81 09-10-80 10-00-87 HO REASON PROVIDED.

8122 11-02-81 11-30-81 08-14-81 01-00-91 NO REASON PROVIDED.

8123 12-01-81 12-04-81 INSPECTION REPORTS ARE AVAILABLE AT LOCAL PDR'S.

L0 CAL PUBLIC D0CUMENT R 0 0 M:

STATE LIBRARY AND ARCHIVES 403 SEVENTH AVENUE, NORTH NASHVILLE, TENNESSEE 37219

oi r

C0NSTRUCTION 5TATUS REPQRT PAGE NO 2-053 HARTSVILLE A-2 NUCLEAR P0WER PLANTS STATUS AS OF 12-31-81 C0NSTRUCTION S T A T U S:

APPLICANT'S CURRENT ESTIMATED FUEL LOADING DATE:

01-01-91 APPLICANTS CONSTRUCTION COMPLETION ESTIMATE AS APPLICANT'S PREVIOUS ESTIMATED FUEL LOADING DATE:

10-00-87 DEFINED IN CP: (EARLIEST) 06-00-82 APPLICANT'S ESTIMATED FUEL LOADING DATE AT CP ISSUANCE:

06-00-82 (LATEST)

APPLICANT'S CURRENT ESTIMATED COMMERCIAL OPERATION DATE: 10-00-91 CURRENT ESTIMATED PERCENT CONSTRUCTION COMPLETE: 32%

COMMENTS REGARDING CURRENT CONSTRUCTION STATUS:

ESTIMATED ACTUAL ESTIMATED

' ACTUAL ESTIMATED START START COMPLETIQH COMPLETION % COMPLETE MOBILIZE AND PREPARE SITE:

04-22-76 03-31-77 100%

u PLACE STRUCTURAL CONCRETE:

05-15-78 02-03-87 06-14-79 65%

INSTALL REACTOR PRESSURE VESSEL:

12-18-80 03-26-81 100%

f INSTALL LARGE BORE PROCESS PIPE:

12-28-79 01-02-89 25%

INSTALL LARGE BORE PIPE NANGERS, RESTRAINTS AND SNUBBERS:

05-19-80 01-30-89 4%

INSTALL SMALL BORE PIPE:

07-18-80 01-30-89 4%

INSTALL CABLE TRAY:

01-09-81 06-14-90 6%

INSTALL EXPOSED METAL CONDUIT:

01-25-83 02-25-88 0%

INSTALL POWER CONTROL, INSTRUMENTATION AND SECURITY CABLE:

02-03-87 04-27-90 0%

INSTALL ELECTRICAL TERMINATIONS:

05-15-87 05-08-90 0%

CONDUCT REACTOR COLD NYDR0 STATIC TEST:

04-06-90 04-20-90 0%

CONDUCT NOT FUNCTIONAL TEST:

N/A N/A N/A CONDUCT PREOP AND ACCEPTANCE TESTS HECESSARY FOR FUEL LOAD:

09-28-88 01-01-91 0%

5

v l

l C0NSTRUCTION STATUS REP 0RT PAGE NO: 2-054 HARTSVILLE B-1 NUCLEAR POWER PLANTS STATUS AS OF 12-31-81 PLANT C H A R A C T E R I S T I C S:

KEY PERS0NNELa DOCKET NO:

05000520 CORPORATE CONTACT:

G. KIMMONS, MANAGER i

CP NO. & DATE ISSUED: CPPR-152/ 05-09-77 0FFICE OF ENG. & CONSTRUCTION CP EXPIRATION DATE:

CORPORATE ADDRESS:

400 COMMERCE AVENUE APPLICANT:

TENNESSEE VALLEY AUTHORITY KNOXVILL E, TENNESSEE 37902 PLANT LOCATION:

40 MI E OF NASHVILLE, TN IE REGION:

2 CORPORATE PHONE NO:

(615) 632-2911 AE:

TENNESSEE VALLEY AUTHORITY HSSS:

GENERAL ELECTRIC CONSTRUCTOR:

TENNESSEE VALLEY AUTHORITY NRC LPM:

REACTOR TYPE:

BWR IE PROJECT INSPECTOR:

DER (MWE):

1205 IE RESIDENT INSPECTOR:

W. SWAN INSPECT ION S T A T U S:

FUEL L0AD DATE CNANGES TIME PERIOD AS REP 0RTED BY UTIL1TY OCT. 1981 - DEC. 1981 REPORT HEW REASON FOR CHANGE REPORT BEG DATE END DATE DATE SCHEDULE REPORTED BY UTILITY NUMBER OF INSP.

OF INSP.

07-23-76 04-26-82 SLIPPAGE DUE TO REEVAll!ATICH OF 8118 10-01-81 10-30-81 CONSTRUCTION SCHEDULE STATUS BY TVA.

8119 11-17-81 11-20-81 05-06-77 09-01-82 DELAY IN ISSUANCE OF LWA PART II.

8120 11-17-81 11-20-81 09-12-79 03-00-88 NO REASOM NOTED.

8121 11-13-81 11-18-81 09-10-80 07-00-94 NO REASGN PROVIDED.

8122 11-02-81 11-30-81 09-30-81 N/S DEFERRED.

8123 12-01-81 12-04-81 INSPECTION REPORTS ARE AVAILABLE AT LOCAL PDR'S.

i L0 CAL PUBLIC D0CUMENT R 0 0 M:

STATE LIBRARY AND ARCHIVES' 403 SEVENTH AVENUE, NORTH HASHVILLE, TENNESSEE 37219 e

C0NSTRUCTION STATUS REP 0RT PAGE NO: 2-055 HARTSVILLE B-1 NUCLEAR POWER PLANTS STATUS.AS OF:

12-31-81 C0NSTRUCT ION S 's A T U S:

APPLICANT'S CURRENT ESTIMATED FUEL LOADING DATE:

N/S APPLICANTS CONSTRUCTION COMPLETION ESTIMATE AS APPLICANT'S PREVIOUS ESTIMATED FUEL LOADING DATE:

07-00-94 DEFINED IN CP: (EARLIEST) 06-00-81 APPLICANT'S ESTIMATED FUEL LOADING DATE AT CP ISSUANCE:

12-00-81 (LATEST)

APPLICANT'S CURRENT ESTIMATED COMMERCIAL OPERATION DATE: N/S CURRENT ESTIMATED PERCENT CONSTRUCTION COMPLETE:

17%

COMMENTS REGARDING CURRENT CONSTRUCTION STATUS: PROJECT DEFERRED.

i ESTIMATED ACTUAL ESTIMATED ACTUAL ESTIMATED START START COMPLETIQH COMPLETION % COMPLETE MOBILIZE AHD PREPARE SITE:

04-22-76 03-31-77 100%

PLACE STRUCTURAL CONCRETE:

09-29-77 INSTALL REACTOR PRESSURE VESSEL:

INSTALL LARGE BORE PROCESS PIPE:

INSTALL LARGE BORE PIPE HANGERS, RESTRAINTS AND SHUBBERS:

INSTALL SMALL BORE PIPE:

INSTALL CABLE TRAY:

INSTALL EXPOSED METAL CONDUIT:

INSTALL POWER, CONTROL, INSTRUMENTATION AND SECURITY CABLE:

INSTALL ELECTRICAL TERMINATI0HS:

CONDUCT REACTOR COLD HYDROSTATIC TEST:

CONDUCT HOT FUNCTIONAL TEST:

CONDUCT PREOP AND ACCEPTANCE TESTS NECESSARY FOR FUEL LOAD:

^

C0N$TRUCTION STATUS REPORT PAGE NO: 2-056 HARTSVILLE B-2 NUCLEAR POWER PLANTS STATUS AS OF 12-31-81 PLANT C H A R A C T E R I 5 T I C S:

KEY PERSONNELa DOCKET NO:

05000521 CORPORATE CONTACT:

G.

KIMMONS, MANAGER CP NO. 8 DATE ISSUED: CPPR-153/ 05-09-77 0FFICE OF ENG. & CONSTRUCTION CP EXPIRATION DATE:

CORPORATE ADDRESS:

400 COMMERCE AVENUE APPLICANT:

TENNESSEE VALLEY AUTHORITY KNOXVILLE, TENNESSEE 37902 PLANT LOCATION:

40 MI E OF HASNVILLE, TH IE REGION:

2 CORPORATE PHONE NO (615) 632-2911 AE TENNESSEE VALLEY AUTHORITY NSSS:

GENERAL ELECTRIC CONSTRUCTOR:

TENNESSEE VALLEY AUTHORITY NRC LPM:

REACTOR TYPE:

BWR IE PROJECT INSPECTOR:

DER (MWE):

1205 IE RESIDENT INSPECTOR:

W. SWAN INSPECTION STATUSt FUEL L0AD DATE CHANGES TIME PERIOD AS REPORTED BY UTILITY:

OCT. 1981 - DEC. 1981 REPORT NEW REASON FOR CHANGE REPORT BEG DATE END DATE DATE SCHEDULE REPORTED BY UTILITY NUMSFR OF INSP.

GF INSP.

07-23-76 04-26-83 SLIPPAGE DUE TO REEVALUATION OF 8118 10-01-81 10-30-81 CONSTRUCTION SCHEDULE STATUS BY TVA.

8119 11-17-81 11-17-81 05-06-77 09-01-83 DELAY IN ISSUANCE OF LWA PART II.

8120 11-17-81 11-20-81 09-12-79 03-00-89 NO REASON NOTED.

8121 11-13-81 11-18-81 09-10-80 07-0P-95 NO REASON PROVIDED.

8122 11-02-81 11-30-81 09-30-81 N/S DEFERRED.

8123 12-01-81 12-04-81 INSPECTION REPORTS ARE AVAILABLE AT LOCAL PDR'S.

i l

I l

I L0 CAL PUBLIC D0CUMENT R 0 0 M:

STATE LIBRARY AND ARCHIVES 403 SEVENTH AVENUE, NORTH i

NASHVILLE, TENNESSEE.37219 I

C0NSTRUCTION STATUS REP 0RT PAGE NO: 2-057 NARTSVILLE B-2 NUCLEAR POWER PLANTS STATUS AS OF 12-31-81 C0NSTRUCTION

$TATUSt APPLICANT'S CURRENT ESTIMATED FUEL LOADING DATE:

N/S-APPLICANTS CONSTRUCTION COMPLETION ESTIMATE AS APPLICANT'S PREVIOUS ESTIMATED FUEL LOADING DATE:

07-00-95 DEFINED IN CP: (EARLIEST)

APPLICANT'S ESTIMATED FUEt LOADING DATE AT CP ISSUANCE:

12-00-82 (LATEST)

APPLICANT'S CURRENT ESTIMATED COMMERCIAL OPERATION DATE: N/S CURRENT ESTIMATED PERCENT CONSTRUCTION COMPLETE:

7%

COMMENTS REGARDING CURRENT CONSTRUCTION STATUS: PROJECT DEFERRED.

ESTIMATED ACTUAL ESTIMATED ACTUAL ESTIMATED START START

[pMPLETION COMPLETION % COMPLETE MOBILIZE AND PREPARE SITE:

04-22-76 03-31-77 100%

PLACE STRUCTURAL CONCRETE:

09-29-77

-INSTALL REACTOR PRESSURE VESSEL:

INSTALL LARGE BORE PROCESS PIPE:

INSTALL LARGE BORE PIPE HANGERS, RESTRAINTS AND SHUBBERS:

INSTALL SMALL BORE PIPE:

INSTALL CABLE TRAY:

INSTALL EXPOSED METAL CONDUIT:

INSTALL POWER, CONTROL, INSTRUMENTATION AND SECURITY CABLE:

4 INSTALL ELECTRICAL TERMINATIONS:

CONDUCT REACTOR COLD HYDROSTATIC TEST CONDUCT HOT FUNCTIONAL TEST:

CONDUCT PREOP AND ACCEPTANCE TESTS HECESSARY FOR FUEL LOAD:

S

C0NSTRUCTION STATUS REPQRT PAGE NO: 2-058 HOPE CREEK 1 NUCLEAR P0WER PLANTS STATUS AS OF:

12-31-81 PLANT CHARACTERISTICSt KEY PERS0NNELa DOCKET NO:

05000354 CORPORATE CONTACT:

T. J. MARTIN, VICE PRESIDENT CP NO. 4 DATE ISSUED: CPPR-120/ 11-04-74 ENGINEERING & CONSTRUCTION CP EXPIRATION DATE:

12-31-86 CORPORATE ADDRESS:

80 PARK PLAZA APPLICANT:

PUBLIC SERVICE ELECTRIC 4 GAS NEWARK, NEW JERSEY 07101 PLANT LOCATION:

18 MI SE OF WILMINGTON, DEL IE REGION:

1 CORPORATE PHONE NO:

(201) 430-8316 AE:

BECHTEL NSSS:

GENERAL ELECTRIC CONSTRUCTOR:

BECHTEL NRC LPM:

R. GILBERT REACTOR TYPE:

BWR IE PROJECT INSPECTOR:

DER (MWE):

1067 IE RESIDENT INSPECTOR:

W. N. BATEMAN INSP ECTION-STA T U S:

FUEL L0AD DATE CHANGES TIME PERIOD AS REPQRTED BY UTILITY OCT, 1981 - DEC, 1981 REPORT NEW REASON FOR CHANGE REPORT BEG DATE END DATE DATE SCHEDULE REPORTED BY UTILITY HyMSER OF INSP.

OF INSP.

04-00-75 06-00-82 DELAY IN CBTAINING STATE OF NEW JERSEY 81-15 10-05-81 11-01-81 COASTAL AREAS FACILITY PERMIT.

81-16 11-02-81 11-30-81 05-00-76 12-00-82 REEVAlllATION OF DEALY CAUSED BY N. J.

81-17 11-12-81 11-12-81 COASTAL AREAS FACILITY PERMIT.

8 1-18 12-01-81 01-03-82 10-00-76 11-00-83 RE-EXAMINATION OF THE EFFORT REQUIRED TO CONSTRUCT THE PLANT.

02-00-80 11-00-84 NO REASON GIVEN.

08-00-80 06-00-86 LOWER THAN ANTICIPATED ELECTRICITY SALES Inspection Reoorts are available at local PDRs.

GROWTH, CONTINUED INFLATION, AND RECESSIONARY TRENDS IN ECONOMY.

L0 CAL PUBLIC D0CUMENT R 0 0 Mr SALEM FREE PUBLIC LIBRARY i

112 WEST BROADWAY ~

SALEM, NEW JERSEY 08079 i

I

C0NSTRUCTION

$TATUS REPORT PAGE NO: 2-059 NOPE CREEK 1 NUCLEAR POWER PLANTS STATUS AS OF 12-31-81

.C0NSTRUCTION STATUSt APPLICANT'S CURRENT ESTIMATED FUEL LOADING DATE:

C6-00-86 APPLICANTS CONSTRUCTION COMPLETION ESTIMATE AS APPLICANT'S PREVIOUS ESTIMATED FUEL LOADING DATE:

11-00-84 DEFINED IN CP: (EARLIEST)

APPLICANT'S ESTIMATED FUEL LOADING DATE AT-CP ISSUANCE:

06-00-81 (LATEST) 12-31-86 APPLICANT'S CURRENT ESTIMATED COMMERCIAL OPERATION DATE: 12-00-86 CURRENT ESTIMATED PERCENT CONSTRUCTION COMPLETE: 40%

COMMENTS REGARDING CURRENT CONSTRUCTION STATUS: MREACTOR BUILDING FOUNDATION TO RPV PEDESTAL.

3 ESTIMATED ACTUAL

. ESTIMATED ACTUAL ESTIMATED START START COMPLETION COMPLETION % COMPLETE MOBILIZE AND PREPARE SITE:

02-00-76 03-00-76 08-00-77 08-00-77 100%

PLACE STRUCTURAL CONCRETE M 07-00-77 08-00-77 10-00-79 09-00-79 100%

INSTALL REACTOR PRESSURE VESSEL:

11-00-80 11-00-80 12-00-80 12-00-80 100%

INSTALL LARGE BORE PROCESS PIPE:

04-00-79 04-00-79 04-00-85 48%

INSTALL LARGE BORE PIPE NANGERS, RESTRAINTS AND SNUEBERS:

04-00-79 04-00-79 04-00-85 15%

INSTALL SMALL BORE PIPE:

12-00-81 07-00-81 01-00-85 2%

INSTALL CABLE TRAY:

08-00-79 08-00-79 03-00-85 32%

INSTALL EXPOSED METAL CONDUIT:

09-00-81 05-00-81 04-00-85 4%

INSTALL POWER, CONTROL, INSTRUMENTATION AND SECURITY CABLE:

02-00-83 04-00-85 0%

INSTALL ELECTRICAL TERMINATIONS 03-00-83 05-00-85 0%

CONDUCT REACTOR COLD NYDR0 STATIC TEST:

01-00-86 01-00-86 0%

CONDUCT NOT FUNCTIONAL TEST:

N/A N/A N/A N/A N/A CONDUCT PREOP AND ACCEPTANCE TESTS HECESSARY FOR FUEL LOAD:

03-00-86

'06-00-86 0%

i

C0N$TRUCTION STATUS REPQRT PAGE NO 2-060 LASALLE 1 NUCLEAR POWER PLANTS STATUS AS CF2 12-31-81 PLANT CHARACTERISTIC'S KEY PERS0NN EL DOCKET NO:

05000373 CORPORATE CONTACT:

B.

LEE, JR., VICE PRESIDENT CP NO. 8 DATE ISSL'ED: CPPR-99 / 09-10-73 CP EXPIRATION DA7E:

03-31-80 CORPORATE ADDRESS:

P. O.

BOX 767 APPLICANT:

COMMONWEALTH EDISON CHICAGO, ILLINDIS 60690 PLANT LOCATION:

11 MI SE OF OTTAWA, ILL IE REGION:

3 CORPORATE PHONE NO:

(312) 294-3103 AE SARGENT & LUNDY NSSS:

GENERAL ELECTRIC CONSTRUCTOR:

COMMONWEALTH EDISON NRC LPM:

A.

BOURNIA REACTOR TYPE:

BWR IE PROJECT INSPECTOR:

H. WESCOTT DER (MWE):

1078 IE RESIDENT INSPECTOR:

R. WALKER INSPECTION STATUS FUEL L0AD DATE CHANGES TIME PERIOD AS REP 0RTED BY UTILITY:

OCT. 1981 - DEC, 1981 REPORT NEW REASON FOR CHANGE REPORT BEG DATE END DATE DATE SCHEDULE REPORTED BY UTILITY NUMBER OF INSP.

OF INSP.

04-01-76 LICENSING DELAYS.

8137 10-13-81 10-15-81 05-01-77 LICENSING DELAYS /PUBLIC HEARINGS.

8138 10-08-81 10-22-81 08-01-78 PUBLIC HEARINGS.

8139 10-05-81 10-16-81 08-03-76 11-00-78 CONTAINMENT DESIGN REVISIONS.

8140 10-04-81 11-13-81 04-20-77 03-00-79 REASSESSMENT OF CONSTRUCTION SCHEDULE 8141 11-03-81 11-04-81 STATUS.

8142 11-04-81 11-06-81 05-04-79 07-01-79 INCORPORATION OF KWU QUENCHER INTO PLANT 8146 12-09-81 12-10-81 DESIGN.

09-24-79 06-00-80 DESIGN DELAYS AND CONSTRUCTION DELAYS Inspection Reports are available at local PDRs.

CAUSED BY COMPLEXITY OF INCLUDING MARK II CONTAINMENT HYDRODYNAMIC LOADS.

05-14-80 09-00-80 NO REASON PROVIDED.

09-15-80 12-00-80 NO REASCH PROVIDED.

01-14-81 05-00-81 NO REASON PROVIDED.

09-30-81 12-00-81 DESIGN AND CONSTRUCTION DELAYS TO INSTALL REDESIGNED PIPE SUPPORTS AND TO INCLUDE CHANGES FOR REVISED LOADS.

12-31-81 03-15-82 ADDITIONAL TIME IS REQUIRED TO COMPLETE PREOPERATIONAL TESTS, CLEAN NRC OPEN ITEMS AND CLOSE OUTSTANDING DEFICIENCIES.

L0 CAL PUBLIC D0CUMENT R00M ILLINDIS VALLEY COMMUNITY COLLEGE RURAL ROUTE NO. 1 OGLCSBY, ILLINDIS 16348

-a

C0NSTRUCTION STATUS REPORT PAGE NO: 2-061 LASALLE 1 NUCLEAR POWER PLANTS STATUS AS OF:

12-31-81 C0NSTRUCTION S T A T U S:

APPLICANT'S CURRENT ESTIMATED FUEL LOADING DATE:

03-15-82 APPLICANTS CONSTRUCTION COMPLETION ESTIMATE AS APPLICANT'S PREVIOUS ESTIMATED FUEL LOADING DATE:

12-00-81 DEFINED IN CP (EARLIEST)

APPLICANT'S ESTIMATED FUEL LOADING DATE AT CP ISSUANCE:

03-01-75 (LATEST) 04-30-82 APPLICANT'S CURRENT ESTIMATED COMMERCIAL OPERATION DATE: 06-30-82 CURRENT ESTIMATED PERCENT CONSTRUCTION COMPLETE: 99%

COMMENTS REGARDING CURRENT CCHSTRUCTION STATUS:

ESTIMATED ACTUAL ESTIMATED ACTUAL ESTIMATED START START COMPLETION CpMPLETION % COMPLETE MOBILIZE AND PREPARE SITE:

10-00-73 06-00-74 100%

PLACE STRUCTURAL CONCRETE:

06-00-74 09-00-76 100%

INSTALL REACTOR PRESSURE VESSEL:

09-00-76 10-00-76 100%

INSTALL LARGE BORE PROCESS PIPE:

11-00-76 07-00-78 100%

INSTALL LARGE BORE PIPE HANGERS, RESTRAINTS AND SHUBBERS:

03-00-76 01-00-82 99%

INSTALL SMALL BORE PIPE:

03-00-76 12-00-81 12-00-81 100%

IHSTALL CABLE TRAY:

02-00-76 09-00-80 100%

INSTALL EXPOSED METAL CONDUIT:

02-00-76 09-00-81 100%

INSTALL POWER, CONTROL,' INSTRUMENTATION AND SECURITY CABLE:

01-00-77 31-00-82 99%

INSTALL ELECTRICAL TERMINATIONS:

01-00-77 01-00-82 99%

CONDUCT REACTOR COLD HYDROSTATIC TEST:

11-00-80 11-00-80 100%

CONDUCT HOT FUNCTIONAL TEST:

N/A N/A N/A N/A N/A CONDUCT PREOP AND ACCEPTANCE TESTS NECESSARY FOR FUEL LOAD:

05-00-77 03-00-82 95%

C0NSTRUCTION STATUS REPORT PAGE NO: 2-062 LASALLE 2 NUCL EAR POWER PLANTS STATUS AS OF:

12-31-81 PLANT CHARACT E R I S T I C S:

KEY PERSONN E L:

DOCKET NO:

05000374 CORPORATE CONTACT:

B. LEE, JR., VICE PRESIDENT CP NO. & DATE ISSUED: CPPR-100/ 09-10-73 CP EXPIRATION DATE:

12-31-30 CORPORATE ADDRESS:

P.

O.

BOX 767 APPLICANT:

COMMONWEALTH EDISON CHICAGO, ILLINDIS 6069C i

PLANT LOCATION:

11 MI SE OF OTTAWA, ILL IE REGION:

3 CORPORATE PHONE NO:

(312) 294-3103 AE:

SARGENT & LUNDY NS$$:

GENERAL ELECTRIC CONSTRUCTOR:

COMMONWEALTH EDISON NRC LPM:

A.

BOURNIA REACTOR TYPE:

BWR IE PROJECT INSPECTOR:

H. WESCOTT DER (MWE):

1078 IE RESIDENT INSPECTOR:

R. WALKER IN5PECTION S T A T U 5:

FUEL L0AD DATE CHANGES TIME PERIOD AS REPORT ED PY UT IL I T Y:

OCT, 1981 - DEC. 1981 REPORT NEW REASON FOR CHANGE REPORT BEG DATE END DATE DATE SCHEDULE REPORTED BY UTILITY NUMBER OF INSP.

OF INSP.

09-01-76 LICENSING DELAYS.

8118 10-13-81 10-15-81 10-01-77 LICENSING DELAYS /PUBLIC HEARINGS.

8119 11-03-81 11-04-81 10-15-73 01-01-79 PUBLIC HEARINGS.

8120 11-04-81 11-06-81 10-17-74 06-01-79 ECONOMIC REASONS.

04-20-77 03-00-80 REASSESSMENT OF CONSTRUCTION SCHEDULE Inspection Reports are available at local PDRs.

STATUS.

09-24-79 06-00-81 DESIGN DELAYS AND CONSTRUCTION DELAYS CAUSED BY COMPLEXITY OF INCLUDING MARK II CONTAINMENT HYDRODYNAMIC LOADS.

05-14-80 12-00-81 NO REASON PROVIDED.

01-14-81 05-00-82 NO REASON PROVIDED.

09-30-81 12-00-82 FOCUS ON UNIT 1 ALTERATIONS WHICH REFLECT ON UNIT 2 INSTALLATION.

L0 CAL PUBLIC D0CUMENT R 0 0 M:

ILLINDIS VALLEY COMMUNITY COLLEGE RURAL ROUTE NO. 1 OGLESBY, ILLINOIS 16348

- - -.~_

-.. _ - _ -.~...

... -. ~....-_-_

C0NSTRUCTION STATUS REPORT PAGE NO: 2-063 LASALLE 2 NUCLEAR POWER PLANTS STATUS,AS OF:

12-31-81 i

C0NSTRUCTION S T A T U S:

APPLICAHf'S CURRENT ESTIMATED FUEL LOADING DATE:

12-00-82 APPLICANTS CONSTRUCTION COMPLETION ESTIMATE AS APPLICANT'S PREVIOUS ESTIMATED FUEL LOADING DATE:

05-00-82 DEFINED IN CP: (EARLIEST)

. APPLICANT'S ESTIMATED FUEL LOADING DATE AT CP ISSUANCE:

08-01-75 (LATEST) 03-31-82 APPLICANT'S CURRENT ESTIMATED COMMERCIAL OPERATION DATE: 06-00-83 CURRENT ESTIMATED PERCENT CONSTRUCTION COMPLETE: 84%

COMMENTS REGARDING CURRENT CONSTRUCTION STATUS:

ESTIMATED ACTUAL ESTIMATED ACTUAL ESTIMATED START START COMPLETION COMPLETION % COMPLETE MOSILIZE AND PREPARE SITE:

10-00-73 07-00-74 100%

' PLACE STRUCTURAL CONCRETE:

07-00-74 09-00-76 100%

INSTALL REACTOR PRESSURE VESSEL:

11-00-76 11-00-76 100%

INSTALL LARGE BORE PROCESS PIPE:

11-00-76 02-00-82 99%

INSTALL LARGE BORE PIPE HANGERS, RESTRAINTS AND SHUBBERS:

01-00-77 11-00-82 39%

INSTALL SMALL BORE PIPE:

11-00-76 06-00-82 89%

j INSTALL CABLE TRAY:

01-00-77 01-00-82 99%

INSTALL EXPOSED METAL CONDUIT:

01-00-77 09-00-82 76%

L INSTALL POWER, CONTROL, INSTRUMENTATION AND SECURITY CABLE:

02-00-78 10-00-82 88%

i INSTALL ELECTRICAL TERMINATIONS:

02-00-78 10-00-82 67%

CONDUCT REACTOR COLD HYDROSTATIC TEST:

05-00-82 05-00-82 0%

CONDUCT HOT FUNCTIONAL TEST:

N/A N/A N/A N/A N/A L

CONDUCT PREOP AND ACCEPTANCE TESTS NECESSARY FOR FUEL LOAD:

02-00-82 12-00-82 0%

i y

4 4

[

C0NSTRUCTION STATUS REPORT PAGE NO: 2-064 LIMERICK 1 NUCLEAR POWER PLANTS STATUS AS OF:

12-31-81 l

PLANT CHARACTER I S T I C 5:

KEY PERSONNEL:

DOCKET NO:

05000352 CORPORATE CONTACT:

V.

S. BOYER, SENIOR VICE PRESIDENT CP NO. & DATE ISSUED: CPPR-106/ 06-19-74 NUCLEAR POWER CP EXPIRATION DATE:

10-01-85 CORPORATE ADDRESS:

PHILADELPHIA ELECTRIC COMPANY APPLICANT:

PHILADELPHIA ELECTRIC 2301 MARKET STREET PLANT LOCATION:

35 MI NW OF PHILADELPHIA. PA PHILADELPHIA. PENNSYLVANIA 19101 IE REGION:

1 CORPORATE PHONE NO:

(215) 841-4500 AE2 BECHTEL NSSS:

GENERAL ELECTRIC CONSTRUCTOR:

BECHTEL NRC LPM:

H. ABELSON REACTOR TYPE:

BWR IE PROJECT INSPECTOR:

DER (MWE):

1065 IE RESIDENT INSPECTOR:

J. P. DURR INSPECTION STATUSt FUEL L0AD DATE CHANGES TIME PERIOD AS R EPQRTED BY U T I L I T Y:

OCT, 1981 - DEC, 1981 REPORT NEW REASON FOR CHANGE REPORT BEG DATE END DATE DATE SCHEDULE REPORTED BY UTILITY NVMSER OF INSP.

OF IN1Pm 09-27-74 10-01-80 DELAY ENTIRELY ATTRIBUTABLE TO FINANCING 81-16 10-01-81 11-30-81 PROBLEMS.

81-17 12-01-81 01-08-82 10-15-75 08-01-80 SCHEDULE REFINEMENT AND BUDGET l

ADJUSTMENTS.

l 05-24-76 10-01-82 HIGHER CAPITAL COSTS AND LOWER THAN EXPECTED DEMAND FOR ELECTRICITY.

Inspection Reports are available at local PDRs.

09-23-80 10-00-83 INCREASE OF SCOPE DUE TO DESIGN CHANGES S NEW REGULATORY REQUIREMENTS, DESIGN PROBLEMS ASSOCIATED W/ MARK II CONTAINMENT, REFINEMENT OF ESTIMATES, AND LIMITS CN YEARLY CAPITAL AVAILABlE.

02-20-81 10-00-84 REFINEMENT OF MANHOUR ESTIMATES AND DURATIONS REQUIRED TO COMPLETE REMAINING EN3INEERING AND FIELD WORK.

L0 CAL PUBLIC D0CUMENT R 0 0 M:

POTTSTOWN PUBLIC LIBRARY 500 HIGH STREET POTTSTOWN, PENNSYLVANIA 19464 l

l l

l l

.______________._______._m

.mm.

_m t

4 C0NSTRUCTION STATUS REPQRT PAGE NO:-2-065

' LIMERICK 1 NUCLEAR POWER PLANTS STATUS AS OF2 12-31-81 C0NSTRUCTION STATUSt APPLICANT'S CURRENT' ESTIMATED FUEL LOADING DATE:

10-00-84 APPLICANTS CONSTRUCTION COMPLETION ESTIMATE AS APPLICANT'S PREVIOUS-ESTIMATED FUEL LOADING DATER 10-00-83 DEFINED IN CPt (EARLIEST) 10-00-83 APPLICANT'S ESTIMATED FUEL LOADING DATE AT CP ISSUANCE:

04-00-79 (LATEST) 10-00-85 i

APPLICANT'S CURRENT ESTIMATED COMMERCIAL OPERATION DATE: 04-01-85 CURRENT ESTIMATED PERCENT CONSTRUCTION COMPLETE: 68%

COMMENTS REGARDING CURRENT CONSTRUCTION STATUS 2 WE CONTINUE TO REPORT THE OVERALL COMPLETION PERCENTAGES BASED ON ON TOTAL SCOPE AND MANHOUR EXPENDITURES.

l ESTIMATED ACTUAL ESTIMATED ACTUAL ESTIMATED STARI__

START COMPLETICH COMPLETI13 % COMPLETE MOBILIZE AND PREPARE SITE:

05-00-7u 05-00-70 G9-00-74 09-00-74 100%

PLACE STRUCTURAL CONCRETE:

07-00-74 07-00-74 11-00-80 11-00-80 100%

INSTALL. REACTOR PRESSURE VESSEL:

11-00-76 11-00-76 12-00-76 12-00-76 100%

4 INSTALL LARGE BORE PROCESS PIPE:

01-00-76 01-00-76 02-00-83 81%

INSTALL LARGE BORE PIPE HANGERS, RESTRAINTS AND SNUBBERS:

01-00-76 01-00-76 04-00-83 74%

INSTALL SMALL BORE PIPE:

01-00-77 01-00-77 06-00-83 67%

INSTALL CABLE TRAY:

01-00-76 01-00-76 02-00-83 98%

INSTALL EXPOSED METAL CONDUIT:

02-00-76 02-00-76 11-00-83 57%

INSTALL POWER, CONTROL, INSTRUMENTATION AND SECURITY CABLE:

01-00-81 01-00-81 01-00-84 19%

INSTALL ELECTRICAL TERMINATIONS:

01-00-81 01-00-81 03-00-84 15%

CONDUCT REACTOR COLD HYDROSTATIC TESTt 11-00-83 11-00-83 0%

l CONDUCT NOT FUNCTIONAL TEST

  • N/A N/A N/A N/A N/A CONDUCT PREOP AND ACCEPTANCE TESTS NECESSARY FOR FUEL LOAD
  • 02-00-83 10-00-84 0%

e i

h

C 0 N S T R U C-T I O N

$TATUS REPQRT PAGE NO: 2-066 LIMERICK 2 NUCLEAR POWER PLANT $

STATUS AS OF:

12-31-81 PLANT CHARACTERISTICSt KEY P E R S 0 N N E L:

DOCKET NO:

05000353 CORPORATE CONTACT:

V.

S.

BOYER, $dNICR VICE PRESIDENT CP HO. & DATE ISSUED:

CPPR-107/ 06-19-74 HUCLEAR POWER CP EXPIRATION DATE:

10-01-87 CORPORATE ADDRESS:

PHILADELPHIA ELECTRIC COMPANY APPLICANT:

PHILADELPHIA ELECTRIC 2301 MARKET STREET PLANT LOCATION:

35 MI NW OF PHILADELPHIA, PA PHILADELPHIA, PENNSYLVANIA 19101 IE REGION:

1 CORPORATE PHONE NO:

(215) 841-4500 AE2 BECHTEL HSSS:

GENERAL ELECTRIC CONSTRUCTOR:

BECHTEL NRC LPM:

H. ABELSON REACTOR 1YPE:

BWR IE PROJECT INSPECTOR:

DER (MWE):

1065 TE RESIDENT INSPECTOR:

J. P.

DURR INSP ECTION STATUSt FUEL L0AD DA TE CHANGES TIME PERIOD AS REPQRTED BY U T I L I T Y:

OCT. 1981 - DEC. 1981 REPORT NEW REASON FOR CHANGE REPORT BEG DATE END DATE DATE SCHEDULE PEPORTED BY UTILITY NUMBS 8 Rf_JNSP.

OF INSP.

09-27-74 10-01-81 DELAY ENTIRELY ATTRIBUTABLE TO FINANClHG 81-14 10-01-81 11-30-81 PROBLEMS.

81-15 12-01-81 01-08-82 10-15-75 01-01-82 SCHEDULE REFINEMENT AND BUDGET ADJUSTMENTS.

05-24-76 10-01-84 HIGHER CAPITAL COSTS AND LOWER THAN EXPECTED DEMAND FOR ELECTRICITY.

Inspection Reports are available at Iocal PDRs.

09-23-80 10-00-86 INCREASE OF SCOPE DUE TO DESIGN CHANGES 8 NEW REGULATORY REQUIREMENTS, DESIGN PROBLEMS ASSOCIATED W/ MARK II CONTAINMENT, REFINEMENT OF ESTIMATES AND LIMITS ON YEARLY CAPITAL AVAILABLE.

02-20-81 04-00-87 REFINEMENT OF MANHOUR ESTIMATES AND DURATIONS REQUIRED TO COMPLETE REMAINING ENGINEERING AND FIELD WORK.

L0 CAL PUBLIC D0CUMENT R 0 0 M:

POTTSTOWN PUBLIC LIBRARY 500 HIGH STREET POTTSTOWN, PENNSYLVANIA 19464

C0NSTRUCTION STATUS REPORT PAGE NO: 2-067 LIMERICK 2 NUCLEAR POWER

?LANTS STATUS AS OF 12-31-81 C0N5TRUCTION STATUSt APPLICANT'S CURRENT ESTIMATED FUEL LOADING DATE:

04-00-87 APPLICANTS CONSTRUCTION COMPLETION ESTIMATE AS APPLICANT'S PREVIOUS ESTIMATED FUEL LOADING DATE:

10-00-86 DEFINED IN CP: (EARLIEST)

APPLICANT'S ESTIriATED FUEL LOADING DATE AT CP ISSUANCE:

09-00-80 (LATEST)

APPLICANT'S CURRENT ESTIMATED COMMERCIAL OPERATION DATE: 04-00-87 CURRENT ESTIMATED PERCENT CONSTRUCTION COMPLETE: 30%

COMMENTS REGARDING CURRENT CONSTRUCTION STATUS: WE CONTINUE TO REPORT OVERALL COMPLETION PERCENTAGES BASED ON TOTAL SCOPE AND MANHOUR EXPENDITURES.

ESTIMATED ACTUAL ESTIMATED ACTUAL ESTIMATED START START CCMPLETION

[0MPLETION % COMPLETE MOBILIZE AND PREPARE SITE:

05-00-70 05-00-70 09-00-74 09-00-74 100%

PLACE STRUCTURAL CONCRETE:

09-00-74 09-00-74 11-00-80 11-00-80 100%

INSTALL REACTOR PRESSURE VESSEL:

09-00-77 09-00-77 10-00-77 10-00-7s 100%

INSTALL LARGE BORE PROCESS PIPE:

01-00-76 01-00-76 04-00-85 19%

INSTALL LARGE 30RE PIPE NANGERS, RESTRAINTS AND $NUBBERS:

01-00-76 01-00-76 12-00-84 14%

INSTALL SMALL DORE PIPE:

01-00-78 01-00-78 01-00-85 4%

INSTALL CABLE TRAY:

06-00-78 06-00-78 06-00-85 11%

INSTALL EXPOSED METAL CONDUIT:

12-00-82 04-00-86 0%

INSTALL POWER, CONTROL, INSTRUMENTATION AND SECURITY CABLE:

01-00-84 09-00-86 0%

INSTALL ELECTRICAL TERMINATIONS:

03-00-84 11-00-86 0%

CONDUCT REACTOR COLD HYDROSTATIC TEST:

05-00-86 05-00-86 0%

CONDUCT HOT FUNCTIDH4L TEST:

N/A N/A N/A N/A N/A CONDUCT PREOP AND ACCEPTANCE TESTS NECESSARY FOR FUEL LOAD 08-00-85 04-00-87

C0NSTRUCTION STATUS REPORT PAGE NO: 2-068 MARBLE NILL 1 NUCLEAR P0WER PLANTS STATUS AS OF 12-31-81 PLANT CHARACTERISTICS:

KEY PERS0NNEL DOCKET NO:

05000546 CORPORATE CONTACT:

S. W. SHIELDS, SEN. VICE PRESIDENT NUCLEAR DIVISION CP NO. 8 DATE ISSUED: CPPR-170/ 04-04-78 CP EXPIRATION DATE:

01-01-84 CORPORATE ADDRESS:

1000 EAST MAIN STREET PLAINFIELD, INDIANA 46168 APPLICANT:

PUBLIC SERVICE OF INDIANA PLANT LOCATION:

to MI $ OF MADISON, IN IE REGICH:

3 CORPORATE PHONE NO:

(317) 839-9611 AE SARGENT & LUNDY NSSS:

WESTINGNOUSE CONSTRUCTOR:

PUBLIC SERVICE OF INDIANA NRC LPM:

K. KIPER REACTOR TYPE:

PWR IE PROJECT INSPECTOR E. R. SCHWEIBINZ DER (MWE):

1130 IE RESIDENT INSPECTOR:

J. J. HARRISON, JR.

INSPECTION STATUS FUEL L0AD DATE CHANGES TIME PERIOD AS REP 0RTED BY UTILITY:

OCT, 1981 - DEC. 1981 REPORT NEW REASON FOR CHANGE REPORT BEG DATE END DATE DATE SCHEDULE REPORTED BY UTILITY NUMS58 0F INSP.

OF INSP.

08-00-80 06-00-86 NO REASON PROVIDED.

j 8119 10-31-81 10-31-81 8120 10-01-81 10-31-81 Inspection Reports are available at local PDRs.

L0 CAL PUBLIC D0CUMENT R 0 0 Ms MADISON-JEFFERSON COUNTY PUBLIC LIBRARY 420 WEST MAIN STREET MADISON, INDIANA 47250

C0N$TRUCTION STATUS REPORT PAGE NO 2-069 MARBLE HILL 1 NUCLEAR POWER PLANTS STATUS AS OF 12-31-81 C0NSTRUCTION STATUSt APPLICANT'S CURRENT ESTIMATED FUEL LOADING DATE:

06-00-86 APPLICANTS CONSTRUCTION COMPLETION ESTIMATE AS I

APPLICANT'S PREVIOUS ESTIMATED FUEL LOADING DATE:

04-00-82 DEFINED IN CP: (EARLIEST)

APPLICANT'S ESTIMATED FUEL LOADING DATE AT CP ISSUANCE:

04-00-82 (LATEST) 01-01-84 APPLICANT'S CURRENT ESTIMATED COMMERCIAL OPERATION DATE: 12-00-86 CURRENT ESTIMATED PERCENT CONSTRUCTIDH COMPLETE: 31%

COMMENTS REGARDING CURRENT CONSTRUCTION STATUS: THE ABOVE NUMBER APPROXIMATES THE PERCENT MANHOURS CONSUMED. IT DOES NOT NECESSARILY INDICATE THE PHYSICAL CCMPLETION OF THE PROJECT OR COMPLETION STATUS.

ESTIMATED ACTUAL ESTIMATED ACTUAL ESTIMATED START START COMPLETION COMPLETION % COMPLETE MOBILIZE AND PREPARE SITE:

08-00-77 06-00-86 85%

PLACE STRUCTURAL CONCRETE:

01-00-78 12-00-85 69%

INSTALL REACTOR PRESSURE VESSEL:

09-00-82 11-00-84 0%

INSTALL LARGE BORE PROCESS PIPE:

01-00-79 01-00-85 35%

INSTALL LARGE BORE PIPE HANGERS, RESTRAINTS AND SNUBBERS:

01-00-79 01-00-85 15%

INSTALL SMALL BORE PIPE:

02-00-80 02-00-86 9%

INSTALL CABLE TRAY:

04-00-80 03-00-85 35%

INSTALL EXPOSED METAL CONDUIT:

04-00-80 10-00-85 13%

INSTALL POWER, CONTROL, INSTRUMENTATION AND SECURITY CABLE:

01-00-82 12-00-85 1%

INSTALL ELECTRICAL TERMINATIONS:

01-00-82 03-00-86 1%

CONDUCT REACTOR COLD HYDROSTATIC TEST 08-00-85 09-00-85 0%

CONDUCT HOT FUNCTIONAL TEST:

02-00-86 03-00-86 0%

CONDUCT PREOP AND ACCEPTANCE TESTS NECESSARY FOR FUEL LOAD:

01-00-85 06-00-86 0%

5

+

C0N5 TRUCTION 5TATUS REPORT PAGE NO: 2-070 MARBLE HILL 2 NUCLEAR POWER PLANTS STATUS AS OF 12-31-81 PL A NT CHARA CT ERI 5 T I C S:

KEY P E R S 0 N N E L:

DOCKET NO:

05000547 CORPORATE CONTACT:

S. W.

SHIELDS. SEN. VICE PRESIDENT CP NO.'8 DATE ISSUED:

CPPR-171/ 04-04-78 NUCLEAR DIVISION CP EXPIRATION DATE:

01-01-86 CORPORATE ADDRESS:

1003 EAST MAIN STREET APPLICANT:

PU3LIC SERVICE OF INDIANA PLAINFIELD, INDIANA 46168 PLANT LOCATION:

10 MI S OF MADISON, IN IE REGION:

3 CORPORATE PHONE NO:

(317) 839-9611 AE:

SARGENT & LUNDY

.NSSS:

WESTINGHOUSE CONSTRUCTOR:

PUBLIC SERVICE OF INDIANA NRC LPM:

K.

KIPER REACTOR TYPE:

PWR IE PROJECT INSPECTOR:

E. R. SCHWEIBINZ DER (MNE):

1130 IE RESIDENT INSPECTOR:

J.

J.

HARRISON, JR.

INSPECT ION STA T U 5:

FUEL L0AD DATE CHANGES TIME PERIOD AS REPORT ED BY UTIL I T Y:

OCT, 1991 - DEC, 1981 REPORT HEW REASON FOR CHANGE REPORT BEG DATE END DATE DATE SCHEDULE REPORTED BY UTTLITY NUMBER OF INSP.

OF INSP.

08-00-80 06-00-87 NO REASON PROVIDED.

8119 10-31-81 10-31-81 8120 10-01-81 10-31-81 Inspection Reports are available at local PDRs.

I t

l l

l I

I I

l l

L0 CAL PUBL IC D0CUMENT R 0 0 M:

l NADISON-JEFFERSON COUNTY PUBLIC LIBRARY 420 WEST MAIN STREET MADISON, INDIANA 47250 i

l l

i

C0NSTRUCT ION STATUS REPORT PAGE NO: 2-071 MARBLE HILL 2 NUCLEA R POWER PLANTS STATUS AS OF:

12-31-81 C0NSTRUCT ION STATUSt APPLICANT'S CURRENT ESTIMATED FUEL LOADING DATE:

06-00-87 APPLICANTS CONSTRUCTION COMPLETION ESTIMATE AS APPLICANT'S PREVIOUS ESTIMATED FUEL LOADING DATE:

07-00-83 DEFINED IN CP: (EARLIEST)

APPLICANT'S ESTIMATED FUEL LOADING DATE AT CP ISSUANCE:

07-00-83 (LATEST) 01-01-86 APPLICANT'S CURRENT ESTIMATED COMMERCIAL OPERATION DATE: 12-00-87 CURRENT ESTIMATED PERCENT CONSTRUCTION COMPLETE:

15%

COMMENTS REGARDING CURRENT CONSTRUCTION STATUS: THE ABOVE NUMBER APPROXIMATES THE PERCENT MANNOURS CONSUMED.

IT DOES NOT NECESSARILY INDICATE THE PHYSICAL COMPLETION OF THE PROJECT OR COMPLETION. STATUS.

ESTIMATED ACTUAL ESTIMATED ACTUAL FSTIMATED START START C0FPLETION COMPLETION % COMPLETE MOBILIZE AND PREPARE SITE:

12-00-77 06-00-86 85%

PLACE STRUCTURAL CONCRETE:

03-00-78 12-00-86 68%

INSTALL REACTOR PRESSURE VESSEL:

02-00-84 03-00-86 0%

INSTALL LARGE BORE PROCESS PIPE:

05-00-79 01-00-86 164 INSTALL LARGE BORE PIPE HANGERS, RESTRAINTS AND SNUSBERS:

05-00-79 01-00-86 17%

INSTALL SMALL BORE PIPE:

05-00-80 02-00-87 2%

~

INSTALL CABLE TRAY:

06-00-81 12-00-85 21%

INSTALL EXPOSED METAL CONDUIT:

10-00-81 03-00-86 1%

INSTALL POWER, CONTROL, INSTRUMENTATION AND SECURITY CABLE:

09-00-83 06-00-86 0%

INSTALL ELECTRICAL TERMINATIONS:

03-00-84 09-00-86 0%

CONDUCT REACTOR COLD HYDROSTATIC TEST:

08-00-86 09-00-36 0%

CONDUCT HOT FUNCTIONAL TEST:

02-00-87 03-00-87 0%

CONDUCT PREOP AND ACCEPTANCE TESTS NECESSARY FOR FUEL LOAD:

01-00-86 06-00-87 0%

C0NSTRUCTION STAYUS REPQRT PAGE NO: 2-072 MCGUIRE 2 NUCLEAR POWER PLANTS STATUS AS OF 12-31-81 PLANT CHARACTERI$ TICS KEY PERS0NNEL DOCKET NO:

05000370 CORPORATE CONTACT:

W. H. OWEN, SR. VICE PRESIDENT CP NO. 8 DATE ISSUED:

CPPR-84 / 02-23-73 DESIGN & CONST., DUKE POWER CO.

CP EXPIRATION DATE:

03-01-77 CORPORATE ADDRESS:

PB 3032, 422 S. CHURCH STREET PGWER CHARLOTTE, NORTH CAROLINA 28242

!", f F APPLICANT:

1 MI N OF CHARLOTTE, NC PLANT LOCATION:

IE REGION:

2 CORPORATE PHONE NO:

(704) 373-4120 AE:

DUKE POWER NSSS:

WESTINGHOUSE CONSTRUCTOR:

DUKE POWER NRC LPM:

R. BIRKEL REACTOR TYPE:

PWR IE PROJECT INSPECTOR:

DER (MWE): -

1180 IE RESIDENT INSPECTOR:

M. GRAHAM INSPECTION STATUS:

FUEL L0AD DATE CHANGES TIME PERIOD AS REPORTED BY UTIL ITY OCT. 1981 - DEC, 1981 REPORT HEW REASON FOR CHANGE REPORT BEG DATE END DATE DATE SCHEDULE REPORTED BY UTILITY NUMBER OF INSP.

OF INSP.

05-01-77 INITIALLY DELAYED IN RECEIVING CONSTRUCT-8118 09-15-81 10-15-81 ION PERMIT. CONSTRUCTION DELAYED BY 8119 11-02-81 11-06-81 INCREASED DELIVERY TIME OF MATERIAL AND 8120 12-15-81 12-18-81 COMPONENTS.

8121 11-30-81 12-04-81 07-26-74 12-15-77 CONSTRUCTION DELAYED BY INCREASED 8122 11-18-81 11-20-81 DELIVERY TIME OF MATERIAL AND COMPONENTS.

8124 12-15-81 12-18-81 09-27-74 08-00-78 CONSTRUCTION DELAYS DUE TO CRITICAL 8125 12-01-81 12-04-81 CONDITIONS EXISTING IN THE FINANCI AL MARKETS.

INSPECTION REPORTS ARE AVAILABLE AT LOCAL PDR'S.

04-21-76 09-15-78 NO REASON GIVEN BY THE UTILITY.

04-18-77 08-00-79 CONSTRUCTION DELAY.

08-16-77 N/S LATE EQUIPMENT DELIVERIES. DESIGN MODIFICATIONS 09-20-77 10-10-80 DUE TO CHANGED REGULATORY REQUIREMENTS.

08-13-79 01-00-82 NO REASON GIVEN.

08-00-80 06-00-82 NO REASON PROVIDED.

10-29-81 04-01-83 NO REASON PROVIDED.

L0 CAL PUBL IC D0CUMENT R 0 0 Ms PUBLIC LIBRARY OF CHARLOTTE AND MACKLENBURG COUNTY 310 NORTH TRYON STREET l

CHARLOTTE, NORTH CAROLINA 28202 l

l

C0NSTRUCTION STATUS REP 0RT PAGE NO: 2-073 MCGUIRE 2 NUCLEAR POWER PLANTS STATUS AS OF:

12-31-81 C0NSTRUCTION STATUSt APPLICANT'S CURRENT ESTIMATED FUEL LOADING DATE:

04-01-83 APPLICANTS CONSTRUCTION COMPLETION ESTIMATE AS APPLICANT'S PREVIOUS ESTIMATED FUEL LOADING DATE:

06-00-82 DEFINED IN CP: (EARLIEST)

APPLICANT'S ESTIMATED FUEL LOADING DATE AT CP ISSUANCE:

10-01-76 (LATEST)

APPLICANT'S CURRENT ESTIMATED COMMERCIAL OPERATION DATE: 10-01-83 CURRENT ESTIMATED PERCENT CONSTRUCTION COP.'LETE:

94%

COMMENTS REGARDING CURRENT CONSTRUCTION STATUS:

ESTIMATED ACTUAL ESTIMATED ACTUAL ESTIMATED START START COMPLETION COMPLETI03 % CCMPL(If MOBILIZE AND PREPARE SITE:

04-01-71 05-08-72 100%

PLACE STRUCTURAL CONCRETE:

05-08-72 05-01-82 99%

INSTALL REACTOR PRESSURE VESSEL:

06-09-75 06-10-75 100%

INSTALL LARGE BORE PROCESS PIPE:

03-01-7S 03-01-82 99%

INSTALL LARGE BORE PIPE HANGERS, RESTRAINTS AND SNUBBERS:

04-01-75 07-15-82 85%

INSTALL SMALL BORE PIPE:

04-01-78 03-01-82 98%

INSTALL CABLE TRAY:

08-01-74 07-01-82 90%

INSTALL EXPOSED METAL CONDUIT:

08-01-74 07-01-82 90%

INSTALL POWER, CONTROL, INSTRUMENTATION AND SECURITY CABLE:

04-01-77 08-01-82 94%

INSTALL ELECTRICAL TERMINATIONS:

04-15-77 08-01-82 93%

CONDUCT REACTOR COLD HYDROSTATIC TEST:

07-19-82 07-28-82 0%

CONDUCT HOT FUNCTIONAL TEST:

09-01-82 10-26-32 0%

CONDUCT PREOP AND ACCEPTANCE TESTS HECESSARY FOR FUEL LOAD:

10-27-82 03-01-83 0%

C0NSTRUCTION STATUS REP 0RT PAGE NO: 2-074 MIDLAND 1 NUCL EA R POWER PLANTS STATUS AS OF:

12-31-81 PLANT CHARACTERIST I C S:

KEY PERS0NN E La DOCKET No:

05000329 CORPORATE CONTACT:

J. W. COOK, VICE PRESIDENT CP NO. & DATE ISSUED:

CPPR-81 / 12-15-72 PROJECTS, ENG & CONSTRUCTION CP EXPIRATION DATE:

12-01-84 CORPORATE ADDRESS:

1945 W. PARNALL ROAD APPLICANT:

CONSUMERS POWER JACKSON, MICHIGAN 49201 PLANT LOCATION:

SW BOUNDARY OF MIDLAND, MICH.

IE REGION:

3 CORPORATE PHONE NO:

(S17) 788-0453 AE:

BECHTEL NSSS:

BABCOCK & WILCOX CCNSTRUCTOR:

EECHTEL NRC LPM:

D. HOOD REACTOR TYPE:

PWR IE PROJECT INSPECTOR:

K.

RIDGWAY DER (MWE):

0492 IE RESIDENT INSPECTOR:

R. J. COOK ZN5PECT ION S T A T U S:

FUEL L0AD DATE CHANGES TIME PERIOD AS REPORTED BY UTIL I T Y:

OCT, 1981 - DEC, 1981 REPORT NEW REASON FOR CHANGE REPORT BEG DATE END DATE DATE SCHEDULE REPOPTED BY UTILITY NVMBER OF INSP.

OF INSP, 11-07-74 11-00-80 CONSTRUCTION SCHEDULE STRETCHOUT TO 8120 10-06-81 10-09-81 REDUCE CURRENT CASH OUTFLOW.

8121 11-24-81 11-24-81 01-14-75 11-00-81 CCNSTRUCTION SCHEDULE STRETCHED OUT TO 8122 09-01-81 11-03-81 REDUCE CURRENT CASH OUTFLOW.

09-00-80 12-00-83 PROJECT SCHEDULE REEVALUATION INCORPORATING OUTSTANDING LICENSING Inspection Reports are available at local PDRs.

ISSUES.

L0 CAL PUBLIC D0CUMENT R 0 0 M:

GRACE DOW MEMORIAL TIBRARY 1710 W.

ST. ANDREWS ROAD MIDLAND MICHIGAN 48640

C0NSTRUCT ION STATUS REP 0RT PAGE NO: 2-075 NIDLAND 1 NUCLEAR POWER PLANTS STATUS AS OF:

12-31-81 C0NSTRUCTION STA T U S:

APPLICANT'S CURRENT ESTIMATED FUEL LOADING DATE:

12-00-83 APPLICANTS CONSTRUCTION COMPLETI0H ESTIMATE AS APPLICANT'S PREVIOUS ESTINATED FUEL LOADING DATE:

11-00-81 DEFINED IN CP (EARLIEST) 12-01-83 APPLICANT'S ESTIMATED FUEL LOADING DATE AT CP ISSUANCE:

11-00-79 (LATEST) 12-01-84 APPLICANT'S CURRENT ESTIf1ATED COMMERCIAL OPERATION DATE: 07-00-84M CURRENT ESTIMATED PERCENT CONSTRUCTION COMPLETE: 74%

COMMENTS REGARDING CURRENT CONSTRUCTION STATUS: M COMMERCIAL OPERATION FOR BOTH PROCESS STEAM AND ELECTRICAL.

MM PERCENT COMPLETE IS LARGE BORE HANGERS. RESTRANTS AND SHUBBERS ARE NOT INCLUDED.

ESTIMATED ACTUAL ESTIMATED ACTUAL ESTIMATED START STAPT_

COMPLETION COMPLETLON % COMPLETE 2

MOBILIZE AND PREPARE SITE:

03-00-73 03-00-73 100%

PLACE STRUCTURAL CONCRETE:

08-00-73 01-00-82 99%

INSTALL REACTOR PRESSUDE VESSEL:

06-00-78 08-00-78 100%

INSTALL LARGE BORE PROCESS PIPE:

07-00-76 06-00-82 97%

INSTALL LARGE BORE PIPE HANGERS, RESTRAINTS AND SNUBBERSIMM 12-00-77 12-00-82 91%

INSTALL SMALL BORE PII'E:

01-00-77 12-00-82 92%

INSTALL CABLE TRAY:

04-00-77 12-00-82 95%

INSTALL EXPOSED METAL CONDUIT:

04-00-77 12-00-82 96%

INSTALL POWER, CON 1ROL, INSTRUMENTATION AND SECURITY CABLE:

11-00-78 06-00-83 75%

INSTALL ELECTRICAL TERMINATIONS:

06-00-78 06-00-83 49%

CONDUCT REACTOR COLD HYDROSTATIC TEST:

11-00-82 11-00-82 0%

CONDUCT HOT FUNCTIONAL TEST:

04-00-83 06-00-83 0%

CONDUCT PREOP AND ACCEPTANCE TESTS NECESSARY FOR FUEL LOAD:

02-00-82 12-00-83 0%

C0NSTRUCTION STATUS REPQRT PAGE NO: 2-076 MIDLAND 2 NUCLEAR POWER PLANTS STATUS AS OF 12-31-81 PLANT CNARACTERISTICSt KEY PERS0NNEL DOCKET NO:

05000330 CORPORATE CONTACT:

J. W. COOK, VICE PRESIDENT CP NO. & DATE ISSUED: CPPR-82 / 12-15-72 PROJECTS, ENG & CONSTRUCTION CP EXPIRATION DATE:

07-01-84 CORPORATE ADDRESS:

1945 W. PARNALL ROAD APPLICANT:

CONSUMERS POWER JACKSON, MICHIGAN 49201 PLANT LOCATION -

SW BOUNDARY OF MIDLAND, MICH.

IE REGION:

3 CORPORATE PHONE NO:

(517) 788-0453 AE BECHTEL NSSS:

BABCOCK & WILCOX CONSTRUCTOR:

BECHTEL NRC LPM:

D. HOOD REACTOR TYPE:

PWR IE PROJECT INSPECTOR:

K. RIDGWAY DER (MWE):

0818 IE RESIDENT INSPECTOR:

R. J. COOK INSPECTION 5TATUSt FUEL L0AD DATE CHANGES TIME PERIOD AS REP 0RTED BY UTILITY OCT. 1981 - DEC. 1981 REPORT NEW REASON FOR CHANGE REPORT BEG DATE END DATE DATE SCHEDULE REPORTED BY UTILITY NUMBER OF INSP.

OF INSP.

11-07-74 11-00-79 CONSTRUCTION SCHEDULE STRETCHED OUT TD 8120 10-06-81 10-09-81 REDUCE CURRENT CASH OUTFLOW ANNOUNCED BY 8121 11-24-81 11-24-81 UTILITY.

8122 09-01-81 11-03-81 01-14-75 11-00-80 CONSTRUCTION SCHEDULE STRETCHED OUT.

09-11-79 06-00-81 DEVELOPMENT OF A TWO UNIT INTEGRATED TEST Inspection Reports'are available at local PDRs.

SCHEDULE.

09-00-80 07-00-83 PROJECT SCHEDULE REEVALUATION INCORPORATING OUTSTANDING LICENSING ISSUES.

I L0 CAL PUBLIC D0CUMENT R00M GRACE DOW MEMORIAL LIBRARY 1710 W. ST. ANDREWS ROAD MIDLAND MICHIGAN 48640

m l

C0NSTRUCTION STATUS REPORT PAGE NO: 2-077 MEDLAND 2 HUCLEAR POWER PLANTS STATUS AS OF 12-31-81 C0NSTRUCTION S T A T U 5:

APPLICANT'S CURRENT ESTIMATED FUEL LOADING DATE:

07-00-83 APPLICANTS CONSTRUCTION COMPLETION ESTIMATE AS APPLICANT'S PREVIOUS ESTIMATED FUEL LOADING DATE:

06-00-81 DEFINED IN CP: (EARLIEST) 07-01-83 APPLICANT'S ESTIMATED FUEL LOADING DATE AT CP ISSUANCE:

11-00-78 (LATEST) 07-01-84 APPLICANT'S CURRENT ESTIMATED COMMERCIAL OPERATION DATE: 12-00-83 CURRENT ESTIMATED PERCENT CONSTRUCTION COMPLETE: 74%

COMMENTS REGARDING CURRENT CONSTRUCTION STATUS:

  • PERCENT COMPLETE IS LARGE BORE HANGERS. RESTRAINTS AND *,NUBBERS ARE NOT INCLUDED.

ESTIMATED ACTUAL ESTIMATED ACTUAL ESTIMATED I

START START COMPLETION COMPLETION % COMPLETE MOBILIZE AND PREPARE SITE:

03-00-73 08-00-73 100%

PLACE STRUCTURAL CONCRETE:

08-00-73 04-00-83 99%

INSTALL REACTOR PRESSURE '.CSSEL:

04-00-78 05-00-78 100%

INSTALL LARGE BORE PROCESS PIPE:

04-00-76 06-00-82 97%

INSTALL LARGE BORE PIPE HANGERS, RESTRAINTS AND SNUBBERS:N 11-00-77 12-00-82 84%

INSTALL SMALL BORE PIPE:

01-00-77 12-00-82 84%

INSTALL CABLE TRAY:

04-00-77 03-00-83 9; %

i INSTALL EXPOSED METAL CONDUIT:

04-00-77 03-00-83 83%

INSTALL POWER, CONTROL, INSTRUMENTATION AND SECURITY CABLE:

01-00-78 06-00-83 75%

INSTALL ELECTRICAL TERMINATIONS:

06-00-78 06-00-83 49%

CONDUCT REACTOR COLD HYDROSTATIC TEST 05-00-82 09-00-82 0%

CONDUCT HOT FUNCTIOHAL TEST 12-00-82 03-Ob-83 0%

CONDUCT PREOP AND ACCEPTANCE TESTS NECESSARY FOR FUEL LOAD:

02-00-82 08-00-83 0%

1

)

I i

t

(

C0NSTRUCTION

$TATUS REPQRT PAGE NO: 2-078 MILLSTONE 3 NUCLEAR POWER PLANTS STATUS AS OF 12-31-81 PLANT CHARACTERISTICSt KEY PERS0NNELa DOCKET NO:

05000423 CORPORATE CONTACT:

W. G. COUNSIL. VICE PRESIDENT CP NO. 8 DATE ISSUED: CPPR-113/ 08-09-74 NUCLEAR ENGINEERING & OPERATIONS CP EXPIRATION DATE:

10-01-79 CORPORATE ADDRESS:

P. O.

BOX 270 APPLICANT:

NORTNEAST NUCLEAR ENERGY NARTFORD. CONNECTICUT 06101 PLANT LOCATION:

5 MI SW OF NEW LONDON, CONH IE REGION:

1 CORPORATE PHONE NO:

(203) 666-6911 AE:

STONE 8 WEBSTER NSSS:

WESTINGNOUSE CONSTRUCTOR:

STONE & WEBSTER NRC LPM:

J. GRANT REACTOR TYPE:

PWR IE PROJECT INSPECTOR:

DER (MWE):

1159 IE RESIDENT INSPECTOR:

INSPECTION STATUSt FUEL L0AD DATE CNANGES TIME PERIOD AS REPQRTED BY UTILITY OCT, 1981 - DEC, 1981 REPORT NEW REASON FOR CHANGE REPORT BEG DATE END DATE DATE ilHEDULE REPORTED BY UTILITY NUttBER OF INSP, OF INSP.

03-00-75 06-00-79 REEVALUATION OF PROGRAM STATUS.

31-12 09-28-81 10-23-81 11-00-76 12-00-81 1 UNCERTAIN FUEL SUPPLY.

81-13 10-19-81 10-23-81

2. CHANGES IN LOAD DEMAND.

81-14 10-24-81 11-30-81

3. INCREASES IN PROJECT COST.

81-15 12-01-81 12-31-81

4. MODIFICATIONS IN LONG RANGE PLANNING.

10-20-77 12-00-85 FINANCIAL CONSIDERATIONS.

Inspection Reports are available at local PDRs.

L0 CAL PUBLIC D0CUMENT R 0 0 M:

WATERFORD PUBLIC LIBRARY R0PE FERRf ROAD, ROUTE 156 WATERFORD, CONNECTICUT -06385

i C0NSTRUCTION STATUS REPORT PAGE NO: 2-079 MILLSTONE 3 NUCLEAR POWER PLANTS STATU% AS OF 12-31-81 C0NSTRUCT ION

$TATUSt APPLICANT'S CURRENT ESTIMATED FUEL LOADING DATE:

12-01-85 APPLICANTS CONSTRUCTION COMPLETICH ESTIMATE AS APPLICANT'S PREVIOUS ESTIMATED FUEL LOADING DATE:

12-01-81 DEFINED IN CP: (EARLIEST) 12-01-78 APPLICANT'S ESTIMATED FUEL LOADING DATE AT CP ISSUANCE:

12-01-78 (LATEST)

APPLICANT'S CURRENT ESTIMATED COMMERCIAL OPERATION DATE: 05-01-86 CURRENT ESTIMATED PERCENT CONSTRUCTION COMPLETE: 43%

COMMENTS REGARDING CURRENT CONSTRUCTION STATUS:

ESTIMATED ACTUAL ESTIMATED ACTUAL ESTIMATED START START COMPLETION COMPLETIDH % COMPLETE MOBILIZE AND PREPARE SITE:

C5-00-74 09-00-74 09-00-74 100%

PLACE STRUCTURAL CONCRETE:

10-00-74 08-00-74 71%

INSTALL REACTOR PRESSURE VESSEL:

07-00-80 07-00-80 07-00-80 100%

INSTALL LARGE BORE PROCESS PIPE:

02-00-77 01-00-85 43%

INSTALL LARGE BORE PIPE HANGERS, RESTRAINTS AND SNUBBERS:

02-00-77 01-00-85 18%

INSTALL SMALL BORE PIPE:

02-00-77 01-00-85 20%

i INSTALL CABLE TRAY:

03-00-77 01-00-85 43%

i

. INSTALL EXPOSED METAL CONDUIT:

10-00-77 01-00-84 15%

INSTALL POWER, CONTROL, INSTRUMENTATION AND SECURITY CABLE:

03-00-78 12-00-84 0.8%

i INSTALL ELECTRICAL TERMINATI0HS:

03-00-78 01-00-85 0.5%

CONDUCT REACTOR COLD HYDROSTATIC TEST 03-00-85 03-00-85 03-00-85 0%

CONDUCT HOT FUNCTIONAL TEST 08-00-85 08-00-85 08-00-85 0%

CONDUCT PREOP AND ACCEPTANCE TESTS NECESSARY FOR FUEL LOAD:

12-00-85 12-00-85 12-00-85 0%

9 6

C0N5TRUCTION 5TATUS REPQRT PAGE NO: 2-080 NINE MILE POINT 2 NUCLEAR POWER PLANTS STATUS AS OF 12-31-81 PLANT C H A R A C T E R I S T I C 5:

KEY PERS0NNEL:

DOCKET NO:

05000410 CORPORATE CONTACT:

S. F. MANNO, PROJECT MANAGER CP HO. 8 DATE ISSUED: CPPR-112/ 06-24-74 CP EXPIRATION DATE:

07-13-78 CORPORATE ADDRESS:

300 ERIE BOULEVARD WEST SYRACUSE, NEW YORK 13202 APPLICANT:

HIAGARA MONAWK POWER PLANT LOCATION:

8 MI NE OF OSWEGO, NY IE REGIOMs 1

CORPORATE PHONE NO:

(315) 474-1511 AE:

STONE 8 WEBSTER NSSS:

GENERAL ELECTRIC CCHSTRUCTOR:

STONE & WEBSTER NRC LPM:

D. LYNCH REACTOR TYPE:

BWR IE PROJECT INSPECTOR:

DER (MWE):

1080 IE RESIDENT INSPECTOR:

R. D. SCHULE IN$PECTION 5TATUS FUEL L0AD DATE CHANGES TIME PERIOD A5 REPORTED BY UTIL I T Y:

OCT, 1981 - DEC. 1981 REPORT NEW REASON FOR CHANGE REPORT BEG DATE END DATE DATE SCHEDULE REPORTED BY UTILITY NVMB(R OF INSP.

OF INSP.

03-14-78 03-31-83 1.

DESIGN CHANGES TO MITIGATE CONTAINMENT 81-12 10-13-81 11-13-81 DYNAMIC LOADS.

81-13 11-05-81 12-18-81

2. DESIGN CHANGES TO IMPLEMENT SEPARATION 81-14 12-21-81 01-20-82 REQUIREMENTS OF REG. GUIDE 1.75.

12-14-78 03-31-84 1.

WORK STOPPAGES AND SHUTDOWN OF J05.

2. DELAYS IN PROCUREMENT OF EQUIPMENT.
3. REESTIMATE OF SCHEDULE POWER RECMTS.

Inspection Reports are available at local PDRs.

4 HEARING DELAYS.

08-00-80 03-00-86 1 POWER GENERATION CONTROL COMPLEX (PGCC).

2. GEOLOGICAL IMPACTS.
3. MARK II CONTAINMENT.

4.

BIOLOGICAL SHIELD WALL.

5. THREE MILE ISLAND IMPACTS.
6. NEW YORK STATE PUBLIC SERVICE CCMMISSION.

9 L0 CAL PUBLIC D0CUMENT R00Ms STATE UNIVERSITY COLLEGE AT OSWEGO PEHFIELD LIBRARY OSWEGO, NEW YORK 13126 1

. _ =.

~

C0NSTRUCTION STATUS REPORT PAGE Not 2-081 NINE MILE POINT 2 NUCLEAR P0WER PLANTS STATUS AS OFs 12-31-81 C0NSTRUCTION STATUSt APPLICANT'S CURRENT ESTIMATED FUEL LOADING DATE 03-00-86 APPLICANTS CONSTRUCTION COMPLETION ESTIMATE AS APPLICANT'S PREVIOUS ESTIMATED FUEL LOADING DATE8 04-00-84 DEFINED IN CP (EARLIEST)

APPLICANT'S ESTIMATED FUEL LOADING DATE AT CP ISSUANCE:

05-01-78 (LATEST) j APPLICANT'S CURRENT ESTIMATED COMMERCIAL OPERATION DATE 10-01-86 CURRENT ESTIMATED PERCENT CONSTRUCTION COMPLETE 37%

COMMENTS REGARDING CURRENT CONSTRUCTION STATUS

  • 1 m

ESTIMATED ACTUAL ESTIMATED ACTUAL ESTIMATED START START COMPLFTION COMPLETION % COMPLETE MOBILIZE AND PREPARE SITE 08-25-75 08-25-75 08-01-76 08-01-76 100%

PLACE. STRUCTURAL CONCRETE:

05-09-77 05-09-77 08-19-85 69%

l INSTALL REACTOR PRESSURE VESSEL:

08-13-79 08-13-79 08-08-80 08-08-80 100%

INSTALL LARGE BORE PROCESS PIPE:

06-07-76 06-07-76 12-03-84 36%

INSTALL LARGE BORE PIPE HANGERS, RESTRAINTS AND SNUBBER $8 09-05-77 09-05-77 12-03-84 14%

INSTALL SMALL BORE PIPET 02-01-82 03-11-85 0%

INSTALL CABLE TRAY:

11-06-78 11-06-78 07-09-84 26%

INSTALL EXPOSED METAL CONDUIT 09-12-77 09-12-77 08-12-85 14%

INSTALL POWER, CONTROL, INSTRUMENTATION AND SECURITY CABLE:

01-04-82 10-07-85 0%

INSTALL ELECTRICAL TERMINATIONS

  • 03-01-82 12-30-85 0%

CONDUCT REACTOR COLD HYDROSTATIC TEST

  • 04-29-85 05-20-85 0%

t CONDUCT NOT FUNCTIONAL TEST N/A N/A N/A N/A N/A 1

CONDUCT PREOP AND ACCEPTANCE TESTS NECESSARY FOR FUEL LOAD:

11-14-83 02-24-86 0%

i

C0NSTRUCTION

$TATUS REPQRT PAGE NO: 2-082 NORTH ANNA 3 HUCLEAR P0WER PLANTS STATUS AS OF 12-31-81 PLANT CNARACTERISTICSt KEY P E R S 0 N N E La DOCKET NO:

05000404 CORPORATE CONTACT:

S. C. BROWN, JR., SR. V. P. PSE8C CP HO. 8 DATE ISSUED:

CPPR-114/ 07-26-74 PCWER CP EXPIRATION DATE:

12-21-83 CORPORATE ADDRESS:

P. O. BOX 2666 APPLICANT:

VIRGINIA ELECTRIC 8 POWER RICHMOND, VIRGINIA 23216 PLANT LOCATION:

40 MI NW OF RICHMOND, VA IE REGIGHz 2

CORPORATE PHONE NO:

(804) 771-3274 AE STONE 8 WEBSTER HSSS:

BABCOCK 8 WILCOX CONSTRUCTOR:

OWNER NRC LPM:

R. L. CAPRA REACTOR TYPE:

PWR IE PROJECT INSPECTOR:

C. R. MCFARLAND DER (MWE):

0907 IE RESIDENT INSPECTOR:

IN$PECTION STATUSt FUEL L0AD DATE C N A'N C E S

-TIME PERIOD A5 REPORTED 8Y UTILITY OCT, 1981 - DEC. 1981 REPORT NEW REASON FOR CHANGE RFPORT BEG DATE END DATE DATE SCHEDULE REPORTED BY UTILITY NUMBER OF INSP.

OF INSP.

03-21-75 07-00-80 ECONOMIC FACTORS.

8103 12-08-81 12-10-81 07-23-76 11-01-80 SCHEDULE SLIPPAGE IS DUE TO REEVALUATION OF CONSTRUCTION PROGRESS.

03-01-77 11-00-81 VOLUNTARY DELAY DUE TO EFFORTS AT INSPECTION REPORTS ARE AVAILABLE AT LOCAL PDR'S, CONSERVATION AND LOAD MANAGEMENT.

04-00-80 N/S NO REASON PROVIDED.

11-19-81 04-00-89 LOAD MANAGEMENT.

i L0 CAL PUBLIC D0CUMENT R 0 0 Ms I

ALDERMAN LIBRARY LOUISA COUNTY COURTHOUSE UNIVERSITY OF VIRGINIA P. O. BOX 27 l

CHARLOTTESVILLE, VA 22901 LOUISA, VIRGINIA 23093 i

l

__. = - -

C0NSTRUCTION STATUS REPORT PAGE NO: 2-083 NORTH ANNA 3 NUCLEAR POWER PLANTS STATUS AS OFs 12-31-81 C0N5TRUCTION STATUSt APPLICANT'S CURRENT ESTIMATED FUEL LOADING DATE:

04-00-89 APPLICANTS CONSTRUCTION COMPLETION ESTIMATE AS APPLICANT'S PREVIOUS ESTIMATED FUEL LOADING DATE:

11-00-81 DEFINED IN CP: (EARLIEST) 07-31-78 APPLICANT'S ESTIMATED FUEL LOADING DATE AT CP ISSUANCE:

07-00-78 (LATEST) 12-31-83 APPLICANT'S CURRENT ESTIMATED COMMERCIAL OPERATION DATE: 10-00-89 CURRENT ESTIMATED PERCENT CONSTRUCTION COMPLETE:

8%

COMMENTS RECARDING CURRENT CONSTRUCTION STATUS: DRILLING OF CAISSONS AND ROCK ANCHORS FOR SITE FOUNDATIONS CURRENTLY UNDER WAY.

PERCENT CONSTRUCTION COMPLETE UNDER REVIEW.

APPLICATION FOR CP EXTENSION TO BE SUBMITTED IN JULY, 1982.

ESTIMATED ACTUAL ESTIMATED ACTUAL ESTIMATED START START COMPLETION COMPLETION % COMPLETE MOBILIZE AND PREPARE SITE:

07-00-72 01-0-276 100%

PLACE STRUCTURAL CONCRETE:

01-02-76 11-29-86 19%

INSTALL REACTOR PRESSURE VESSEL:

10-21-85 11-18-85 0%

INSTALL LARGE BORE PROCESS PIPE:

09-06-84 03-30-87 0%

INSTALL LARGE BORE PIPE HANGERS, RESTRAINTS AND SNUBBERS:

09-06-84 03-30-87 0%

INSTALL SMALL BORE PIPE:

11-05-84 02-18-88 0%

INSTALL CABLE TRAY:

11-05-84 10-12-87 0%

INSTALL EXPOSED METAL CONDUIT:

12-03-84 09-26-88 0%

INSTALL POWER, CONTROL, INSTRUMENTATION AND SECURITY CABLE:

11-19-84 11-07-88 0%

INSTALL ELECTRICAL TERMINATIONS:

09-09-85 12-07-88 0%

CONDUCT REACTOR COLD HYDROSTATIC TEST 09-26-88 10-17-88 0%

CONDUCT HOT FUNCTIONAL TEST:

11-14-88 01-02-89 0%

CONDUCT PREOP AND ACCEPTANCE TESTS NECESSARY FOR FUEL LOAD:

12-00-86 04-00-89 0%

. ~

C0NSTRUCTION 5TATUS REPORT PAGE NO: 2-084 PALO VERDE 1 NUCLEAR POWER PLANTS STATUS AS OF:

12-31-81 PLANT CHARACTERISTICSt KEY PERS0NNELa DOCKET ND:

05000528 CORPORATE CONTACT:

E. E. VAN BRUNT, JR., VICE PRES.

CP NO. 8 DATE ISSUED: CPPR-141/ 05-25-76 NUCLEAR PROJECTS MANAGEMENT CP EXPIRATION DATE:

11-01-82 CORPORATE ADDRESS:

P. O.

BOX 21666 APPLICANT:

ARIZONA PUBLIC SERVICE PHOENIX, ARIZONA 85036 PLANT LOCATION:

36 MI W OF PHOENIX, AZ IE REGION:

5 CORPORATE PHONE NO:

(6023 271-7900 AE:

BECHTEL HSSS:

COMBUSTION ENGINEERING CONSTRUCTOR:

BECHTEL NRC LPM:

J. KERRIGAN REACTOR TYPE:

PWR IE PROJECT INSPECTOR:

DER (MWE):

1304 IE RESIDENT INSPECTOR:

L. VORDERBRUEGGEN INSPECTION $TATUSt FUEL L0AD DATE CHANGES TIME PERIOD AS REP 0RTED BY UT ILITY:

OCT. 1981 - DEC. 1981 REPORT NEW REASON FOR CHANGE REPORT BEG DATE END DATE DATE SCHEDULE REPORTED BY UTILITY HUMBER OF INSP.

OF INSP.

09-13-79 11-00-82 NO REASON REPORTED.

8 1-17 10-06-81 10-06-81 81-18 10-13-81 10-13-81 81-19 10-19-81 10-23-81 81-20 10-05-81 10-09-31 81-21 10-01-81 10-30-81 81-22 11-02-81 11-30-81 81-23 09-28-81 10-31-81 81-24 11-02-81 12-04-81 81-25 12-01-81 12-30-81 I

Inspection Reports are available at local PDRs.

L0 CAL PUBLIC D0CUMENT R00Mr PHOENIX PUBLIC LIBRARY 12 EAST MCDOWELL ROAD PHOENIX, ARIZONA 85004

=

. _ -... -, ~ ~ -.. ~ -. - -.

C0NSTRUCTION STATUS REPQRT PAGE NO: 2-085 PALD VERDE 1 NUCLEAR POWER PLANTS STATUS AS OF 12-31-81 C0NSTRUCTIaN STATUS:

APPLICANT'S CURRENT ESTIMATED FUEL LOADING DATE:

11-01-82 APPLICANTS CONSTRUCTION COMPLETION ESTIMATE AS APPLICANT'S PREVIOUS ESTIMATED FUEL LOADING DATE:

11-00-81 DEFINED IN CP: (EARLIEST) 06-01-81 APPLICANT'S ESTIMATED FUEL LOADING DATE AT CP ISSUANCE:

11-00-81 (LATEST) 11-01-82 APPLICANT'S CURRENT ESTIMATED COMMERCIAL OPERATION DATE: 05-00-83 (URRENT ESTIMATED PERCENT CONSTRUCTION COMPLETE: 95%

COMMENTS REGARDING CURRENT CONSTRUCTION STATUS:

i ESTIMATED ACTUAL ESTIMATED ACTUAL ESTIMATED START START COMPLETION COMPLETION E_QQMPLETE MOBILIZE AND PREPARE SITE:

05-00-76 10-00-76 100%

PLACE' STRUCTURAL CONCRETE:

08-00-76 01-00-81 100%

INSTALL REACTOR PRESSURE VESSEL:

11-00-78 12-00-78 100%

INSTALL LARGE BORE PROCESS PIPE:

03-00-77 03-00-82 99%

INSTALL LARGE BORE PIPE HANGERS, RESTRAINTS AND SHUBBERS:

09-00-78 04-00-82 93%

INSTALL SMALL BORE PIPE:

06-00-78 05-00-82 96%

INSTALL CABLE TRAY:

10-00-77 01-00-82 11-00-81 100%

INSTALL EXPOSED METAL CONDUIT:

03-00-78 04-00-82 51%

INSTALL POWER, CONTROL, INSTRUMENTATION AND SECURITY CABLE:

02-00-79 05-00-82 962%

INSTALL ELECTRICAL TERMINATIONS:

08-00-79 06-00-82 71%

CONDUCT REACTOR COLD HYDROSTATIC TEST:

02-00-82 02-00-82 0%

CONDUCT HOT FUNCTIONAL TEST 06-00-82 08-00-82 0%

CONDUCT PREOP AND ACCEPTANCE TESTS NECESSARY FOR FUEL LOAD:

01-00-82 11-00-82 0%

l I

r 4

~

C0NSTRUCTION STATUS REP 0RT PAGE NO: 2-086 PALO VERDE 2 N U C L E'A R POWER PLANTS STATUS AS OF 12-31-81 PLANT CHARACTERI$TICSt KEY PERS0NNEL DOCKET NO:

05000529 CORPORATE CONTACT:

E.

E. VAN BRUNT. JR., VICE PRES.

CP NO. 8 DATE ISSUED:.CPPR-142/ 05-25-76 NUCLEAR PROJECTS MANAGEMENT CP EXPIRATION DATE:

11-01-84 CORPORATE ADDRESS:

P. D. BOX 21666 APPLICANT:

ARIZONA PUBLIC SERVICE PNDENIX, ARIZONA 85036 PLANT LOCATION:

36 MI W OF PNDENIX, AZ IE REGION:

5 CORPORATE PNOME NO:

(602) 271-7900 AE BECHTEL NOSS:

COMBUSTION ENGINEERING CONSTRUCTOR:

BECHTEL NRC LPM:

J. KERRIGAN REACTOR TYPE:

PWR IE PROJECT INSPECTOR:

PdR (MWE):

1304 IE RESIDENT INSPECTOR:

L. VORDERBUREGGEN I !{ SPECTION 5TATUSt FUEL L0AD DATECHANGES TIME PERIOD AS REP 0RTED BY UTILITY OCT, 1981 - DEC. 1981 REPORT N EW REASON FOR CHANGE REPORT BEG DATE END DATE DATE SCHEDULE REPORTED BY UTILITY NUMBER OF INSP.

OF INSP.

81-13 10-06-81 10-06-81 81-14 10-13-81 10-13-81 81-15 10-05-81 10-09-81 81-16 09-28-81 10-31-81 81-17 11-02-81 12-04-81 Inspection Reports are available at Iocal PDRs.

L0 CAL P.U B L I C D0CUMENT R 0 0 Ms PHOENIX PUBLIC LIBRARY 12 EAST MCDOWELL ROAD PHOENIX, ARIZONA 85004

... - _ ~ - - _...

I C0NSTRUCTION STATUS REP 0RT PAGE NO: 2-087 PALO VERDE 2 NUCLEAR POWER PLANTS STATUS AS OF 12-31-81 3

C0NSTRUCTION

$ T A T U S:

APPLICANT'S CURRENT ESTIMATED FUEL LOADING DATE:

11-00-83 APPLICANTS CONSTRUCTION COMPLETION ESTIMATE AS APPLICANT'S PREVIOUS ESTIMATED FUEL LOADING DATE:

11-00-83 DEFINED IN CP: (EARLIEST) 02-01-83 APPLICANT'S ESTIMATED FUEL LOADING DATE AT CP ISSUANCE:

11-00-83 (LATEST) 11-01-84 APPLICANT'S CURRENT ESTIMATED COMMERCIAL OPERATION DATE: 05-00-84 CURRENT ESTIMATED PERCENT CONSTRUCTION COMPLETE: 75%

COMMENTS REGARDING CURRENT CONSTRUCTION STATUS:

ESTIMATED ACTUAL ESTIMA'TED ACTUit CSTIMATED START START COMPLETION COMPLETION % COMPLETE MOBILIZE AND PREPARE SITE:

06-00-76 06-00-77 100%

PLACE STRUCTURAL CONCRETE:

08-00-77 12-00-81 12-00-81 100%

INSTALL REACTOR PRESSURE VESSEL:

06-00-80 07-00-80 100%

j INSTALL LARGE BORE PROCESS PIPE:

09-00-78 07-00-82 95%

INSTALL LARGE BORE PIPE HANGERS, RESTRAINTS AND SNUBBERS:

10-00-78 10-00-82 66%

~

INSTALL SMALL BORE PIPE:

04-00-79 10-00-82.

52%

4 INSTALL CABLE TRAY:

06-00-78 03-00-82 99%

INSTALL EXPOSED METAL CONDUIT:

01-00-78 10-00-82 70%

INSTALL POWER, CONTROL, INSTRUMENTATION AND SECURITY CABLE:

02-00-81 12-00-82 38%

INSTALL ELECTRICAL TERMINATIONS:

05-00-81 02-00-83 23%

CONDUCT REACTOR COLD HYDROSTATIC TEST 02-00-83 02-00-83 0%

CONDUCT HOT FUNCTIONAL TEST:

06-00-83 08-00-83 0%

CONDUCT PREOP AND ACCEPTANCE TESTS NECESSARY FOR FUEL LOAD:

09-00-82 11-00-83 0%

C0N$TRUCTION 5TATU$

REP 0RT PAGE NO2 2-088 PALO VERDE 3 HUCLEAR P0WER PLANTS STATUS AS OF:

12-31-81 PLANT CHARACTERISTICSt KEY PERS0NNEL t

CORPORATE CONTACT:

E. E. VAN BRUNT, JR., VICE PRES.

l DOCKET NO:

05000530 NUCLEAR PROJECTS MANAGEMENT CP HO. 8 DATE ISSUED: CPPR-143/ 05-25-76 CP EXPIRATION DATE:

11-01-86 CORPORATE ADDRESS:

P. O.

BOX 21666 FHDENIX, ARIZONA 85036 APPLICANT:

ARIZONA PUBLIC SERVICE PLANT LOCATION:

36 MI W OF PHOENIX, AZ IE REGION:

5 CORPORATE PHONE NO:

(602) 271-7900 AE BECHTEL NSSS:

COMBUSTICH ENGINEERING

' CONSTRUCTOR:

BECHTEL NRC LPM:

J. KERRIGAN IE PROJECT INSPECTORS REACTOR TYPE PWR DER (MWE):

1304 IE RESIDENT INSPECTOR:

L. VORDERBUREGGEN IN$PECTION S T A T U 58 FUEL L0AD DATE CHANGES TIME PERIOD AS REP 0RTEDBY UTILITY 8 OCT. 1981 - DEC. 1981 REPORT NEW REASON FOR CHANGE REPORT BEG DATE END DATE DATE SCHEDULE REPORTED BY UTILITY NUMBER QF INSP.

OF INSP.

81-13 10-06-81 10-06-81 81-14 10-13-81 10-13-81 81-15 10-05-81 10-09-81 81-16 09-28-81 10-31-81 81-17 11-02-81 12-04-81 Inspection Reports are available at local PDRs.

L0 CAL PUBLIC D0CUMENT R 0 0 Ms PHOENIX PUBLIC LIBRARY 12 EAST MCDOWELL ROAD PN0ENIX, ARIZONA 85004

C0NSTRUCTION SVATUS REP 0RT PAGE NO: 2-0A9 FALD VERDE 3 NUCLEAR POWER PLANTS STATUS AS OF:

,12-31-81 C0NSTRUCTION STATUSt APPLICANT'S CURRENT ESTIMATED FUEL LOADING DATE:

11-00-85 APPLICANTS CONSTRUCTION COMPLETION ESTIMA.2 AS APPLICANT'S PREVIOUS ESTIMATED FUEL LOADING DATE:

11-00-85 DEFINED IN CP: (EARLIEST) 11-01-84 APPLICANT'S ESTIMATED FUEL LOADING DATE AT CP ISSUANCE:

11-00-85 (LATEST) 11-01-86 APPLICANT'S CURRENT ESTIMATED COMMERCIAL OPERATION DATE: 05-00-86 CURRENT ESTIMATED PERCENT CONSTRUCTION COMPLETE: 30%

COMMENTS REGARDING CURRENT CONSTRUCTION STATUS:

ESTIMATED ACTUAL ESTIMATED ACTUAL ESTIMATED START START COMPLETION COMPLETION % COMPLETE MOBILIZE AND PREPARE SITE:

06-00-76 04-00-79 100%

PLACE STRUCTURAL CONCRETE:

03-00-79 12-00-83 73%

INSTALL REACTOR PRESSURE VESSEL:

04-00-82 05-00-82 0%

INSTALL LARGE BORE PROCESS PIPE:

04-00-79 08-00-84 34%

IHSTALL LARGE BORE PIPE HANGERS, RESTRAINTS AND SHUBBERS:

10-00-80 12-00-84 7%

INSTALL SMALL BORE PIPE:

06-00-80 10-00-84 3%

INSTALL CABLE TRAY:

04-00-80 02-00-84 26%

INSTALL EXPOSED METAL CONDUIT:

01-00-80 10-00-84 13%

INSTALL POWER, CONTROL,' INSTRUMENTATION AND SECURITY CABLE:

10-00-82 12-00-84 0%

INSTALL ELECTRICAL TERMIHATIONS:

01-00-83 02-00-85 c%

CONDUCT REACTOR COLD HYDROSTATIC TEST 02-00-85 02-00-85 0%

COHDUCT HOT FUNCTIONAL TEST:

06-00-85 08-00-85 0%

CONDUCT PREOP AHD ACCEPTANCE TESTS NECESSARY FOR FUEL LOAD:

09-00-84 11-00-85 0%

+c

-(

g L

C0NSTRUCTION

-S T A T U S.,

R E P C.R'T PAGE N0: 2-090 PERRY 1 NUCLEAR POWER PLANTS STATUS AS OF:

12-31-81 PLANT

'C H A R A C T E R I S T I C St KdY P E R S O N-N E L DOCKET NO:

.05000440 CORPORATE CONTACT:

'D.

R. DAVIDSON, VICE PRESIDENT CP NO. 4 DATE ISSUED: CPPR-148/ 05-03-77 ENGINEERING CP EXPIRATION DATE:

CGDPORATE ADDRESS:

P. O. BOX 5000/55 PUBLIC SQUARE APPLICANT:

CLEVELAND ELECTRIC ILLUMINATING CLEVELAND, ONIO 44101 PLANT LOCATION:

7 MI NE OF PAINESVILLE, ONIO IE REGION:

3

, CORPORATE PHONE NO:

(216) 622-9808 AE:

GILBERT ASSOCIATES NSSS:

GENERAL ELECTRIC CONSTRUCTOR:

KAISER ENGINEERS NRC LPM:

M. D. HOUSTON REACTOR TYPE:

BWR IE PROJECT INSPECTOR:

DER (MWE): '

1205 IE RESIDENT INSPECTOR:

M. GILDNER IN5PECTION 5 T A'T U S FUEL L0AD DATE CHANGES

-TIME PERIOD AS REPORTED 5Y U T I L I T Y:

OCT, 1981 - DEC, 1981 REPORT NEW REASON FOR CHANGE REPCRT BEG DATE END DATE DATE SCHEDULE REPORTED BY UTILITY NUMQU8 0F INSP.

OF INSP.

03-25-77 05-30-81 LICENSING DELAYS.

8115 10-07-81 10-09-81 01-18-79 05-00-82 SCHEDULE REEVALUATION.

02-00-80 05-00-83 NO REASON PROVIDED.

02-22-82 11-00-83 NO REASON PROVIDED.

Inspection Reports are available at lor dL PDRs.

l i

I l

f l

L0 CAL PUBLIC D0CUMENT R00M PERRY PUBLIC LIBRARY 3753 MAIN STREET l

l PERRY, ONIO 44081 j

l l

l

C0N$TRUCTION 5TATUS REPORT PAGE HO: 2-091 PERRY 1 NUCL EAR POWER PLANTS STATUS AS OF:

12-31-81 C0N$TRUCTION

$ T A T U S:

APPLICANT'S CURRENT ESTIMATED FUEL LOADING DATE:

11-00-83 APPLICANTS CONSTRUCTION COMPLETION ESTIMATE AS APPLICANT'S PREVIOUS ESTIMATED FUEL LOADING DATE:

05-00 83 DEFINED IN CP: (EARLIEST)

APPLICANT'S ESTIMATED FUEL LOADING DATE AT CP ISSUANCE:

05-30-31 (LATEST)

APPLICANT'S CURRENT ESTIMATED COMMERCIAL OPERATION DATE: 05-00-84 CURREHT ESTIMATED PERCENT CONSTRUCTIOc COMPLETE: 81%

COMMENTS REGARDING CURRENT CONSTRUCTION STATUS:

ESTIMATED ACTUAL ESTIMATED ACTUAL ESTIMATED START START COMPLETION COMPLETION % COMPLETE MOBILIZE AND PREPARE SITE:

10-00-74 03-00-76 100%

PLACE STRUCTURAL CONCRETE:

03-00-76 05-00-83 99%

INSTALL REACTOR PRESSURE VESSEL:

07-00-78 09-00-78 10'0%

INSTALL LARGE BORE PROCESS PIPE:

07-00-78 07-00-83 93%

INSTALL LARGE BORE PIPE HANGERS, RESTRAINTS AND SHUBBERS:

08-00-83 73%

INSTALL SMALL BORE PIPE:

08-00-83 70%

INSTALL CABLE TRAY:

06-00-82 99%

INSTALL EXPOSED METAL CONDUIT:

09-00-83 69%

INSTALL POWER, CCHTROL, INSTRUMENTATION AND SECURITY CABLE:

08-03-79 10-00-83 53%

INSTALL ELECTRICAL TERMINATIONS:

10-17-79 10-00-83 58%

CONDUCT REACTOR COLD HYDROSTATIC TEST 03-00-83 03-00-83 0%

CONDUCT HOT FUNCTIONAL TEST:

N/A N/A N/A CONDUCT PREOP AND ACCEPTANCE TESTS HECESSARY FOR FUEL LOAD:

03-00-79 10-00-83 0%

i C0NSTRUCTION STATUS REPQRT

'PAGE NO: 2-092 PERRY 2 NUCLEAR POWER PLANTS STATUS AS OF:.12-31-81 PLANT CHARACTERISTICSt KEY PERS0NNELa DOCKET NO:

05000441 CORPORATE CONTACT:

D. R. DAVIDSON, VICE PRESIDENT CP NO. 8 DATE ISSUED: CPPR-149/ 05-03-77 ENGINEERING CP EXPIRATION DATE:

CORPORATE ADDRESS:

P. O.

BOX 5000/55 PUBLIC SQUARE APPLICANT:

CLEVELAND ELECTRIC ILLUMINATING CLEVELAND, ONIO 41101 i

PLANT LOCATION:

7 MI NE OF PAINESVILLE, ONIO IE REGION:

3 CORPORATE PHONE NO:

(216) 622-9808 AE GILBERT ASSOCIATES NSSS GENERAL ELECTRIC CONSTRUCTOR:

KAISER ENGINEERS NRC LPM:

M. D. NOUSTON REACTOR TYPE:

BWR IE PROJECT INSPECTOR:

DER (MWE):

1205 IE RESIDENT INSPECTOR:

M. GILDNER l

INSPECTION STATUS:

FUEL L0AD DATE CNANGES TIME PERIOD AS REP 0RTED BY UTILITY OCT. 1981 - DEC. 1981 i

REPORT NEW REASON FOR CHANGE REPORT.

BEG DATE END DATE DATE SCHEDULE REPORTED BY UTILITY NUMBER OF INSP.

OF INSP.

i 03-25-77 12-30-82 LICENSING DELAYS, t

8115 10-07-81 10-09-81 01-18-79 09-00-83 SCHEDULE REEVALUATION.

02-00-80 05-00-F7 NO REASON PROVIDED.

]

Inspection Reports are available at local PDRs.

~

L0 CAL PUBLIC DDCUMENT R 0 0 M:

PERRY PUBLIC LIBRARY 3753 MAIN STREET PERRY, ONIO 44081 l

l l

C0NSTRUCTION STATUS REPQRT PAGE NO: 2-093 PERRY 2 NUCLEAR POWER PLANTS STATUS AS OF:

12-31-81 00NSTRUCTION S T A T U S:

APPLICANT'S CURRENT ESTIMATED FUEL LOADING DATE:

05-00-87 APPLICANTS CONSTRUCTION COMPLETION ESTIMATE AS APPLICANT'S PREVICUS ESTIMATED FUEL LOADING DATE:

09-00-83 DEFINED IN CP (EARLIEST)

APPLICANT'S ESTIMATED FUEL LOADING DATE AT CP ISSUANCE:

12-30-82 (LATEST)

APPLICANT'S CURRENT ESTIMATED COMMERCIAL OPERATION DATE: 05-00-88 CURRENT ESTIMATED PERCENT CONSTRUCTION COMPLETE: 41%

COMMENTS REGARDING CURRENT CONSTRUCTION STATUS:

ESTIMATED ACTUAL ESTIMATED ACTUAL ESTIMATED START START COMPLETION COMP L E T I_EH % COMPLETE MOBILIZE AND PREPARE SITE:

10-00-74 04-00-76 100%

PLACE STRUCTURAL CONCRETE:

04-00-76 10-00-85 89%

INSTALL REACTOR PRESSURE VESSEL:

10-00-78 01-00-79 100%

INSTALL LARGE BORE PROCESS PIPE:

04-00-79 11-00-86 18%

INSTALL LARGE BORE PIPE HANGERS, RESTRAINTS AND SNUBBERS:

04-00-79 11-00-86 14%

-INSTALL SMALL BORE PIPE:

12-00-86 0%

INSTALL CABLE TRAY:

10-00-78 09-00-85 30%

INSTALL EXPOSED METAL CONDUIT:

10-00-78 01-00-87 24%

INSTALL POWER, CONTROL, INSTRUMENTATION AND SECURITY CABLE:

04-00-80 02-00-87 0%

INSTALL ELECTRICAL TERMINATIONS:

06-00-80 02-00-87 0%

CONDUCT REACTOR COLD HYDROSTATIC TEST:

04-00-86 04-00-86 0%

CONDUCT HOT FUNCTIONAL TEST:

N/A N/A N/A N/A N/A CONDUCT PREOP AND ACCEPTANCE TESTS NECESSARY FOR FUEL LOAD:

01-00-85 04-00-87 0%

1 C0NSTRUCTION STATUS REPQRT PAGE NO: 2-094 PHIPPS BEND 1 NUCLEAR POWER PLANTS STATUS AS OF:

12-31-81 l

PLANT CHARACTERISTICSt KEY rERS0NNELa DOCKET NO:

05000553 CORPORATE CONTACT:

G. KIMMONS, MANAGER CP NO. 8 DATE ISSUED: CPPR-162/ 01-16-78 0FFICE OF ENG. DESIGN & CONST.

i CP EXPIRATION DATE:

04-00-84 CORPORATE ADDRESS:

400 COMMERCE AVENUE APPLICANT:

TENNESSEE VALLEY AUTHORITY KNOXVILLE, TENNESSEE 37902 PLANT LOCATION:

15 MI SW OF KINGSPORT, TENN IE REGION:

2 CORPORATE PHONE NO:

(615) 632-2911 AE TENNESSEE VALLEY AUTHORITY NSSS:

GENERAL ELECTRIC CONSTRUCTOR:

TENNESSEE VALLEY AUTHORITY NRC LPM:

REACTOR TYPE:

BWR IE PROJECT INSPECTOR:

DER (MWE):

1220 IE RESIDENT INSPECTOR:

IN$PECTION STATUSt FUEL L0AD DATE CHANGES TIME PERIOD AS REPORTED BY UTILITY:

OCT, 1981 - DEC. 1981 REPORT NEW REASON FOR CHANGE REPORT BEG DATE END DATE DATE SCHEDULE REPORTED BY UTILITY NUMBER OF INSP.

OF INSP.

09-12-79 02-00-86 NO REASON STATED.

HONE.

09-10-80 12-00-87 NO REASON PROVIDED.

08-14-81 01-00-93 NO REASON PROVIDED.

INSPECTION REPORTS ARE AVAILABLE AT LOCAL PDR'S.

L0 CAL PUBLICD0CUMENT. R 0 0 i:

KINGSPORT PUBLIC LIBRARY BROAD 4 NEW STREETS KINGSPORT, TENNESSEE 37660

C.0 N S T R U C T I O N STATUS REPQRT PAGE NO: 2-095~

PHIPPS BEND 1 NUCLEAR POWER PLANTS STATUS AS OF 12-31-81 C0NSTRUCTION 5TATUS:

APPLICANT'S CURRENT ESTIMATED FUEL LOADING DATE:

01-00-93 APPLICANTS CONSTRUCTION COMPLETION ESTIMATE AS APPLICANT'S PREVIOUS ESTIMATED FUEL LOADING DATE:

12-00-87 DEFINED IN CP: (EARLIEST)

APPLICANT'S ESTIMATED FUEL LOADING DATE AT CP ISSUANCE:

01-00-83 (LATEST)

APPLICANT'S CURRENT ESTIMATED COMMERCIAL OPERATION DATE: 10-00-93 CURRENT ESTIMATED PERCENT CONSTRUCTION COMPLETE: 29%

COMMENTS REGARDING CURRENT CONSTRUCTION STATUS: CONSTRUCTION IN DEFERRED STATUS EFFECTIVE 01-01-82.

ESTIMATED ACTUAL ESTIMATED ACTUAL ESTIMATED START START COMPLETION COMPLETION % COMPLETE MOBILIZE AND PREPARE SITE:

10-19-77 12-04-89 70%

PLACE STRUCTURAL CONCRETE:

08-18-78 02-17-93 67%

INSTALL REACTOR PRESSURE VESSEL:

11-1s-80 12-01-80 100%

INSTALL LARGE BORE PROCESS PIPE:

04-30-79 06-29-92 19%

INSTALL LARGE BORE PIPE HANGERS, RESTRAINTS AND SHUBBERS:

0%

INSTALL SMALL BORE PIPE:

0%

INSTALL CABLE TRAY:

04-14-80 04-26-91 14%

INSTALL EXPOSED METAL CONDUIT:

04-14-80 04-26-91 6%

INSTALL POWER, CONTROL, INSTRUMENTATION AND SECURITY CABLE:

02-27-81 02-17-93 6%

INSTALL ELECTRICAL TERMINATIONS:

01-12-90 02-17-93 4%

CONDUCT REACTOR COLD NYDR0 STATIC TEST:

06-22-92 06-29-92 0%

CONDUCT HOT FUNCTIONAL TEST:

N/A N/A 0%

. CONDUCT PREOP AND ACCEPTANCE TESTS NECESSARY FOR FUEL LOAD:

06-23-91 12-29-92 0%

'l C0NSTRUCTION STATUS REP 0RT PAGE NO: 2-096 PHIPPS BEND 2 NUCLEAR POWER PLANTS STATUS AS OF:

12-31-81 PLANT CHARACTERISTICSt KEY P E R S 0 N N E L:

7 DOCKET NO:

05000554 CORPORATE CONTACT:

G. CIMMcHS, MANAGER CP NO. 8 DATE ISSUED: CPPR-163/ 01-16-78 0FFICE OF ENG. DESIGN & CONS (.

CP EXPIRATION DATE:

CORPORATE ADDRESS:

400 COMMERCE AVENUE APPLICANT:

TENNESSEE VALLEY AUTHORITY KNOXVILLE, TENNESSEE 37902 PLANT LOCATION:

15 MI SW OF KINGSPORT, TENN a

i IE REGION:

2 CORPORATE PHONE NO:

(615) 632-2911 i

AE TENNESSEE VALLEY AUTHORITY l

l NSSS:

GENERAL ELECTRIC CONSTRUCTOR:

TENNESSEE VALLEY AUTHORITY NRC LPM:

REACTOR TYPE:

BWR IE PROJECT INSPECTOR:

DER (MWE):

1220 IE RESIDENT INSPECTOR:

IN5PECTION STATUSt FUEL L0AD DATE CHANGES TIME PERIOD AS REP 0RTED 8Y U T I L I T Y:

OCT. 1981 - DEC, 1981 REPORT NEW REASON FOR CHANGE NUMBER OF INSP.

OF INSP.

_ SCHEDULE REPORTED BY UTILITY REPORT BEG DATE END DATE DATE i

09-12-79 05-00-88 HO REASON STATED.

NONE.

09-10-80 07-00-93 NO REASON PROVIDED.

08-14-81 N/S DEFERRED.

INSPECTION REPORTS ARE AVAILABLE AT LOCAL PDR'S.

I L0 CAL PUBLIC D0CUMENT R 0 0 M:

KINGSPORT PUBLIC LIBRARY BROAD & NEW STREETS KINGSPORT, TENNESSEE 37660

_. ~ _ _ _ _. _..

1 l

C0NSTRUCTION STATUS REP 0RT PAGE NO: 2-097 PHIPPS BEND 2 NUCLEAR POWER PLANTS STATUS AS OF:

12-31-81' C0NSTRUCTION S T A T U S:

APPLICANT'S CURRENT ESTIMATED FUEL LDADING DATE:

N/S APPLICANTS CONSTRUCTION COMPLETION ESTIMATE AS APPLICANT'S PREVIOUS ESTIMATED FUEL LOADING DATE:

07-00-93 DEFINED IN CP: (EARLIEST)

APPLICANT'S ESTIMATED FUEL LOADING DATE AT CP ISSUANCE:

01-00-83 (LATEST)

APPLICANT'S CURRENT ESTIMATED COMMERCIAL OPERATION DATE: N/S CURRENT ESTIMATED PERCENT CONSTRUCTICH COMPLETE:

5%

COMMENTS REGARDING CURRENT CONSTRUCTION STATUS: PROJECT DEFERRED.

I t

ESTIMATED ACTUAL ESTIMATED ACTUAL ESTIMATED i

START START COMPLETION COMPLETTON % COMPLETE MOBILIZE AND PREPARE SITE:

N/S PLACE STRUCTURAL CONCRETE:

INSTALL REACTOR PRESSURE VESSEL:

INSTALL LARGE BORE PROCESS PIPE:

i INSTALL LARGE BORE PIPE HANGERS, RESTRAINTS AND SNUBBERS:

i INSTALL SMALL BORE PIPE:

INSTALL CABLE TRAY:

i INSTALL EXPOSED METAL CONDUIT:

IMSTALL POWER, CONTROL, INSTRUMENTATION AND SECURITY CABLE:

INSTALL ELECTRIC... TERMINATIONS:

CONDUCT REACTOR COLD HYDROSTATIC TEST:

CONDUCT NOT FUNCTIONAL TEST CONDUCT PREOP AND ACCEPTANCE TESTS NECESSARY FOR FUEL LOAD:

l

C0NSTRUCTION STATUS REP 0RT PAGE NO: 2-098 QIVER BEND 1 NUCLEAR P0WER PLANTS STATUS AS OF:

12-31-81 PLANT C H A R A C T E R I S T I C S:

KEY PERS0NNEL:

DOCKET NO:

05000458 CORPORATE CONTACT:

J.

E. BOOKER, MNGR.-TECH. PROG.

RIVER BEND NUCLEAR GROUP CP NO. & DATE ISSUED: CPPR145 / 03-25-77 CORPORATE ADDRESS:

P.

O.

BOX 2951 CP EXPIRATION DATE:

03-31-83 BEAUMONT, TEXAS 77704 APPLICANT:

GULF STATES UTILITIES PLANT LOCATION:

24 MI NNW OF BATON ROUGE, LA CORPORATE PHONE NO:

(713) 838-3843. EXT. 281 IE REGION:

4 AE STONE 8 WEBSTER NSSS:

GENERAL ELECTRIC CONSTRUCTOR:

STONE a WEBSTER NRC LPM J. STEFFAN0 IE PROJECT INSPECTOR:

REACTOR TYPE:

BWR IE RESIDENT INSPECTOR:

A. B. BEACH DER (MWE):

0934 INSPECTION STATUSt FUEL L0AD DATE CHANGES TIME PERIOD AS REP 0RTED BY U T I L I T Y:

OCT. 1981 - DEC. 1981 REPORT NEW REASON FOR CHANGE REPORT BEG DATE END DATE DATE SCHEDULE REPORTED BY UTILITY NUMBER OF INSP.

OF INSP.

05-13-77 03-00-83 DENIAL OF RATE INCREASE COMBINED WITH REGULATORY AND CONSTRUCTION DELAYS.

8111 10-01-81 11-21-81 8112 11-02-81 11-06-81 05-19-78 03-00-84 INABILITY TO OBTAIN ADEQUATE RATE RELIEF.

8113 11-02-81 11-06-81 12-03-80 10-00-83 NO REASON PROVIDED.

8114 12-07-81 12-11-81 11-10-81 04-00-85 FUNDING LIMIT ATIONS OF THE PROJECT.

Inspection reports are avalIable at Iocal PDRs.

L0 CAL PUBLIC D0CUMENT R 0 0 M:

AUDUBON LIBRARY GOVERNMENT DOCUMENTS DEPT.

WEST FELICIANA BRANCH LOUISIANA STATE UNIVERSITY FERDINAND STREET BATON ROUGE, LOUISIANA 70803 ST. FRANCISVILLE, LA 70775

. ~..

C0NSTRUCTION STATUS REPQRT PAGE NO: 2-099 RIVER BEND.1 NUCLEAR POWER PLANTS STATUS A3 0F 1~-31,

C0NSTRUCTION STATUSt APPLICANT'S CURREPT ESTIMATED FUEL LOADING DATC:

04-00-85 APPLICANTS CONSTRUCTION COMPLETION ESTIMATE AS-APPLICANT'S PREVIOUS ESTIMATED FUEL LOADING DATE:

10-00-83 DEFINED IN CT: (EARLIEST) 03-31-81 APPLICANT'S ESTIMATED FUEL LOADING DATE AT CP ISSUANCE:

10-00-81 (LATEST) 03-31-83 APPLICANT'S CURRENT ESTIMATED COMMERCIAL OPERATION DATE: 12-00-85 CURRENT ESTIMATED PERCENT CONSTRUCTION COMPLETE: 43%

COMMENTS REGARDING CURRENT CONSTRUCTION STATUS:

ESTIMATED ACTUAL ESTIMATED ACTUAL ESTIMATED START START COMPLETION COMPLETION % COMPLETE MOBILIZE AND PREPARE SITE:

04-08-79 04-08-79 10-31-84 88%

PLACE STRUCTURAL CONCRETE:

08-20-79 08-20-79 10-23-83 68%

INSTALL REACTOR PRESSURE VESSEL:

06-21-81 06-21-81 06-26-81 06-26-81 100%

INSTALL LARGE BORE PROCESS PIPE:

07-01-79 07-01-79 02-29-84 27%

INSTALL LARGE BORE PIPE HANGERS, RESTRAINTS AND SNUBBERS:

07-01-79 07-01-79 02-29-84 8%

INSTALL SMALL BORE PIPE:

08-01-80 08-01-80 10-16-84 3%

l l

INSTALL CABLE TRAY:

04-23-81 04-23-81 06-13-83 20%

INSTALL EXPOSED METAL CONDUIT:

10-01-81 10-01-81 01-16-84 23%

INSTALL POWER, CONTROL, INSTRUMENTATION AND SECURITY CABLE:

10-16-81 10-16-81 03-03-84 1%

INSTALL ELECTRICAL TERMINATIONS:

10-16-81 10-16-81 03-03-84 1%

CONDUCT REACTOR COLD NYDR0 STATIC TEST:

05-16-84 05-31-84 0%

d CONDUCT NOT FUNCTIONAL TEST:

N/A N/A N/A N/A L

CONDUCT PREOP AND ACCEPTANCE TESTS NECESSARY FOR FUEL LOAD:

10-01-83 04-00-85 0%

o C0N$TRUCTION STATUS REPORT PAGE NO.2-100 RIVER BEND 2 NUCLEAR P0WER PLANTS STATUS AS OF 12-31-81 PLANT C N A R A C T E R I S T I C S:

KEY P E R S 0 N N E La DOCKET Nor 05000459 CORPORATE CONTACT:

J.

E.~ BOOKER, MNGR.-TECN. PROG.

CP NO. 4 DATE ISSUED: CPPR146 / 03-25-77 RIVER BEND NUCLEAR GROUP CP EXPIRATION DATE:

03-31-83 CORPORATE ADDRESS:

P. O. BOX 2951 APPLICANT:

GULF STATES UTILITIES BEAUMONT, TEXAS 77704 PLANT LOCATION:

24 MI NNW OF BATON ROUGE, LA IE REGION:

4 CORPORATE PHONE NO:

(713) 838-3843, EXT. 281 AE STONE 4 WEBSTER NS$$8 GENERAL ELECTRIC CONSTRUCTOR:

STONE 4 WEBSTER NRC LPM:

J. STEFFAND REACTOR TYPE:

BWR IE PROJECT INSPECTOR:

DER (MWE):

0934 IE RESIDENT INSPECTOR:

A. B. BEACH IN$PECTION S T A T U S:

FUEL L0AD DATE CNANGES TIME PERIOD AS REPQRTED BY U T I L I T Y:

OCT. 1981 - DEC, 1981 REPORT N EW REASON FOR CHANGE REPORT BEG DATE END DATE DATE SCHEDULE REPORTED BY UTILITY NUMBER 0F INSP.

OF INSP.

05-19-78 INDEF.

INDEFINITE DELAY CONTINUES DUE TO None FINANCIAL CONSIDERATIONS.

Inspection reports are available at Iocal PDRs.

i.

1 L0 CAL PUBLIC D0CUMENT R 0 0 M:

AUDUBON LIBRARY GOVERNMENT DOCUMENTS DEPT.

WEST FELICIANA BRANCH LOUISIANA STATE UNIVERSITY FERDINAND STREET BATON ROUGE, LOUISIANA 70803 ST. FRANCISVILLE, LA 70775

m__

C0NSTRUCTION STATUS REPORT PAGE NO: 2-101 RIVER BEND 2 NUCLEAR P0WER PLANTS STATUS AS OF:

12-31-81

-C 0.H S T R U C T I O N S T A T U 5:

APPLICANT'S CURRENT ESTIMATED FUEL LOADING DATE:

N/S APPLICANTS CONSTRUCTION COMPLETION ESTIMATE AS APPLICANT'S PREVIOUS ESTIMATED FUEL LOADING DATE:

N/S DEFINED IN CP (EARLIEST) 03-31-83 APPLICANT'S ESTIMATED FUEL LOADING DATE AT CP ISSUANCE:

N/S (LATEST) 03-31-85 APPLICANT'S CURRENT ESTIMATED COMMERCIAL OPERATION DATE: N/S CURRENT ESTIMATCD PERCENT CONSTRUCTION COMPLETE:

1%

COMMENTS PEGARDING CURRENT CONSTRUCTION STATUS: INDEFINITE DELAY DUE TO FINANCIAL CONSIDERATIONS.

ESTIMATED ACTUAL ESTIMATED ACTUAL ESTIMATED START START COMPLETION COMPLETION % COMPLETE MOBILIZE AND PREPARE SITE:

N/S PLACE STRUCTURAL CONCRETE:

INSTALL R'EACTOR PRESSURE VESSEL:

INSTALL LARGE BORE PROCESS PIPE:

INSTALL LARGE BORE PIPE MANGERS, RESTRAINTS AND SNUBBERS:

INSTALL SMALL BORE PIPE:

a INSTALL CABLE TRAY:

INSTALL EXPOSED METAL CONDUIT:

INSTALL POWER, CONTROL, INSTRUMENTATION AND SECURITY CABLE:

INSTALL ELECTRICAL TERMINATIONS:

CONDUCT REACTOR COLD HYDROSTATIC. TEST:

CONDUCT HOT FUNCTIONAL TEST:

CONDUCT PREOP AND ACCEPTANCE TESTS NECESSARY FOR FUEL LOAD:

j i

p t

C0N5TRUCT. ION 5TATUS REPORT PAGE NO: 2-102 SAN ONOFRE 2 NUCLEAR-. POWER PLANTS STATUS'AS OF:

12-31-81 PLANT C H A R A C T E R I S T I C S:

KEY P E R S 0 N N E L:

DOCKET NO:

05000361 CORPORATE CONTACT:

DR. L. T. PAPAY, VICE PRESIDENT CP NO. 8 DATE ISSUED: CPPR-97 / 10-18-73 ADVANCED ENGINEERING CP EXPIRATION DATE:

06-01-80 CORPORATE ADDRESS:

2244 WALNUT GROVE AVENUE APPLICANT:

SOUTHERN CALIFORNIA EDISON ROSEMEAD, CALIFORNIA 91770 i

PLANT LOCATION:

5 MI S OF SAN CLEMENTE, CA IE REGION:

5 CORPORATE PHONE NO:

(213) 592-1472 AE:

BECHTEL NSSS:

COMBUSTION ENGINEERING 1

CONSTRUCTOR:

BECHTEL NRC LPM:

H. ROOD REACTOR TYPE:

PWR IE PROJECT INSPECTOR:

DER (MWE):

1140 IE RESIDENT INSPECTOR:

R. J. PATE f-

. INSPECTION STATUS:

FUEL L0AD DATE CHANGES i

TIME PERIOD AS REP 0RTED BY U T I L I T Y:

OCT, 1981 - DEC. 1981 REPORT HEW REASON FOR CHANGE REPORT BEG DATE END DATE DATE SCHEDULE REPORTED BY UTILITY HVMBE8 0F INSP.

OF INSP.

11-14-74 08-00-79 ISSUANCE OF A PERMIT BY THE CALIFORNIA l

81-28 10-26-81 12-04-81 COASTAL COMMISSION.

81-29 10-13-81 23-81 12-12-74 12-10-79 NO REASON NOTED.

81-30 11-09-81 11-10-81 10-22-75 02-00-80 LABOR DIFFICULTIES.

31-31 10-26-81 11-06-81 02-00-80 11-00-80 NO REASON PROVIDED.

I 81-32 10-05-81 10-09-81 04-18-80 04-15-81 NO REASON PROVIDED.

81-33 CANCELLED 02-18-81 06-16-81 NO REASON PROVIDED.

81-34 11-16-81 12-11-81 09-30-81 10-15-81 NO REASON PROVIDED.

81-35 11-16-81 12-04-81 81-36 12-14-81 OPEN 1

Inspection Reports are available at local PDRs.

1 i

L0 CAL P U B L-I C D0CUMENT R 0 0 Ms MISSION VIEJO BRANCH LIBRARY 24851 CHRISANTA DRIVE MISSION VIEJO, CALIFORNIA 92676

. - - - ~ - -. - - -. -.....-.. ~. -

C0NSTRUCTION STATUS REP 0RT PAGE NO: 2-103 SAN ONOFRE 2 NUCLEAR POWER PLANTS STATUS AS OF: 31-81 4

C0N5TRUCTION S T A T U S:

1 APPLICANT'S CURRENT ESTIMATED FUEL LOADING DATE:

10-15-81 APPLICANTS CONSTRUCTION COMPLETION ESTIMATE AS AP?LICANT'S PREVIOUS ESTIMATED FUEL LOADING DATE:

06-16-81 DEFINED IN CP: (EARLIEST)

APPLICANT'S ESTIMATED FUEL LOADING DATE AT CP ISSUANCE:

02-00-79 (LATEST) 02-02-82 APPLICANT'S CURRENT ESTIMATED COMMERCIAL OPERATION DATE: 07-01-82 CURRENT ESTIMATED PERCENT CONSTRUCTION COMPLETE: 99%

COMMENTS REGARDING CURRENT CONSTRUCTION STATUS:

4 4

ESTIMATED ACTUAL ESTIMATED ACTUAL FSTIMATED START START COMPLETION COMPLETION % COMPLETE MOBILIZE AND PREPARE SITE:

02-04-74 10-07-74 100%

PLACE STRUCTURAL CONCRETE:

11-24-74 06-16-75 100%

INSTALL REACTOR PRESSURE VESSEL:

04-25-77 04-29-77 100%

INSTALL LARGE BORE PROCESS PIPE:

11-15-75 06-30-80 100%

INSTALL LARGE BORE PIPE HANGERS, RESTRAINTS AND SNUBBERS:

11-01-76 12-01-80 100%

INSTALL SMALL BORE PIPE:

08-01-76 05-15-80 100%

1 INSTALL CABLE TRAY:

02-01-76 06-01-80 100%

INSTALL EXPOSED METAL CONDUIT:

07-01-76 12-31-80 100%

INSTALL POWER, CONTROL, INSTRUMENTATION AND SECURITY CABLE:

02-11-77 12-01-80 100%

INSTALL ELECTRICAL TERMINATIONS:

11-01-77 12-31-80 100%

CONDUCT REACT 0* COLD HYDROSTATIC TEST 09-12-80 09-22-80 100%

CONDUCT HOT FUNCTIONAL TEST:

12-11-80 03-20-81 100%

CONDUCT PREOP AND ACCEPTANCE TESTS NECESSARY FOR FUEL LOAD:

01-01-80 10-15-81 98%

4 1

+

i i

r

C0NSTRUCTION STATUS REPORT PAGE NO: 2-104 SAN ONOFRE 3

.M 18 C L E A R POWER PLANTS STATUS AS OF 12-31-81 PLANT C H A R A C T E R I 5 T I C S:

KEY PERS0NNEL DOCKET NO:

05000362 CORPORATE CONTACT:

DR. L. T. PAPAY, VICE PRESIDENT CP NO. 8 DATE ISSUED: CPPR-98 / 10-18-73 '

CORPORATE ADDRESS:

2244 WALNUT GROVE AVENUE ADVANCED ENGINEERING CP EXPIRATION DATE:

06-01-81 APPLICANT:

SOUTHERN CALIFORNIA EDISON ROSEMEAD, CALIFORHJA 91770 PLANT LOCATION:

5 MI S OF SAN CLEMENTE, CA IE REGIDH:

5 CORPORATE PHONE NG:

(213) 592-1472 AE:

BECHTEL HSSS:

COMBUSTION ENGINEERING CONSTRUCTOR:

BECHTEL HRC LPM:

H. ROOD REACTOR TYPE:

PWR IE PROJECT INSPECTOR:

DER (MWE):

1140 IE RESIDENT INSPECTOR:

R. J. PATE IN5PECTION 5 T A T U S:

FUEL L0AD DATE CHANGES TIME PERIOD AS REP 0RTED BY UTIL I T Y:

OCT. 1981 - DEC. 1981 REPORT NEW REASON FOR CHANGE REPORT BEG DATE END DATE DATE SCHEDULE REPORTED BY UTILITY NUMBER OF INSP.

OF INSP.

11-14-74 11-00-80 ISSUANCE OF A PERMIT BY THE CALIFORNIA 81-08 10-26-81 11-06-81 COASTAL COMMISSION.

81-09 11-16-81 12-11-81 12-12-74 03-09-81 NO REASON HOTED.

10-22-75 05-00-81 LABOR DIFFICULTIES.

Inspection Reports are available at Iocal PDRs.

02-00-80 11-00-81 NO REASON PROVIDED.

02-18-81 09-00-82 NO REASON PROVIDED.

09-30-81 11-01-82 NO REASON PROVIDED.

L0 CAL PUBLIC D0CUMENT R 0 0 M:

MISSION VIEJO BRANCH LIBRARY 24851 CHRISANTA DRIVE MISSION VIEJO, CALIFORNIA 92676 t

--- ~ _... -

.~ -

C0NSTRUCTION STATUS REP 0RT PAGE NO: 2-105 SAN CHOFRE 3 HUCLEAR P O W E.R P L A N'T S STATUS AS OF 12-31-81 C0N$TRUCTION 5TATUSt l

APPLICANT'S CURRENT ESTIMATED FUEL LOADING DATE:

11-01-82 APPLICANTS CONSTRUCTION COMPLETION ESTIMATE AS APPLICANT'S PREVIOUS ESTIMATED FUEL LOADING DATE:

09-00-82 DEFINED IN CP (EARLIEST)

APPLICANT'S ESTIMATED FUEL LOADING DATE AT CP ISSUANCE:

05-00-80 (LATEST) 03-02-83 APPLICANT'S CURRENT ESTIMATED COMMERCIAL OPERATION DATE: 08-16-83 CURRENT ESTIMATED PERCENT CONSTRUCTION COMPLETE: 87%

COMMENTS REGARDING CURRENT CONSTRUCTION STATUS:

ESTIMATED ACTUAL ESTIMATED ACTUAL ESTIMATED START START COMPLETION COMPLETION % COMPLETE j

MOBILIZE AND PREPARE SITE:

02-07-74 10-07-74 100%

. PLACE STRUCTURAL CONCRETE:

11-24-74 06-16-75 100%

4 INSTALL REACTOR PRESSURE VESSEL:

12-19-77 12-23-77 100%

INSTALL LARGE BORE PROCESS PIPE:

04-01-77 12-00-81 99%

INSTALL LARGE BORE PIPE HANGERS, RESTRAINTS AND SNUBBERS:

09-01-77 03-00-82 96%

INSTALL SMALL BORE PIPE:

01-01-77 03-00-82 99%

I'NSTALL CABLE TRAY:

02-01-77 09-30-81 100%

INSTALL EXPOSED METAL CONDUIT:

06-01-77 04-00-82 99%

I'NSTALL POWER, CONTROL, INSTRUMENTATION AND SECURITY CABLE:

02-15-78 05-00-82 92%

INSTALL ELECTRICAL TERMINATIONS:

02-01-79 06-00-82 84%

CONDUCT REACTOR COLD HYDROSTATIC TEST 03-10-82 03-23-82 0%

CONDUCT NOT FUNCTIONAL TEST:

06-04-82 07-28-82 0%

CONDUCT PREOP AND ACCEPTANCE TESTS NECESSARY FOR FUEL LOAD 08-01-81 10-15-82 0%

6 1

C0NSTRUCTION STATUS REPQRT PAGE ND: 2-106 JEABROOK 1 NUCLEAR POWER PLANTS STATUS AS OF 12-31-81 PLANT C H A R A C T E R I S T I C S:

KEY P E R S 0 N N E L:

DOCKET NO:

05000443 CORPORATE CONTACT:

W. C. TALLMAN, CHIEF EXEC. OFFICER CP NO. & DATE ISSUED: CPPR-135/ 07-07-76 CP EXPIRATION DATE:

06-30-83 CORPORATE ADDRESS:

1000 ELM STREET APPLICANT:

PUBLIC SERVICE OF NEW HAMPSHIRE MANCHESTER, NEW HAMPSHIRE 03105 PLANT LOCATION:

10 MI S OF PORTSMOUTH, NH IE REGION:

1 CORPORATE PHONE NO:

(603) 669-4000 AE:

UNITED ENG. & CONSTRUCTORS MSSS:

WESTINGHOUSE CONSTRUCTOR:

UNITED ENG. 8 CONSTRUCTORS NRC LPM:

L. WHEELER REACTOR TYPE:

PWR IE PROJECT INSPECTOR:

DER (MWE):

1198 IE RESIDENT INSPECTOR:

A. C. CERNE INSPECTION S T A T U 5:

FUEL L0AD DATE CHANGES TIME PERIOD A5 REP 0RTED BY UTIL I T Y:

OCT, 1981 - DEC, 1981 REPORT NEW REASON FOR CHANGE REPORT BEG DATE END DATE DATE SCHEDULE REPORTED BY UTILITY NUMBER OF INSP.

OF INSP.

09-06-77 09-01-82 DELAYS DUE TO EPA REVERSAL OF PREVIOUS 81-11 10-15-81 10-15-81 APPROVAL OF ONCE THROUGH CIRCULATING 81-12 10-05-81 11-16-81 WATER SYSTEM & SUBSEQ. NRC WITHDRAWAL OF 81-13 11-03-81 11-06-81 CONST PERMIT, & TIME REQ TO REMOBILIZE 81-14 11-17-81 01-08-82 11-08-78 01-01-83 SCHEDULE REEVALUATION.

04-04-81 11-30-83 SCHEDULE REEVALUATION.

Inspection Reports are available at local PDRs.

L0 CAL PUBLIC D0CUMENT R00M EXETER PUBLIC LIBRARY FRONT STREET EXETER, NEW HAMPSHIRE 03883

A i

C0NSTRUCTION STATUS REPORT PAGE NO: 2-107 SEaBROOK't NUCLEAR POWER PLANTS STATUS A'S OF:

12-31-81 C 0 N S'T R U C T I O N S T A T U S:

APPLICANT'S CURRENT ESTIMATED FUEL LOADING DATE:

11-30-83 APPLICANTS CONSTRUCTION COMPLETION ESTIMATE'AS APPLICANT'S PREVIOUS ESTIMATED FUEL LOADING DATE:

.01-01-82 DEFINED IN CP: (EARLIEST) 02-00-79 APPLICANT'S ESTIMATED FUEL LOADING DATE AT CP ISSUANCE:

08-01-81 (LATEST) 06-00-83 APPLICANT'S CURRENT ESTIMATED COMMERCIAL OPERATION DATE: 02-28-84 h

CURRENT ESTIMATED PERCENT CONSTRUCTION COMPLETE: 59%

i COMMENTS REGARDING CURRENT CONSTRUCTION STATUS:

l ESTIMATED ACTUAL ESTIMATED ACTUAL ESTIMATED START START COMPLETION COMPLETION % COMPLETE MOBILIZE AND PREPARE SITE:

07-00-76 08-00-77 08-00-77 100%

PLACE STRUCTURAL CONCRETE:

09-00-77 08-00-83 75%

INSTALL REACTOR PRESSURE VESSEL:

05-00-81 05-00-81 100%

INSTALL LARGE BORE PROCESS PIPE:

10-00-79 09-00-83 36%

INSTALL LARGE BORE PIPE NANGERS, RESTRAINTS AND SNUBBERS:

10-00-79 09-00-83 27%

INSTALL SMALL BORE PIPE:

09-00-80 03-00-83 5%

INSTALL CABLE TRAY:

09-00-79 12-00-82 56%

INSTALL EXPOSED METAL CONDUIT:

04.

79 C7-00-83 27%

INSTALL POWER, CONTROL,. INSTRUMENTATION AND SECURITY CABLE:

05-00-81 07-00-83 9%

INSTALL ELECTRICAL TERMINATIONS:

06-00-81 08-00-83 8%

CONDUCT REACTOR COLD NYDR0 STATIC TEST:

07-00-83 07-00-83 0%-

CONDUCT HOT FUNCTIONAL TEST:

08-00-83 09-00-83 0%

1 CONDUCT PREOP AND ACCEPTANCE TESTS NECESSARY FOR FUEL LOAD:

02-00-82 11-00-83 0%

c k

4 i

r 5

C0NSTRUCTION STATUS REP 0RT PAGE NO: 2-108 SEABROOK 2 NUCLEAR POWER PLANTS STATUS AS OF:

12-31-81 PLANT C H A R A C T E R I S T I C S:

KEY P E R S 0 N N E L:

DOCKET NO:

05000444 CORPORATE CONTACT:

W. C. TALLMAN, PRESIDENT CP h0. 8 DATE ISSUED: CPPR-136/ 07-07-76 CP EXPIRATION DATE:

10-31-84 CORPORATE ADDRESS:

1000 ELM STREET APPLICANT:

PUBLIC SERVICE OF NEW HAMPSHIRE l

MANCHESTER, NEW HAMPSHIRE 03105 PLANT LOCATION:

10 MI S OF PORTSMOUTH, NH IE REGION:

1 CORPORATE PHONE NO:

(603) 669-4000 AE:

UNITED ENG. 8 CONSTRUCTORS NSSS:

WESTINGHOUSE CONSTRUCTOR:

UNITED ENG. & CONSTRUCTORS NRC LPM:

L. WHEELER REACTOR TYPE:

PWR IE PROJECT INSPECTOR:

DER (MWE): '

1198 IE RESIDENT INSPECTOR:

A.

C. CERNE INSPECTION 5 T A T U S:

FUEL L0AD DATE CHANGES TIME PERIOD AS REP 0RTED BY UTILITY OCT, 1981 - DEC. 1981 REPORT HEW REASON FOR CHANGE REPORT BEG DATE END DATE DATE SCHEDULE REPORTED BY UTILITY NUMBER OF INSP.

OF INSP.

09-06-77 09-01-84 DELAYS DUE TO EPA REVERSAL OF PREVIOUS 81-09 10-1S-81 10-15-81 APPROVAL OF ONCE THROUGH CIRCULATING 81-10 10-05-81 11-16-81 WATER SYSTEM & SUBSEQ. NRC WITHDRAWAL OF 81-11 11-17-81 01-08-82 CONST PERMIT. & TIME REQ TO REMOBILIZE 11-08-78 11-01-84 SCHEDULE REEVALUATION.

04-04-81 02-28-86 SCHEDULE REEVALUATION.

Inspection Reports are available at local PDRs.

L0 CAL PUBLIC D0CUMENT R 0 0 M:

EXETER PUBLIC LIBRARY FRONT STREET EXETER, NEW HAMPSHIRE 03883

.~.

C0NSTRUCTION

$TATUS R E P O R'T PAGE NO: 2-109 SEABROOK 2 NUCLEAR PDWER PLANTS STATUS AS OF:

12-31-81 C0NSTRUCTION S T A T U S:

i APPLICANT'S CURRENT ESTIMATED FUEL LOADING DATE:

02-28-86 APPLICANTS CONSTRUCTION COMPLETION ESTIMATE AS APPLICANT'S PREVIOUS ESTIMATED FUEL LOADING DATE:

11-01-84 DEFINED IN CP: (EARLIEST) 01-00-81 APPLICANT'S ESTIMATED FUEL LOADING DATE AT CP ISSUANCE:

10-01-83 (LATEST) 10-00-84 APPLICANT'S CURRENT ESTlMATED COMMERCIAL OPERATION DATE: 05-3t-86 CURRENT ESTIMATED PERCENT CONSTRUCTION COMPLETE: 11%

COMMENTS REGARDING CURRENT CONSTRUCTION STATUS:

4 ESTIMATED ACTUAL ESTIMATED ACTUAL ESTIMATED START START COMPLETION COMPLETION % COMPLETE MOBILIZE AND PREPARE SITE:

07-00-76 08-00-77 100%

i PLACE STRUCTURAL CONCRETE:

08-00-81 07-00-85

-27%

INSTALL REACTOR PRESSURE VESSEL:

08-00-83 09-00-83 0%.

r l

INSTALL LARGE BORE PROCESS PIPE:

01-00-83 02-00-86 0%

4 INSTALL LARGE BORE PIPE NANGERS, RESTRAINTS AND SNUBBERS:

01-00-83 02-00-86 0%

9

' INSTALL SMALL BORE PIPE:

12-00-83 02-00-86 0%

INSTALL CABLE TRAY:

06-00-83 04-00-85 0%

INSTALL EXPOSED METAL CONDUIT:

01-00-83 07-00-85 0%

INSTALL POWER, CONTROL, INSTRUMENTATION AND SECURITY CABLE:

10-00-83 07-00-85 0%

INSTALL ELECTRICAL TERMINATIONS:

11-00-83 08-00-85 0%

CONDUCT REACTOR COLD NYDR0 STATIC TEST:

10-00-85 10-00-85 0%

l CONDUCT NOT FUNCTIONAL TEST:

12-00-85 01-00-86 0%

CONDUCT PREOP AND ACCEPTANCE TESTS NECESSARY FOR FUEL LOAD:

05-00-84 02-00-86 0%

a

C0NSTRUCTION STATUS REPORT PAGE NO: 2-110 SHOREHAM NUCLEAR POWER P L A t' T S STATUS AS OF 12-31-81 PLANT CHARACTER I S T I C S:

KEY P E R S 0 N N E L:

DOCKET NO:

05000322 CORPORATE CONTACT:

M.

S. POLLOCK, VICE PRESIDENT CP NO. 3 DATE ISSUED: CPPR-95 / 04-14-73 CP EXPIRATION DATE:

03-31-83 CORPORATE ADDRESS:

175 EAST OLD COUNTRY ROAD APPLICANT:

LONG ISLAND LIGHTING CO.

HICKSVILLE, NEW YORK 11801 PLANT LOCATION:

BROOKHAVEN, NY (LI)

IE REGION:

1 CORPORATt PHONE NO:

(516) 733-4013 AE STONE & WtBSTER NSSS:

GENERAL ELECTRIC CONSTRUCTOR:

STONE & WEBSTER HRC LPM:

J. H. WILSON REACTOR TYPE:

BWR IE PROJECT INSPECTOR:

L. NARROW DER (MWE):

0849 IE RESIDENT INSPECTOR:

J. C. HIGGINS INSPECTION STATUS:

FUEL L0AD DATE CHAHGES TIME PERIOD AS REPORTED BY U T I L I T Y:

OCT, 1981 - DEC. 1981 REPORT NEW REASON FOR CHANGE REPORT BEG DATE END DATE DATE SCHEDULE REPORTED BY UTILITY NUMBER OF INSP.

OF INSP.

02-20-74 12-00-77 1.

CHANGE IN AEC SEISMIC 8 PIPE BREAK 81-19 11-09-81 11-13-81 CRITERIA RESULTED IN 2 MONTHS 81-20 10-20-81 11-22-81 ADDITIONAL EFFORT IN THE INSTALLATION 81-21 11-07-81 OPEN INV 0F PRIMARY CONTAINMENT & PRV PEDESTAL.

81-22 11-23-81 12-31-81

2. DIFFICULTIES ENCOUNTERED DURING CON-81-23 12-07-81 12-11-81 STRUCTION OF PRIMARY CONTAINMENT WALL

& RPV PEDESTAL AND IMBEDMENT FOR PIPE BREAK INSIDE CONTAINMENT.

11-10-75 12-00-78 1 LABOR STRIKES, UNAVAILABILITY OF Inspection Reports are available at local PDRs.

MATERIAL, WEATHER 8 CONSTRUCTION DIFFICULTIES HAVE RESULTED IN A 12 MONTH DELAY.

09-21-77 03-00-80 1.

LATE DELIVERY OF PURCHASED MATERIAL (PIPING AND VALVES).

2. LOWER THAN EXPECTED LABOR PRODUCTIVITY
3. DESIGN CHANGES DUE TO REG. REQUIREMENTS 01-10-79 06-00-80 MANPOWER CONSTRAINTS AND DESIGN-PROCUREMENT PROBLEMS.

02-00-80 11-00-80 HD REASON PROVIDED.

06-19-80 05-00-82 DELAY DUE TO COMPLETION OF SYSTEMS.

06-09-81 09-00-82 DELAY DUE TO COMPLETION OF SYSTEMS.

L0 CAL PUBLIC D0CUMENT R 0 0 M:

SHOREHAM-WADING RIVER PUBLIC LIBRARY ROUTE 25A SHOREHAM, NEW YORK 11786 i

t

.C0NSTRUCTI6H STATUS REP 0RT PAGE'NO: 2-111 3HOREHAM NUCLEAR POWER PLANTS STATUS AS OF:

12-31-81 C0NSTRUCTION S T A T U S:

APPLICANT'S CURRENT ESTIMATED FUEL LOADING DATE:

09-00-82 APPLICANTS CONSTRUCTION COMPLETION ESTIMATE AS APPLICANT'S PREVIOUS ESTIMATED FUEL LOADING DATE:

05-00-82 DEFINED IN CP: (EARLIEST)

APPLICANT'S ESTIMATED FUEL LDADING DATE AT CP ISSUANCE:

03-00-77 (LATEST) 09-00-82 APPLICANT'S CURRENT ESTIMATED COMMERCIAL OPERATION DATE: 03-00-83 CURRENT ESTIMATED PERCENT CONSTRUCTION COMPLETE: 88%

COMMENTS REGARDING CURRENT CONSTRUCTION STATUS:

ESTIMATED ACTUAL ESTIMATED ACTUAL ESTIMATED START START COMPLETION COMPLETlQH % COMPLETE MOBILIZE AND PREPARE SITE:

11-00-72 03-00-73 1,00%

PLACE STRUCTURAL CONCRETE:

03-00-73 12-00-77 100%

INSTALL REACTOR PRESSURE VESSEL:

03-00-75

.12-00-75 100%

INSTALL LARGE BORE PROCESS PIPE:

05-00-75 10-00-79 100%

INSTALL LARGE BORE PIPE NANGERS, RESTRAINTS AND SHUBBERS:

07-00-75 09-00-82 91%

e INSTALL SMALL BORE PIPE:

05-00-75 09-00-82 95%

INSTALL CABLE TRAY:

02-00-76 09-00-82 99%

. INSTALL EXPOSED METAL CONDUIT:

02-00-76 09-00-82 95%

INSTALL POWER, CONTROL, INSTRUMENTATION AND SECURITY CABLE:

06-00-76 09-00-82 85%

INSTALL ELECTRICAL. TERMINATIONS:

06-00-76 09-00-82 85%

CONDUCT REACTOR COLD NYDR0 STATIC TEST:

10-00-79 10-00-79 10-00-79 100%

CONDUCT NOT FUNCTIONAL TES1:

N/A N/A N/A N/A N/A CONDUCT PREOP AND ACCEPTANCE TESTS HECESSARY FOR FUEL LOAD:

01-00-80 09-00-82 44%

-. ~ -

C0NSTRUCTION STA.TUS REPQRT PAGE MO: 2-112 SOUTH TEXAS 1 NUCLEAR POWER PLANTS STATUS AS OF:

12-31-81 PLANT CHARACTERISTICS KEY P E R S 0 N N E L:

DOCKET NO:

05000498 CORPORATE CONTACT:

J. H. GOLDBERG, VICE PRESIDENT' CP HO. & DATE ISSUED: CPPR-128/ 12-22-75 NUCLEAR ENGINEERING & CONSTRUCTION CP EXPIRATION DATE:

05-31-82 CORPORATE ADDRESS:

P.

O.

BOX 1700 APPLICANT:

HOUSTON LIGHTING AND POWER COMPANY HOUSTON, TEXAS 77001 PLANT LOCATION:

12 MI SSW OF BAY CITY, TEX IE REGION:

4 CORPORATE PHONE NO:

.(713) 486-3828 AE BECHTEL NSSS:

WESTINGHOUSE CONSTRUCTOR:

EBASCG NRC LPM:

D. SELLS REACTOR TYPE:

PWR IE PROJECT INSPECTOR:

DER (MWE):

1250 IE RESIDENT INSPECTOR:

W. HILL INSPECTION S T A T U S:

FUEL LOAD DATE CHANGES r

TIME PERIOD AS REPORTED BY U T I L I T Y:

OCT. 1981 - DEC. 1981 REPORT NEW REASON FOR CHANGE REPORT BEG DATE END DATE DATE 1EHEDULE REPORTED BY UTILITY NUMBER OF INSP.

OF INSP.

SCHEDULE REEVALUATION.

10-30-78 11-00-81 i

8132 09-01-81 10-31-81 01-18-80 09-00-83 SCHEDULE REEVALUATION.

8133 10-06-81 10-23-81 11-18-81 N/A NA : NOT AVAILABLE

,^

8134 10-19-81 10-23-81 8135 10-29-81 11-10-81 8136 11-01-81 12-01-81 i

r Inspection reports are available at local PDRs.

f L

L0 CAL PUBLIC D0CUMENT R 0 0 M:

MATAGORDA COUNTY LAW LIBRARY P. O. BOX 487 BAY CITY, TEXAS 77414.

b b

C0NSTRUCTION

$TATUS REP 0RT PAGE NO: 2-113 SOUTH TEXAS 1 NUCLEAR POWER PLANTS STATUS AS OF 12-31-81 C0NSTRUCTION 5 T A T U 5:

APPLICANT'S CURRENT ESTIMATED FUEL LOADING DATE:

N/A APPLICANTS CONSTRUCTION COMPLETION ESTIMATE AS APPLICANT'S PREVIOUS ESTIMATED FUEL LOADING DATE:

09-01-83 DEFINED IN CP: (EARLIEST)

APPLICANT'S ESTIMATED FUEL LOADING DATE AT CP ISSUANCE:

05-01-80 (LATEST)

APPLICANT'S CURRENT ESTIMATED COMMERCIAL OPERATION DATE: N/A CURRENT ESTIMATED PERCENT CONSTRUCTION COMPLETE: 45%

COMMENTS REGARDING CURRENT CONSTRUCTION STATUS: OWNER IN PROCESS OF CHANGING AE/ CONSTRUCTORS. SCHEDULE BEING RE-EVALUATED.

NA : NOT AVAILABLE.

ESTIMATED ACTUAL ESTIMATED ACTUAL ESTIMATED START START COMPLETION COMPLETION % COMPLETE MOBILIZE AND PREPARE SITE:

09-00-75 12-00-75 100%

PLACE STRUCTURAL CONCRETE:

04-00-76 NA NA INSTALL REACTOR PRESSURE VESSEL:

09-00-79 09-00-79 100%

INSTALL LARGE BORE PROCESS PIPE:

10-00-78 HA NA INSTALL LARGE BORE PIPE HANGERS, RESTRAINTS AND SNUBBERS:

10-00-78 NA NA INSTALL SMALL BORE PIPE:

10-00-78 NA NA INSTALL CABLE TRAY:

10-00-78

'HA NA i

INSTALL EXPOSED METAL CONDUIT:

07-00-78 NA NA INSTALL POWER, CONTROL, INSTRUMENTATION AND SECURITY CABLE:

NA NA NA INSTALL ELECTRICAL TERMINATIONS:

NA NA NA CONDUCT REACTOR COLD HYDROSTATIC TEST:

NA NA NA CONDUCT HOT FUNCTIONAL TEST:

NA NA NA CONDUCT PREOP AND ACCEPTANCE TESTS NECESSARY FOR FUEL LOAD:

NA NA NA m

C0N5TRUCT' ION STATUS REPQRT PAGE NO 2-114 SOUTH TEXAS 2 NUCLEAR POWER PLANTS STATUS AS OF:

12-31-81 PLANT C H A R A C T E R I S T I C S:

KEY P E R S 0 N N E L:

DOCKET NO:

05000499 CORPOELTE CCNTACT:

J. H. GOLDBERG VICE PRESIDENT CP NO. 1 DATE ISSUED: CPPR-129/ 12-22-75 NUCLEAR ENGINEERING & CONSTRUCTION CP EXPIRATION DATE:

10-31-83 CORPORATE ADDRESS:

P. O. BOX 1700 APPLICANT:

HOUSTON LIGHTING AND POWER COMPANY HOUSTON, TEXAS 77001 PLANT LOCATION:

12 MI SSW OF BAY CITY, TEX IE REGION:

4 CORPORATE PHONE NO:

(713) 486-3828 AE BECHTEL NSSS:

WESTINGHOUSE CONSTRUCTOR:

EBASCO NRC.PM:

D. SELLS REACTOR TYPE:

PWR IE PROJECT INSPECTOR:

DER (MWE):

1250 IE RESIDENT INSPECTOR:

W. HILL IN5PECTION 5TATUSt FUEL L0AD DATE CHANGES TIME PERIOD AS REPORTED BY U T I L I T Y:

OCT, 1981 - DEC. 1981 REPORT NEW REASON FOR CHANGE REPORT BEG DATE END DATE DATE SCHEDULE REPORTED BY UTILITY NUMBER OF INSP.

OF INSP.

10-30-78 11-00-82 SCHEDULE REEVALUATIC.!.

8132 09-01-81 10-31-81 01-18-80 09-00-85 SCHEDULE REEVALUATION.

8133 10-06-81 10-23-81 11-18-81 N/A N/A : NOT AVAILABLE.

8134 10-19-81 10-23-81 8135 10-29-81 11-10-81 8136 11-01-81 12-01-81 Inspection reports are available at local PDRs.

L0 CAL PUBLIC D0CUMENT R 0 0 Mt MATAGORDA COUNTY LAW LIBRARY P. O.

BOX 487 BAY CITY, TEXAS 77414

C0N5TRUCTION STATUS REPQRT PAGE NO: 2-115

~

SOUTH TEXAS 2 NUCLEAR POWER PLANTS STATUS AS OF:

12-31-81 C0NSTRUCTION STATUSt APPLICANT'S CURRENT ESTIMATED FUEL LOADING DATE:

N/A APPLICANTS CONSTRUCTION COMPLETION ESTIMATE AS APPLICANT'S PREVIOUS ESTIMATED FUEL LOADING DATE:

09-01-85 DEFINED IN CP (EARLIEST)

APPLICANT'S ESTIMATED FUEL LOADING DATE AT CP ISSUANCE:

10-01-81 (LATEST)

APPLICANT'S CURRENT ESTIMATED COMMERCIAL OPERATION DATE: N/A CURRENT ESTIMATED PERCENT CONSTRUCTION COMPLETE:

18%

COMMENTS REGARDING CURRENT CONSTRUCTION STATUS: OWNER IN PROCESS OF CHANGING AE/ CONSTRUCTORS. SCHEDULE BEING RE-EVALUATED.

N/A : NOT AVAILABLE.

J ESTIMATED ACTUAL ESTIMATED ACTUAL ESTIMATED START START COMPLETION COMPLETION % COMPLETE MOBILIZE AND PREPARE SITE:

09-00-75 12-00-75 100%

PLACE STRUCTURAL CONCRETE:

03-00-77 NA NA INSTALL REACTOR PRESSURE VESSEL:

NA NA NA INSTALL LARGE BORE PROCESS PIPE:

NA NA NA INSTALL LARGE BORE PIPE HANGERS, RESTRAINTS AND SNUBBERS:

NA NA NA INSTALL SMALL BORE PIPE:

NA NA tOL INSTALL CABLE TRAY:

NA NA NA INSTALL EXPDSED METAL CONDUIT:

NA NA NA INSTALL POWER CONTROL, INSTRUMENTATION AND SECURITY CABLE:

NA NA NA INSTALL. ELECTRICAL TERMINATIONS:

NA NA NA CONDUCT REACTOR COLD NYDR0 STATIC TEST:

NA NA NA CONDUCT HOT FUNCTIONAL TEST:

NA NA NA CONDUCT PREOP AND ACCEPTANCE TESTS NECESSARY FOR FUEL LOAD:

NA NA NA 1

C0NSTRUCTION STATUS REPQRT PAGE NO: 2-116 ST LUCIE 2 NUCLEAR P0WER PLANTS STATUS AS OF:

12-31-81 PLANT C H A R A C T E R I S T I C S:

KEY PERS0NNELa DOCKET NO:

05000389 CORPORATE CONTACT:

R. E..UHRIG, VICE PRESIDENT I

CP NO. & DATE ISSUED: CPPR-144/ 05-02-77 NUCLEAR AFFAIRS CP EXPIRATIch DATE:

CORPORATE ADDRESS:

P. O. BOX 529100 APPLICANT:

FLORIDA POWER & LIGHT MIAMI, FLORIDA 33152 PLANT LOCATION:

12 MI SE OF FT. PIERCE FLA IE REGIDH:

2 CORPORATE PHONE NO:

(305) 552-3842 AE2 EBASCO NSSS:

COMBUSTION ENGINEERING CONSTRUCTOR:

EBASCO NRC LPM:

V. HERSES REACTOR TYPE:

PWR IE PROJECT INSPECTOR:

DER (MWE):

0842 IE RESIDENT INSPECTOR:

S.

A.

ELROD INSPECTION S T A T U 5:

FUEL L0AD DATE CHANGES TIME PERIOD AS REP 0RTED BY U T I L I T Y:

OCT. 1981 - DEC. 1981 REPORT NEW REASON FOR CHANGE REPORT BEG DATE END DATE DATE SCHEDULE REPORTED BY UTILITY NUMBER OF INSP.

OF INSP.

03-24-77 06-00-83 1 LWA HALTED BY COURT ORDER.

8120 10-21-81 10-23-81

2. CP WAS ANTICIPATED 03-01-75 BUT 8121 11-02-81 11-06-81 EARLIEST ANTICIPATED DATE 06-01-77.

8122 11-02-81 11-09-81 03-01-78 10-00-82 REEVALUATION OF PROJECT.

8123 11-16-81 11-20-81 10-17-78 05-00-82 REEVALUATION OF PROJECT.

8124 11-23-81 11-25-81 05-15-80 10-00-82 NO REASON PROVIDED.

8125 12-14-81 12-17-81 12-31-81 07-01-82 NO REASON PROVIDED.

INSPECTION REPORTS ARE AVAILABLE AT LOCAL PDR'S.

L0 CAL PUBLIC D0CUMENT R 0 0 M:

INDIAN RIVER-JUNIOR COLLEGE LIBRARY 3209 VIRGINIA AVENUE FT. PIERCE, FLORIDA 33450 i

l

C 0 N S T R U C T I 0-N

$TATUS REPQRT PAGE NO: 2-117 ST LUCIE 2 NUCLEAR POWER PLANTS STATUS AS OF:

12-31-81 C0N5TRUCTION S T A T U S:

APPLICANT'S CURRENT ESTIMATED FUEL LOADING DATE:

10-28-82 APPLICANTS CONSTRUCTION COMPLETION ESTIMATE AS APPLICANT'S PREVICUS ESTIMATED FUEL LOADING DATE:

05-00-82 DEFINED IN CP: (EARLIEST) 05-13-83 APPLICANT'S ESTIMATED FUEL LOADING DATE AT CP ISSUANCE:

05-13-83 (LATEST) 05-13-83 APPLICANT'S CURRENT ESTIMATED COMMERCIAL OPERATION DATE: 05-13-83 CURRENT ESTIMATED PERCENT CONSTRUCTION COMPLETE: 81%

COMMENTS REGARDING CURRENT CONSTRUCTION STATUS:

ESTIMATED ACTUAL ESTIMATED ACTUAL ESTIMATED START START COMPLETION COMPLETION % COMPLETE MOBILIZE AND PREPARE SITE:

05-02-77 05-02-77 07-00-77 07-00-77 100%

PLACE STRUCTURAL CONCRETE:

07-06-77 07-07-77 10-05-81 98%

INSTALL REACTOR PRESSURE VESSEL:

06-18-80 06-22-80 12-21-81 21%

INSTALL LARGE BORE PROCESS PIPE:

09-00-78 10-00-78 04-30-82 94%

INSTALL LARGE BORE PIPE HANGERS, RESTRAINTS AND SNUBBERS:

09-00-78 11-00-78 07-02-82 72%

INSTALL SMALL BORE PIPE:

10-00-78 11-00-78 06-30-82 80%

INSTALL CABLE TRAY:

10-30-78 02-00-79 05-30-82 98%

INSTALL EXPOSED METAL CONDUIT:

01-05-79 02-00-79 11-30-82 83%

INSTALL POWER, CONTROL, INSTRUMENTATION AND SECURITY CABLE:

01-30-79 05-00-79 11-30-82 61%

INSTALL ELECTRICAL TERMINATIONS:

05-00-79 08-00-79 12-30-82 38%

CONDUCT REACTOR COLD NYDR0 STATIC TEST:

03-17-82 04-28-82 0%

CONDUCT NOT FUNCTIONAL TEST:

07-03-82 08-11-82 0%

CONDUCT PREOP AND ACCEPTAhsE TESTS HECESSARY FOR FUEL LOAD:

04-20-80 03-19-80 10-27-82 29%

i

.C0N5TRUCTION STATUS REPQRT PAGE NO: 2-118

. SUMMER 1 NUCLEAR-POWER PLANTS STA1US AS OF:

12-31-81 I

PLANT

<C N A R A C T E R I S T I C S:

KEY P E R S 0 N N E L:

DOCKET'NO:

..'05000395 CORPORATE CONTACT:

E. H. CREWS, JR., VICE PRESIDENT CONST. 8 PROD. ENGINEERING CP NO. 8 DATE ISSUED: CPPR-94 / 03-21-73 CP EXPIRATION DATE:

01-01-78 CORPORATE ADDRESS:

P. O. BOX 764 APPLICANT:

SOUTH CAROLINA ELECTRIC & GAS COLUMBIA, SOUTH CAROLINA 29218 FLANT LOCATION:

.26 MI NW OF COLUMBIA, SC IE REGION:

-2 CORPORATE PHONE NO (803) 799-1234 X2268 AE:

GILBERT ASSOCIATES NSSS:

WESTINGHOUSE CONSTRUCTOR:

DANIEL INTERNATIONAL NRC LPM:

W. KANE REACTOR TYPE:

PWR IE PROJECT INSPECTOR:

DER (MWE):

0900 IE RESIDENT INSPECTOR:

J. SK0LDS IN$PECTION S T A T U S:

FUEL L0AD DATE CHANGES TIME PERIOD AS REP 0RTED BY UTILITY

  • OCT. 1981 - DEC. 1981 REPORT NEW REASON FOR CHANGE REPORT BEG DATE END DATE DATE SCHEDULE REPORTED BY UTILITY HUMBER OF INSP.

OF INSP.

11-12-74 11-01-78 POWER NEEDS DEFERRED; FINANCIAL 8129 10-01-81 10-31-81 DETERMENTS.

8130 11-02-81 11-06-81 01-07-77 11-30-79 NO REASON GIVEN.

8131 11-01-81 11-30-81 11-07-78 07-01-80 NO REASON GIVEN.

8132 12-01-81 12-23-81 01-31-80 12-01-80 HD REASON GIVEN.

8133 12-07-81 12-11-81 01-31-80 12-01-80 NO REASON GIVEN.

8134 12-14-81 12-18-81 05-05-80 01-03-80 NO REASON GIVEN.

8135 12-28-81 12-31-81 08-00-80 06-00-81 NO REASON GIVEN.

01-16-81 08-00-81 NO REASON PROVIDED.

l l

INSPECTION REPORTS ARE AVAILABLE AT LOCAL PDR'S.

11-25-81 02-00-82 NO REASON PROVIDED.

l l

L'O C A L PUBLIC' D0CUMENT R 0 0 M:

RICHLAND COUNTY PUBLIC LIBRARY 1400 SUMTER STREET-COLUMBIA, SOUTH CAROLINA 29201

_4

~_

C0NSTRUCTION STATUS REPORT PAGE NO: 2-119 SUMMER 1 NUCLEAR POWER PLANTS STATUS AS OF:

12-31-81 C0NSTRUCTION S T A T U S:

APPLICANT'S CURRENT ESTIMATED FUEL LOADING DATEL 02-00-82 APPLICANTS CONSTRUCTION COMPLETION ESTIMATE AS APPLICANT'S PREVIOUS ESTIMATED FUEL LOADING DATE:

03-00-81 DEFINED IN CP: (EARLIEST)

APPLICANT'S ESTIMATED FUEL LOADING DATE AT CP ISSUANCE:

10-01-77 (LATEST)

' APPLICANT'S CURRENT ESTIMATED COMMERCIAL OPERATION DATER 08-31-82 CURRENT ESTIMATED PERCENT CONSTRUCTION COMPLETE: 98%

COMMENTS REGARDING C'XPENT CONSTRUCTION STATUS:

5 ESTIMATED ACTUAL ESTIMATED ACTUAL ESTIMATED START START COMPLETION COMPLETION % COMPLETE MOBILIZE AND PREPARE SITE:

04-00-73 02-00-74 100%

PLACE STRUCTURAL CONCRETE:

03-00-74 02-00-82 99.8%

INSTALL REACTOR PRESSURE VESSEL:

09-00-77 11-00-77 100%

INSTALL LARGE BORE PROCESS PIPE:

01-00-77 02-00-82 99.8%

INSTALL LARGE BORE PIPE NANCERS RESTRAINTS AND SHUBBERS:

03-00-77 02-00-82 94%

INSTALL SMALL BORE PIPE:

01-00-77 02-00-82 99.8%

INSTALL CABLE TRAY:

02-00-77 02-00-82 9'9.5%

INSTALL EXPOSED METAL CONDUIT:

01-00-76 02-00-82 97.5%

INSTALL POWER, CONTROL,. INSTRUMENTATION AND SECURITY CABLE::

09-00-77 02-00-82 97.8%

HSTALL ELECTRICAL TERMINATIDNS:

11-00-77 02-00-82 94.9%

CONDUCT REACTOR COLD HYDROSTATIC TEST:

11-01-79 11-09-79 100%

CONDUCT HOT FUNCTIONAL TEST:

08-00-80 09-00-80 100%

CONDUCT PREOP AND ACCEPTANCE TESTS NECESSARY FOR FUEL LOAD:

06-00-78 02-00-82 76%

i s

i

+

C0NSTRUCTION STATUS REPQRT PAGE NO: 2-120 9USQUEHANNA 1 NUCLEAR POWER PLANTS STATUS AS OF:

12-31-81 P.L A N T CHARACTERI5TICSt KEY P E R S 0 N N E L:

DOCKET ND:

05000387 CORPORATE CONTACT:

N. W. CURTIS. VICE PRESIDENT CP NO.'8 DATE ISSUED: CPPR-101/ 11-02-73 ENGINEERING & CONSTRUCTION CP EXPIRATION DATE:

03-01-21 CORPORATE ADDRESS:

901 HANILTON STREET APPLICANT:

PENNSYLVANIA POWER & LIGHT ALLENTCWN, PENNSYLVANIA 18101

  • PLANT LOCATION:

7 MI NE OF BERWICK, PA IE REGION:

1 CORPORATE PHONE NO:

(215) 770-5381 AE:

BECHTEL NSSS:

GENERAL ELECTRIC CONSTRUCTOR:

BECHTEL NRC LPM:

R. PERCH REACTOR TYPE:

BWR IE PROJECT INSPECTOR:

DER (MWE):

1052 IE RESICENT INSPECTOR:

G. G. RHOADS INSPECTION 5TATUSt FUEL L0AD DATE C H A N G E S-TIME PERIOD AS REP 0RTED BY UTILITY OCT. 1981 - DEC. 1981 REPORT HEW REASON FOR CHANGE REPORT BEG DATE END DATE DATE SCHEDULE REPORTED BY UTILITY HUMBER OF INSP.

OF INSP.

09-10-74 05-01-80 REVISED LOAD FORECASTS FOR THE 1980'S.

81-20 11-16-81 11-20-81 12-31-79 04-09-81 NO REASON PROVIDED.

81-21 10-13-81 10-15-81 10-30-80 06-01-81 NO REASON PROVIDED.

81-22 10-13-81 10-15-81 09-50-81 04-15-82 NO REASON PROVIDED.

81-23 10-27-81 OPEN INV 12-31-81 07-01-82 NO REASON PROVIDED.

81-24 10-19-81 10-23-81 81-25 10-20-81 11-18-81 81-26 12-01-81 12-11-81 81-27 11-19-81 12-20-81 81-28 12-09-81 12-11-81 t

Inspection Reports are available at local PDRs.

L0 CAL PUBLIC D0CUMENT R 0 0 M:

OSTERHOUT FREE LIBRARY 71 SOUTH FRANKLIN STREET WILKES-BARRE, PENNSYLVANIA 18701 l

t

~

.~.. -. _ _ - _...~

C0N5TRUCTION STATUS REPQRT PAGE NO: 2-121 SUSQUEHANNA 1 NUCLEAR POWER PLANTS STATUS AS OF:

12-31-81 C0NSTRUCTION 5 T A T U 5:

APPLICANT'S CURRENT ESTIMATED FUEL LOADING DATE:

07-01-82 APPLICANTS CONSTRUCTION COMPLETION ESTIMATE AS APPLICANT'S PREVIOUS ESTIMATED FUFL LOADING DATE:

04-15-82 DEFINED IN CP: (EARLIEST) 05-01-79 APPLICANT'S ESTIMATED FUEL LOADING DATE AT CP ISSUANCE:

05-01-79 (LATEST) 12-31-82 APPLICANT'S CURRENT ESTIMATED COMMERCIAL OPERATION DATE: 05-15-83 CURRENT ESTIMATED PERCENT CONSTRUCTION COMPLETE: 92%

COMMENTS REGARDING CURRENT CONSTRUCTION STATUS:

i ESTIMATED ACTUAL ESTIMATED ACTUAL ESTIMATED START START COMPLETION COMPLETION % C0rPLETE

[

MOBILIZE AND PREPARE SITE:

11-00-73 03-00-74 100%

i PLACE STRUCTURAL CONCRETE:

09-00-74 03-00-78 100%

INSTALL REACTOR PRESSURE VESSEL:

02-00-76 10-00-76 100%

INSTALL LARGE BORE PROCESS PIPE:

08-00-74 03-00-82 99%

INSTALL LARGE BORE PIPE MANGERS RESTRAINTS AND SNUBBERS:

08-00-75 05-00-82 96%

INSTALL SMALL BORE PIPE:

08-00-75 03-00-82 99%

l INSTALL CABLE TRAY:

09-00-75 03-00-82 99%

1 INSTALL EXPOSED METAL CONDUIT:

04-00-76 03-00-82 99%

[

INSTALL POWER, CONTROL, INSTRUMENTATION AND SECURITY CABLE:

01-00-78 03-00-82 99%

INSTALL ELECTRICAL TERMINATIONS:

01-00-78 04-00-82 96%

CONDUCT REACTOR COLD NYDR0 STATIC TEST 12-00-78 10-00-80 100%

CONDUCT NOT FUNCTIONAL TEST:

N/A N/A N/A N/A N/A CONDUCT PREOP AND. ACCEPTANCE TESTS NECESSARY FOR FUEL LOAD 12-00-79 06-00 59%

P

C0N5TRUCTION STATUS REPQRT PAGE NO: 2-122 SUSQUEHANNA 2 NUCLEAR POWER PLANTS STATUS AS OF:

12-31-81 PLANT C H A R A C T E R I S T I C S' KEY P E R S 0 N N E L:

DOCKET NO:

05000388 CORPORATE CONTACT:

N. W. CURTIS. VICE PRESIDENT CP NO. 8 DATE ISSUED: CPPR-102/ 11-02-73 ENGINEERING 8 CONSTRUCTION CP EXPIRATICN DATE:

09-01-82 CORPORATE ADDRESS:

2 NORTH NINETH STREET APPLICANT:

PENNSYLVANIA POWER 8 LIGHT ALLENTOWN, PENNSYLVANIA 18101 PLANT LOCATION:

7 MI NE OF BERWICK, PA IE REGION:

1 CORPORATE PHONE NO:

(215) 770-5381 AE:

BECHTEL NSSS:

GENERAL ELECTRIC CONSTRUCTOR:

BECHTEL NRC LPM:

R. PERCH REACTOR TYPE:

BWR IE PROJECT INSPECTOR:

DER (MWE):

1052 IE RESIDENT INSPECTGR:

G. G. RH0 ADS INSPECTION S T A T U S:

FUEL L0AD DATE CHANGES TIME PERIOD AS REPORTED BY UTILITY:

OCT. 1981 - DEC. 1981 REPORT NEW REASON FOR CHANGE REPORT BEG DATE END DATE DATE SCHEDULE REPORTED BY UTILITY hyMBER OF INSP.

OF INSP.

09-10-74 11-01-81 REVISED LOAD FORECASTS FOR THE 1980'S.

81-10 11-16-81 11-20-81 02-00-80 04-00-82 NO REASON PROVIDED.

81-11 10-27-81 OPEN INV 10-30-80 11-00-82 NO REASON PROVIDED.

81-12 10-19-81 10-23-81 09-30-81 07-00-83 NO REASON PROVIDED.

81-13 12-01-81 12-11-81 12-31-81 01-01-84 NO REASON PROVIDED.

Inspection Reports are available at local PORs.

L0 CAL PUBL IC D0CUMENT R 0 0 M:

OSTERHOUT FREE LIBRARY 71 SOUTH FRANKLIN STREET WILKES-BARRE, PENNSYLVANIA 18701

________.m t

C0NSTRUCTION STATUS REP 0RT PAGE NO: 2-123 SUSQUENANNA 2 NUCLEAR POWER PLANTS STATUS,AS OF:

12-31-81 C0NSTRUCTION S T A T U 5:

APPLICANT'S CURRENT ESTIMATED FUEL LOADING DATE:

01-00-84 APPLICANTS CONSTRUCTION COMPLETION ESTIMATE AS APPLICANT'S PREVIOUS ESTIMATED FUEL LOADING DATE:

07-15-83 DEFINED IN CP: (EARLIEST) 11-01-80 APPLICANT'S ESTIMATED FUEL LOADING DATE AT CP ISSUANCE:

11-01-80 (LATEST) 03-31-84 APPLICANT'S CURRENT ESTIMATED COMMERCIAL DPERATION DATE: 11-00-84 CURRENT ESTIMATED PERCENT CONSTRUCTION COMPLETE: 65%

I' COMMENTS REGARDING CURRENT CONSTRUCTION STATUS:

ESTIMATED ACTUAL ESTIMATED ACTUAL ESTIMATED j

START START COMPLETION COMPLETION % COMPLETE MOBILIZE AND PREPARE SITE:

11-00-73 07-00-74 100%

PLACE STRUCTURAL CONCRETE:

10-00-74 09-00-78 100%

I INSTALL REACTOR PRESSURE VESSEL:

12-00-76 07-00-77 100%

INSTALL LARGE BORE PROCESS PIPE:

04-00-82 04-00-82 99%

j INSTALL LARGE BORE PIPE HANGERS, RESTRAINTS AND SHUBBERS:

08-00-77 03-00-83 70%

INSTALL SMALL BORE PIPE:

09-00-75 10-00-82 86%

INSTALL CABLE TRAY:

04-00-77 03-00-82 99%

INSTALL EXPOSED METAL CONDUIT:

07-00-75 04-00-82 96%

INSTALL POWER, CONTROL, INSTRUMENTATION AND SECURITY CABLE:

04-00-79 12-00-82 93%

INSTALL ELECTRICAL TERMINATIONS:

10-00-79 01-00-83 66%

CONDUCT REACTOR COLD HYDROSTATIC TEST:

06-00-80 11-00-82 C%

i CONDUCT HOT FUNCTIONAL TEST:

N/A N/A N/A N/A N/A CONDUCT PREOP AND ACCEPTANCE TESTS NECESSARY FOR FUEL LOAD:

06-00-83 0%

4

C0N5TRUCTION STATUS REPQRT PAGE NO: 2-124

-V0GTLE 1 NUCLEAR POWER PLANTS STATUS AS OF:

12-31-81 t

PLANT C H A R A C T E R I S T I C S:

KEY P E R S 0 N N E L:

l' DOCKET NO:

05000424 CORPORATE CONTACT:

D.

E. DUTTON,'VICE PRESIDENT-CP NO. 8 DATE ISSUED: CPPR-108/ 06-28-74 GENERATING PLANT PROJECTS CP EXPIRATION DATE:

04-30-81 CORPORATE ADDRESS:

GEORGIA POWER COMPANY APPLICANT:

GEORGIA POWER 333 PIEDMONT PLANT LOCATION:

25 MI SSE OF AUGUSTA, GA ATLANTA, GEORGIA 30302 IE REGION:

2 CORPORATE PHONE NO:

(404) 522-6060 AE:

SOUTHERN SERVICES & BECHTEL NSSS:

WESTINGHOUSE CONSTRUCTOR:

GEORGIA POWER CO.

NRC LPM:

J. GRANT REACTOR TYPE:

PWR IE PROJECT INSPECTOR:

DER (MWE):

1100 IE RESIDENT INSPECTOR:

W. F. SANDERS INSPECTION STATUS:

FUEL L0AD DATE CHANGES TIME PERIOD AS REP 0RTED BY U T I L I T Y:

OCT, 1981 - DEC. 1981 REPORT NEW REASON FOR CHANGE i

REPORT BEG DATE END DATE DATE SCHEDULE REPORTED BY UTILITY NUMBER OF INSP.

OF INSP.

09-27-74 NOT KNOWN CONSTRUCTION SUSPENDED FOR FINANCIAL I

8110 10-05-81 10-07-81 REASONS.

8111 11-03-81 11-06-81 05-11-77 05-00-83 NO REASON GIVEN.

8112 11-17-81 11-19-81 01-09-78 05-01-84 OVERESTIMATED PROJECTED NEED FOR POWER.

i 8113 11-05-81 12-11-81 07-17-80 11-00-84 NO REASON PROVIDED.

8114 12-14-81 12-17-81 11-18-81 09-01-86 SCHEDULE REASSESSMENT.

i INSPECTION REPORTS ARE AVAILABLE AT LOCAL PDR'S.

l L0 CAL PUBLIC D0CUMENT R 0 0 M:

BURKE COUNTY LIBRARY 4TH STREET WAYNESBORD, GEORGIA 30830 i

i

.~

C0NSTRUCTION STATUS REPORT PAGE N3 2-125 V0GTLE 1 NUCLEAR POWER PLANTS STATUS AS OF:

12-31-81 C0NSTRUCTION S T A T U S:

APPLICANT'S CURRENT ESTIMATED FUEL LOADING DATE:

09-01-86 APPLICANTS CONSTRUCTION COMPLETION ESTIMATE AS APPLICANT'S PREVIOUS ESTIMATED FUEL LOADING DATE:

11-00-84 DEFINED IN CP: (EARLIEST) 04-01-80 APPLICANT'S ESTIMATED FUEL LOADING DATE AT CP ISSUANCE:

10-01-79 (LATEST)

APPLICANT'S CURRENT ESTIMATED COMMERCIAL OPERATION DATE: 03-01-87 CURRENT ESTIMATED PERCENT CONSTRUCTION COMPLETE: 24%

COMMENTS REGARDING CURRENT CONSTRUCTION STATUS: CURRENT ESTIMATED PERCENT COMPLETE CALCULATED FROM THE PHASE III BUDGET.

4 THE QUARTERLY REPORT PERCENT COMPLETE CHANGED SIGNIFICANTLY FROM THE PNASE II BUDGET.

ESTIMATED ACTUAL ESTIMATED ACTUAL ESTIMATED START START COMPLETION COMPLETION % COMPLETE MOBILIZE AND PREPARE SITE:

08-01-76 09-15-77 100%

PLACE STRUCTURAL CONCRETE:

08-01-78 02-15-84 51%

INSTALL REACTOR PRESSURE VESSEL:

02-01-83 03-15-83 0%

^

INSTALL LARGE BORE PROCESS PIPE:

09-01-80 05-01-86 5%

INSTALL LARGE BORE PIPE HANGERS, RESTRAINTS AND SHUBBERS:

09-01-80 05-01-86 0%

INSTALL SMALL BORE PIPE:

07-01-81 05-01-86 0%

INSTALL CABLE TRAY:

08-01-80 04-01-85 7%

INSTALL EXPOSED METAL CONDUIT:

11-01-81 01-01-86 0%

INSTALL POWER, CONTROL, INSTRUMENTATION AND SECURITY CABLE:

03-01-83 11-01-85 0%

INSTALL ELECTRICAL TERMINATIONS:

05-01-83 01-01-86 0%

CONDUCT REACTOR COLD NYDR0 STATIC TEST 03-01-86 04-01-86 0%

CONDUCT HOT FUNCTIONAL TEST:

05-i5-86 07-15-86 0%

CONDUCT PREOP AND ACCEPTANCE TESTS NECESSARY FOR FUEL LOAD:

07-24-84 08-01-86 0%

i w

C0NSTRUCTION STATUS REP 0RT PAGE NO: 2-126 V0GTLE 2 NUCLEAR P0WER PLANTS STATUS AS OF:

12-31-81 PLANT C H A R A C T E R I S T I C S:

KEY PERS0NNEL:

DOCKET NO:

05000425 CORPORATE CONTACT:

D. E. DUTTON, VICE PRESENT CP NO. & DATE ISSUED: CPPR-109/ 06-28-74 GENERATING PLANT PROJECTS CP EXPIRATION DATE:

04-30-82 CORPORATE ADDRESS:

GEORGIA POWER COMPANY APPLICANT:

GEORGIA POWER 333 PIEDMONT PLANT LOCATION:

25 MI SSE OF AUGUSTA, GA ATLANTA, GEORGIA 30302 IE REGION:

2 CORPORATE PHONE NO:

(404) 522-6060

. E:

SOUTHERN SERVICES & BECHTEL A

NSSS:

WESTINGHOUSE CONSTRUCTOR:

GEORGIA POWER CO.

NRC LPM:

J. GRANT REACTOR TYPE:

PWR IE PROJECT INSPECTOR:

DER (MWE):

1100 IE RESIDENT INSPECTOR:

W. F. SANDERS INSPECTION STATUSt FUEL L0AD DATE CHANGES TIME PERIOD AS REPORTED BY U T I L I T Y:

OCT. 1981 - DEC. 1981 REPORT HEW REASON FOR CHANGE REPORT BEG DATE END DATE DATE

$f31RMLE REPORTED BY UTILITY NUMBER OF INSP.

OF INSP.

09-27-74 N'lT KNOWN CONSTRUCTION SUSPENDED FOR FINANCIAL 8110 10-05-81 10-07-81 REASONS.

8111 11-03-81 11-06-81 05-11-77 d5-00-84 NO REASON GIVEN.

8112 11-17-81 11-19-81 11-02-77 05-00-85 OVERESTIMATED PROJECTED NEED FOR POWER.

8113 11-05-81 12-11-81 07-17-80 05-00-87 NO REASON PROVIDED.

8114 12-14-81 12-17-81 11-18-81 03-01-88 SCHEDULE REASSESSMENT.

INSPECTION REPORTS ARE AVAILABLE AT LOCAL PDR'S.

f L0 CAL PUBLIC D0CUMENT R00M BURKE COUNTY LIBRARY 4TH STREET WAYNESBORO, GEORGIA 30830

_... ~ -.

t t

C0N5TRUCTION STATUS REPQRT PAGE NO: 2-127 UCGTLE 2 NUCLEAR POWER PLANTS STATUS AS OF:

12-31-81 C0HSTRUCTION STATUSt APPLICANT'S CURRENT ESTIMATED FUEL LOADING DATE:

03-01-88 APPLICANTS CONSTRUCTION COMPLETION ESTIMATE AS APPLICANT'S PREVIOUS ESTIMATED FUEL LOADING DATE:

05-00-87 DEFINED IN CP: (EARLIEST) 04-01-81 APPLICANT'S ESTIMATED FUEL LOADING DATE AT CP ISSUANCE:

10-01-80 (LATEST)

APPLICANT'S CURRENT ESTIMATED COMMERCIAL OPERATION DATE: 09-01-88 CURRENT ESTIMATED PERCENT CCHSTRUCTION COMPLETE:

8%

COMMENTS REGARDING CURRENT CONSTRUCTION STATUS: CURRENT ESTIMATED PERCENT COMPLETE CALCULATED FROM THE PHASE III BUDGET.

THIS QUARTERLY REPORT PERCENT COMPLETE CHANGED SIGNIFICANTLY FOR CERTAIN ITEMS DUE TO THE PREVIOUS PERCENT COMPLETE BEING CALCULATED FROM THE PHASE II BUDGET.

1 ESTIMATED ACTUAL ESTIMATED ACTUAL ESTIMATED START START COMPLETION COMPLETION % COMPLETE MOSILIZE AND PREPARE SITE:

08-01-76 09-15-77 100%

PLACE STRUCTURAL CONCRETE:

08-01-78 08-15-84 30%

INSTALL REACTOR PRESSURE VESSEL:

08-01-84 09-15-84 0%

INSTALL LARGE BORE PRCCESS PIPE:

09-01-80 11-01-87 3%

INSTALL LARGE BORE PIPE HANGERS RESTRAINTS AND SNUBBERS:

09-01-80 11-01-87 0%

INSTALL SMALL BORE PIPE:

02-01-83 04-01-88 0%

INSTALL CABLE TRAY:

08-01-80 10-01-86 4%

INSTALL EXPOSED METAL CONDUIT:

03-01-83 07-01-87 0%

INSTALL POWER, CONTROL, INSTRUMENTATION AND SECURITY CABLE:

09-01-84 05-01-87 0%

INSTALL CLECTRICAL TERMINATIONS:

11-01-84 07-01-87 0%

CONDUCT REACTOR COLD HYDROSTATIC TEST:

09-01-87 10-01-87 0%

CONDUCT NOT FUNCTIONAL TEST:

12-15-87 02-15-88 0%

CONDUCT PREOP AND ACCEPTANCE TESTS NECESSARY FOR FUEL LOAD:

01-24-86 02-01-88 0%

i

~

l l

l' l

C0NSTRUCTION STATUS REPORT PAGE NO 2-128 WASHINGTON NUCLEAR 1 NUCLEAR POWER PLANTS STATUS AS OF:

12-31-81 i

PLANT C H A R A C T E R I S T I C S:

KEY PERS0NNELa l

DOCKET NO:

05000460 CORPORATE CONTACT:

R. L. FERGUSON, MANAGING DIRECTOR CP NO. 3 DATE ISSUED: CPPR-134/ 12-24-75 CP EXPIRATION DATE:

01-01-82 CORPORATE ADDRESS:

P. O. BOX 968 l

APPLICANT:

WASHINGTON PUBLIC POWER SUPPLY SYSTEM RICHLAND, WASHINGTON 99352 PLANT LOCATION:

30 MI NW OF RICHLAND, WASH IE REGION:

5 CORPORATE PHONE NO:

(509) 372-5000 AE:

UNITED ENG. 8 CONSTRUCTORS HSSS:

BABCOCK & WILCOX CONSTRUCTOR:

BECHTEL NRC LPM:

R. HERNAN REACTOR TYPE:

PWR IE PROJECT INSPECTOR:

P. P. NARBUT DER (MWE):

1267 IE RESIDENT INSPECTOR:

A. TOTH INSPECTION S T A T U S:

FUEL L0AD DATE CHANGES TIME PERIOD AS REP 0RTED BY UTILITY OCT. 1981 - DEC. 1981 REPORT NEW REASON FOR CHANGE REPORT-BEG DATE END DATE DATE SCHEDULE REPORTED BY UTILITY NUMBER OF INSP.

OF INSP.

04-15-76 08-00-80 REASON FOR CHANGE NOT REPORTED BY THE 81-09 10-01-81 10-23-81 UTILITY.

81-10 11-16-81 11-20-81 09-00-76 03-00-81 DELAY IN COMPLETION OF ENGINEERING AND l

81-11 12-01-81 12-30-81 LABOR DIFFICULTIES.

81-12 12-14-81 12-18-81 01-00-78 06-00-82 1 LABOR PRODUCTIVITY BELOW PLANNED LEVELS

2. INCREASE IN PLANNED DURATIONS FOR Inspection Reports are available at local PDRs.

PIPING AND ELECTRICAL ACTIVITIES.

3. EXTENDED DURATIDH FOR PREOPERATIONAL TESTING TO COMMERCIAL OPERATION.

03-07-79 06-00-83 SCHEDULE REEVALUATION / LABOR PRODUCTIVITY BELOW PLANNED LEVELS.

I 06-00-80 01-00-84 NO REASON PROVIDED.

l 12-17-81 08-01-35 NO REASON PROVIDED.

12-00-81 12-00-85 REEVALUATION OF WORK REMAINING TO COMPLETE PROJECT. TARGET COMPLETION DATE 13 8/85.

l l

l L0 CAL PUBLIC D0CUMENT R 0 0 M:

RICHLAND PUBLIC LIBRARY SWIFT AND NORTHGATE STREETS l

RICHLAND, WASHINGTON 99552

C0N5TRUCTION 5TATUS REPORT PAGE NO: 2-129 WASHINGTON NUCLEAR 1 NUCLEAR -POWER PLANTS STATUS AS OF:

12-31-81 C0N5TRUCTION 5 T A T U S:

APPLICANT'S CURRENT ESTIMATED FUEL LOADING DATE:

12-00-85 APPLICANTS CONSTRUCTION COMPLETION ESTIMATE AS APPLICANT'S PREVIOUS ESTIMATED FUEL LOADING DATE:

08-01-85 DEFINED IN CP: (EARLIEST) 01-01-80 APPLICANT'S ESTIMATED FUEL LOADING DATE AT CP ISSUANCE:

03-00-80 (LATEST) 01-01-82n APPLICANT'S CURRENT ESTIMATED COMMERCIAL OPERATION DATE: 06-00-86 i

CURRENT ESTIMATED PERCENT CONSTRUCTION COMPLETE: 53%

COMMENTS REGARDING CURRENT CONSTRUCTION STATUS: NCP EXTENSION PENDING - NEW ESTIMATES FOR L ATEST COMPLETION - JUNE 1, 1986 ESTIMATED ACTUAL ESTIMATED ACTUAL ESTIMATED l

START START COMPLETION COMPLETION % COMPLETE MOBILIZE AND PREPARE SITE:

08-01-75 08-08-75 100%

PLACE STRUCTURAL CONCRETE:

04-00-76 10-00-82 91%

INSTALL REACTOR PRESSURE VESSEL:

08-31-79 08-31-79 100%

INSTALL LARGE BORE PROCESS PIPE:

08-01-79 03-00-84 73%

INSTALL LARGE BORE PIPE NANGERS, RESTRAINTS AND SNUBBEP.S:

08-15-79 06-00-84 52%

INSTALL SMALL BORE PIPE:

04-01-81 09-00-84 15%

INSTALL CABLE TRAY:

01-01-79 08-00-83 72%

INSTALL EXPOSED METAL CONDUIT:

04-01-81 09-00-84 22%

INSTALL POWER, CONTROL, INSTRUMENTATION AND SECURITY CABLE:

08-07-81 12-00-84 10%

INSTALL ELECTRICAL TERMINATIONS:

10-06-81 04-00-85 1%

CONDUCT REACTOR COLD NYDR0 STATIC TEST:

06-00-85 06-00-85 0%

CONDUCT NOT FUNCTIONAL TEST:

08-00-85 08-00-85 0%

CONDUCT PREOP AND ACCEPTANCE TESTS NECESSARY FOR FUEL LOAD:

05-00-84 08-00-85 0%

l l

l

a PAGE HO: 2-130 C0NSTRUCTION STATUS REPQRT STATUS AS OF:

12-31-81 NUCLEAR POWER PLAHTS WASHINGTON NUCLEAR 2 KEY P E R S 0 N N E L:

PLANT C H A R A C T E R I S T I C S:

CORPORATE CONTACT:

R. L. FERGUSON, MANAGING DIRECTOR DOCKET NO:

0S000397 CP NO. 1 DATE ISSUED: CPPR-93 / 03-19-73 CORPORATE ADDRESS:

P. O. BOX 968 CP EXPIRATION DATES 12-01-81 RICHLAND, WASHINGTON 99352 APPLICANT:

WASHINGTON PUBLIC POWER SUPPLY SYSTEM PLANT LOCATIDH:

30 MI NW OF RICHLAND, WASH CORPORATE PHONE HO:

(509) 372-5000 IE REGION:

5 AE BURHS & ROE IE PRINCIPAL INSPECTOR:

HSSS:

GENERAL ELECTRIC NRC LPM:

R.

ALUCK CONSTRUCTOR:

BECHTEL IE PROJECT INSPECTOR:

REACTOR TYPE:

BWR IE RESIDENT INSPECTrR:

R. FEIL DER (MWE):

1103 FUEL L0AD DATE CHANGES INSPECTION S T A T U S:

AS REPQRTED BY U T I L I T Y:

TIME PERIOD OCT. 1981 - DEC. 1981 REPORT NEW REASON FOR CHANGE REPORT BEG DATE END DATE DATE SCHEDULE REPORTED BY UTILITY HUMBER OF INSP.

OF INSP.

08-15-74 07-00-77 HO REASON NOTED.

81-21 10-01-81 10-31-81 01-10-75 12-00-77 INSUFFICIENT MANPOWER BY MAJOR CONSTRUCTOR.

81-22 11-02-81 11-05-81 81-23 11-06-81 11-06-81 08-00-75 04-00-78 PERSISTING CIRTICAL PROBLEMS.

81-24 11-01-81 11-30-81 02-00-76 01-00-79 CONTINUED SLIPPAGE BY MAJOR CIVIL AND MECHANICAL CONTRACTORS.

81-25 12-01-81 12-30-81 07-31-76 06-15-79 CIVIL CONTRACT DEFAULT AND EXTENDED LABOR DISPUTE.

Inspection Reports are available at local PDRs.

10-12-76 12-00-79 CONTINUED SLIPPAGE BY MAJOR CIVIL AND MECHANICAL CONTRACTOR AHD CONTINUING PIPE FITTER STRIKE.

01-17-77 03-00-80 PIPE FITTER STRIKE.

04-27-79 03-00-81 SCHEDULE REEVALUATION 06-00-80 08-00-82 HD REASON PROVIDED.

11-20-81 03-30-83 QUALITY PROBLEMS, LABOR DISPUTE, SCHEDULE RE-EVALUATIDH.

L0 CAL PUBLIC D0CUMENT R 0 0 M:

RICHLAND PUBLIC LIBRARY SWIFT AND HORTHGATE STREETS RICHLAND, WASHINGTON 99352 l

C0NSTRUCTION STATUS REPQRT PAGE NO: 2-131 WASHINGTON NUCLEAR 2 NUCLEAR POWER PLANTS STATUS AS OF:

12-31-81 C0NSTRUCTION S T A T U S:

APPLICANT'S CURRENT ESTIMATED FUEL LOADING DATE:

03-30-83MM APPLICANTS CONSTRUCTION COMPLETION ESTIMATE AS APPLICANT'S PREVIOUS ESTIMATED FUEL LOADING DATE:

08-00-82 DEFINED IN CP: (EARLIEST) 12-00-82 APPLICANT'S ESTIMATED FUEL LOADING DATE AT CP ISSUANCE:

04-00-77 (LATEST) 02-00-84u APPLICANT'S CURRENT ESTIMA.TED COMMERCIAL OPERATION DATE: 09-30-83 l

CURRENT ESTIMATED PERCENT CONSTRUCTION COMPLETE: 88%

l COMMENTS REGARDING CURRENT CONSTRUCTION STATUS: wCP EXTENSION REQUEST PENDING.

l MuGFFICIAL PUBLISHED SCHEDULE DATE IS SEPTEMBER 1983.

MARCH 1983 REPRESENTS THE PROJECT TARGET FUEL LOAD DATE.

ALL ESTIMATED START AND COMPLETION DATES ARE BASED ON THE MARCH 1983 PROJECT TARGET DATE.

ESTIMATED ACTUAL ESTIMATED ACTUAL ESTIMATED START START

[.0MPLETION COMPLETION % CCMPLETE MOBILIZE AND PREPARE SITE:

08-00-72 0%

PLACE STRUCTURAL CONCRETE:

05-00-73 03-00-78 99%

INSTALL REACTOR PRESSURE VESSEL:

03-00-77 100%

INSTALL LARGE BORE PROCESS PIPE:

07-00-75 09-00-82 97%

INSTALL LARGE BORE PIPE HANGERS, RESTRAINTS AND SNUBBERS:

07-00-75 12-00-82 89%

INSTALL SMALL BORE PIPE:

07-00-75 11-00-82 84%

INSTALL CABLE TRAY:

02-00-75 100%

INSTALL EXPOSED METAL CONDUIT:

02-00-75 12-00-82 78%

INSTALL POWER, CONTROL, INSTRUMENTATION AND SECURITY CABLE:

02-00-75 01-00-83 80%

INSTALL ELECTRICAL TERMINATIONS:

02-00-75 01-00-83 72%

CONDUCT REACTOR COLD HYLROSTATIC TEST:

08-00-82 0%

CONDUCT HOT FUNCTIONAL TEST:

N/A N/A N/A N/A N/A CONDUCT PREOP AND ACCEPTANCE TESTS NECESLARY FOR FUEL LOAD:

09-00-82 03-00-83*W 0%

C0NSTRUCTION STATUS REP 0RT PAGE NO: 2-132 WASHINGTON NUCLEAR 3 NUCLEAR POWER PLANTS STATUS AS OF:

12-31-81 PLANT CHAR 4 C T E R I S T I C S:

KEY P E R S 0 N N E L:

CORPORATE CONTACT:

R. L. FERGUSON, MANAGING DIRECTOR DOCKET NO:

05000508 CP NO. 8 DATE ISSUED: CPPR-154/ 04-11-78 CORPORATE ADDRESS:

P. O. BOX 968 l

CP EXPIRATION DATE:

01-01-83 RICHLAND, WASHINGTON 99352 APPLICANT:

WASHINGTON PUBLIC POWER SUPPLY SYSTEM PLANT LOCATION:

26 MI W OF OLYMPIA, WA COPPORATE PHONE NO:

(509) 372-5000 IE REGION:

5 AE:

EBASCO HSSS:

COMBUSTION ENGINEERING NRC LPM:

L. WHEELER CONSTRUCTOR:

EBASCO IE PROJECT INSPECTOR:

REACTOR TYPE:

PWR IE RESIDENT INSPECTOR:

W. G. ALBERT DER (MWE):

1242 FUEL L0AD DATE CHANGES INSPECTION 5 T A T U S:

TIME PERIOD AS REP 0RTED BY U T I L I T Y:

OCT. 1981 - DEC. 1981 REPORT NEW REASON FOR CHANGE REPORT BEG DATE END DATE DATE SCHEDULE REPORTED BY UTILITY NUMBER OF INSP.

OF INSP_.

05-22-79 06-00-84 SCHEDULE REEVALUATION.

81-17 10-05-81 10-30-81 06-00-80 12-00-85 REASON FOR 18 MONTH SLIP WAS:

6 MONTHS - DUE TO LATE PIPING START 81-18 10-14-81 10-30-81 12 MONTHS - DUE TO REVISED QUANTITY 81-19 11-01-81 11-30-81 AND PRODUCTIVITY ESTIMATES.

81-20 12-07-81 12-11-81 81-21 12-01-81 12-30-81 11-00-81 08-00-85 FOUR MONTHS SCHEDULE RECOVERY BASED ON REASSESSMENT OF PROJECT Inspection Reports are available at local PDRs.

CAPABILITY AND CONTRACT INCENTIVES FOR PRIME CONTRACTORS.

L0 CAL PUBLIC D0CUMENT R 0 0 M:

W. H. ABEL MEMORIAL LIBRARY 125 MAIN STREET, SOUTH MONTESAND, WASHINGTON 98563

C0NSTRUCTION STATU$

REPQRT PAGE NO: 2-133 WASHINGTON NUCLEAR 3 NUCLEAR POWER PLANTS STATUS AS OF:

12-31-81 C0NSTRUCTION STA T U S:

APPLICANT'S CURRENT ESTIMATED FUEL LO7.HG DATE:

08-00-85M APPLICANTS CONSTRUCTION COMPLETION ESTIMATE AS APPLICANT'S PREVIOUS ESTIMATED FUEL 1.4 DING DATE:

12-00-85 DEFINED IN CP: (EARLIEST) 01-01-83 APPLICANT'S ESTIMATED FUEL LOADING T, ATE AT CP ISSUANCE:

07-00-83 (LATEST) 01-01-85 APPLICANT'S CURRENT ESTIMATED COMMrdCIAL OPERATION DATE: 02-00-86 CURRENT ESTIMATED PERCENT CONSTiUCTION COMPLETE: 43%

COMMENTS REGARDING CURRENT CONSTRUCTION STATUS: 50FFICIAL PUBLISHED SCHEDULE IS JUNE 1986.

AUGUST 1985 REPRESENTS PROJECT TARGET FUEL LOAD DATE.

ALL ESTIMATED START AND COMPLETION DATES ARE BASED ON THE AUGUST 1985 PROJECT TARGET DATE.

ESTIMATED ACTUAL ESTIMATED ACTUAL ESTIMATED START 11 ART C0hPLETION COMPLETION % COMPLETE MOBILIZE AND PREPARE SITE:

04-00-77 04-00-77 04-00-78 100%

PLACE STRUCTURAL CONCRETE:

09-00-78 09-00-78 01-00-84 79%

INSTALL REACTOR PRESSURE VESSEL:

08-00-81 08-00-81 08-00-81 100%

INSTALL LARGE BORE PROCESS PIPE:

03-00-80 03-00-80 10-00-84 44%

INSTALL L ARGE BORE PIPE HANGERS, RESTRAINTS AND SHUBBERS:

03-00-80 03-00-80 04-00-85 25%

INSTALL SMALL BORE PIPE:

03-00-81 03-00-81 01-00-85 5%

INSTALL CABLE TRAY:

09-00-80 09-00-80 10-00-84 42%

INSTALL EXPOSED METAL CONDUIT:

04-00-81 04-00-81 12-00-84 4%

INSTALL POWER CONTROL, INSTRUMENTATIDH AND SECURITY CABLE:

02-00-82 12-00-84 0%

INSTALL ELECTRICAL TERMINATIONS:

03-00-82 04-00-85 0%

CONDUCT REACTOR COLD HYDROSTATIC TEST:

12-01-84 12-07-84 0%

CONDUCT HOT FUNCTIONAL TEST:

03-01-85 03-29-85 0%

CONDUCT PREOP AND ACCEPTANCE TESTS NECESSARY FOR FUEL LOAD:

09-15-83 08-02-85 0%

~

C0NSTRUCTION STATUS REP 0RT PAGE NO: 2-134 WASHINGTON NUCLEAR 4 NUCLEAR POWER PLANT $

STATUS AS OF:

12-31-81 PLANT CHARACTER IST I C S:

KEY P E R S 0 N N E L:

DOCKET ND:

05000513 CORPORATE CONTACT:

R. L. FERGUSON, MANAGING DIRECTOR CP NO. 8 DATE ISSUED: CPPR-174/ 02-21-78 CORPORATE ADDRESS:

P. O. BOX 968 CP EXPIRATION DATE:

RICHLAND, WASHINGTON 99352 APPLICANT:

WASHINGTON PUBLIC POWER SUPPLY SYSTEM PLANT LOCATION:

30 MI NW OF RICHLAND, WA CORPORATE PHONE NO:

(509) 372-5000 IE REGION:

5 AE:

UNITED ENG. 1 CONSTRUCTORS NSSS:

SABC0CK & WILCOX CONSTRUCTOR:

BECHTEL NRC LPM:

R. HERNAN IE PROJECT INSPECTOR:

P. P. HARBUT REACTOR TYPE:

PWR IE RESIDENT INSPECTOR:

A. TOTH DER (MWE):

1267 INSPECTION S T A T U S:

FUEL L0AD DATE CHANGES TIME PERIOD AS REP 0RTED BY U T I L I T Y:

OCT. 1981 - DEC. 1981 REPORT NEW REASON FOR CHANGE REPORT BEG DATE END DATE DATE SCHEDULE REPORTED BY UTILITY NUMBER OF INSP.

OF INSP.

09-00-76 09-00-82 DELAY IN COMPLETION OF ENGINEERING AND 81-09 10-01-81 10-23-81 LABOR DIFFICULTIES.

81-10 11-16-81 11-20-81 01-00-78 12-00-83 1 LABOR PRODUCTIVITY BELOW PLANNED 81-11 12-10-81 12-10-81 LEVELS.

81-12 12-14-81 12-18-81

2. INCREASE IN PLANNED DURATIONS FOR PIPING AND ELECTRICAL ACTIVITIES.

3.

EXTEND DURATION FOR PREOPERATIONAL Inspection Reports are available at local PDRs.

TESTING TO COMMERCIAL OPERATION.

03-07-79 12-00-84 LABOR PRODUCTIVITY BELOW PLANNED LEVELS / -

LEAD PLANT SCHEDULE REEVALUATION.

06-00-80 01-00-85 NO REASON PROVIDED.

12-17-81 N/S WORK HALTED FOR FINANCIAL REASONS.

L0 CAL PUBLIC D0CUMENT R 0 0 M:

RICHLAND PUBLIC LIBRARY SWIFT AND NORTHGATE STREETS RICHLAND, WASHINGTON 99352

C0NSTRUCTION 5TATUS REP 0RT PAGE NO: 2-135 WASHINGTON NUCLEAR 4 NUCLEAR POWER PLANTS STATUS AS OF:

12-31-81 C0HSTRUCT ION S T A T U S:

APPLICANT'S CURRENT ESTIMATED FUEL LOADING DATE:

N/S APPLICANTS CONSTRUCTION COMPLETI0H ESTIMATE AS APPLICANT'S PREVIOUS ESTIMATED FUEL LCADING DATE:

01-00-85 DEFINED IN CP: (EARLIEST) 12-01-83 APPLICANT'S ESTIMATED FUEL LOADING DATE AT CP ISSUANCE:

09-00-81 (LATEST) 12-01-85 APPLICANT'S CURRENT ESTIMATED COMMERCIAL OPERATION DATE: N/S CURRENT ESTIMATED PERCENT CONSTRUCTION COMPLETE: 24%

COMMENTS REGARDING CURRENT CONSTRUCTION STATUS: WORK ON THIS PROJECT WAS HALTED IN JUNE 1981 FOR FINANCIAL REASONS AND NEED FOR POWER CONSIDERATIONS. THE PLANT IS BEING PLACED IN A " MOTHBALL" STATUS FOR TWO YEARS (UNTIL JUNE 1983).

A DECISION ON FURTHER ACTIVITY WILL BE MADE AT THAT TIME.

ESTIMATED ACTUAL ESTIMATED ACTUAL F.ST IMAT ED START START COMPLETION COMPLETION % COMPLETE MOBILIZE AND PREPARE SITE:

08-00-75 100%

PLACE STRUCTURAL CONCRETE:

11-00-77 6S%

INSTALL REACTOR PRESSURE VESSEL:

INSTALL LARGE BORE PROCESS PIPE:

06-01-80 11%

INSTALL LARGE BORE PIPE HANGERS, RESTRAINTS AND $NUBBERS:

06-01-80 9%

INSTALL SMALL BORE PIPE:

INSTALL CABLE TRAY:

04-01-81 6%

INSTALL EXPOSED METAL CONDUIT:

05-01-81 1%

INSTALL POWER, CONTROL, INSTRUMENTATION AND SECURITY CABLE:

INSTALL ELECTRICAL TEPMINATIONS:

CONDUCT REACTOR COLD HYDROSTATIC TEST:

CONDUCT HOT FUNCTIONAL TEST:

CONDUCT PREOP AND ACCEPTANCE TESTS NECESSARY FOR FUEL LOAD:

4 4

e

C0NSTRUCTION STATUS REP 0RT PAGE NO: 2-136 STATUS As OF:

12-31-81 WASHINGTON NUCLEAR 5 NUCLEAR POWER PLANTS KEY P E R S 0 N N E L:

PLANT CHARACTERISTICS:

CORPORATE CONTACT:

R. L. FERGUSON, MANAGING DIRECTOR DOCKET NO:

05000509 CP NO. 8 DATE ISSUED: CPPR-155/ 04-11-78 CORPORATE ADDRESS:

P. O. BOX 968 CP EXPIRATION DATE:

07-00-84 RICHLAND, WASHINGTON 99352 APPLICANT:

WASHINGTON PUBLIC POWER SUPPLY SYSTEM PLANT LOCATION:

26 MI W OF OLYMPIA, WA CORPORATE PHONE NO:

(509) 372-5000 IE REGION:

5 AE:

EBASCO NSSS:

COMBUSTION ENGINEERING NRC LPM:

L. WHEELER CONSTRUCTOR:

EBASCO IE PROJECT INSPECTOR:

REACTOR TYPE:

PWR IE RESIDENT INSPECTOR:

W. G. ALBERT DER (MWE):

1242 FUEL L0AD DATE CHANGES IN$PECTION S T A T U S:

TIME PERIOD AS REP 0RTED BY U T I L I T Y:

OCT. 1981 - DEC. 1981

.dRT NEW REASON FOR CHANGE REPORT BEG DATE END DATE DATE SCHEDULE REPORTED BY UTILITY HUMBER OF INSP.

OF INSP.

05-22-79 12-00-85 SCHEDULE REEVALUATION.

81-17 10-05-81 10-30-81 06-00-80 01-G0-86 NO REASON PROVIDED.

81-18 10-14-81 10-30-81 12-17-81 N/S WORK HALTED FOR FINANCIAL REASONS.

81-19 11-01-81 11-30-81 81-20 12-07-81 12-11-81 81-21 12-10-81 12-10-81 81-22 12-01-81 12-30-81 Inspection Reports are available at local PDRs.

L0 CAL PUBLIC D0CUMENT R 0 0 M:

W.H. ABEL MEMORIAL LIBRARY 125 MAIN STREET, SOUTH MONTESANO, WASHINGTON 98563

C0NSTRUCTION

$TATUS REP 0RT PAGE ND: 2-137 WASHINGTON HUCLEAR 5 NUCLEAR POWER PLANTS STATUS AS OF:

12-31-81 C0NSTRUCTIOh S T A T U S:

APPLICANT'S CURRENT ESTIMATED FUEL LOADING DATE:

N/S APPLICANTS CONSTRUCTION COMPLETION ESTIMATE AS APPLICANT'S PREVIOUS ESTIMATED FUEL LOADING DATE:

01-00-86 DEFINED IN CP: (EARLIEST) 07-01-84 APPLICANT'S ESTIMATED FUEL LOADING DATE AT CP ISSUANCE:

01-00-85 (LATEST) 07-01-86 APPLICANT'S CURRENT ESTIMATED COMMERCIAL OPERATION DATE: N/S CURRENT ESTIMATED PERCENT CONSTRUCTION COMPLETE:

3%

l COMMENTS REGARDING CURRENT CONSTRUCTION STATUS: WORK ON THIS PROJECT WAS HALTED IN JUNE 1981 FOR FINANCIAL REASONS l

AND NEED FOR POWER CONSIDERATIONS. THE PLANT IS BEING PLACED IN A " MOTHBALL" STATUS FOR TWO YEARS (UNTIL JUNE 1983).

A DECISION i

ON FURTHER ACTIVITY WILL BE MADE AT THAT TIME.

ESTIMATED ACTUAL ESTIMATED ACTUAL ESTIMATED START START COMPLETION C0t1P L E T T O N % COMPLETE MOBILIZE AND PREPARE SITE:

04-00-77 04-00-77 04-00-78 100%

PLACE STRUCTURAL CONCRETE:

INSTALL REACTOR PRESSURE VESSEL:

l INSTALL LARGE BORE PROCESS PIPE:

INSTALL LARGE BORE PIPE HANGERS, RESTRAINTS AND SHUBBERS:

INSTALL SMALL BORE PIPE:

ILSTALL CABLE TRAY:

INSTALL EXPOSED METAL CONDUIT:

INSTALL POWER. CONTROL, INSTRUMENTATION AND SECURITY CABLE:

INSTALL ELECTRICAL TERMINATI0HS:

CONDUCT REACTOR COLD HYDROSTATIC TEST:

CONDUCT HOT FUNCTIONAL TEST:

CONDUCT PREOP AND ACCEPTANCE TESTS NECESSARY FOR FUEL LOAD:

C0NSTRUCTION STATUS REP 0RT PAGE NO: 2-138 NUCLEAR POWER PLANTS STATUS AS OF:

12-31-81 WATERFORD 3 KEY P E R S 0 N N E L:

PLANT C H A R A C T E R I S T I C S:

CORPORATE COHTACT:

L. V. MAURIN, VICE PRESIDENT DOCKET NO:

05000382 NUCLEAR OPERATIONS CP HO. & DATE ISSUED: CPPR-103/ 11-1/-74 CORPORATE ADDRESS:

142 DELARONDE STREET CP EXPIRATION DATE:

10-31-83 NEW ORLEANS, LOUISIANA 70174 APPLICANT:

LOUISIANA POWER & LIGHT PLANT LOCATION:

20 MI W OF NEW ORLEANS, LA CORPORATE PHONE NO:

(504) 366-2345 IE REGIDH:

4 AE:

EBASCO NSSS:

COMBUSTION ENGINEERING NRC LPM:

S. BLACK CONSTRUCTOR:

EBASCO IE PROJECT INSPECTOR:

REACTOR TYPE:

PWR IE RESIDENT INSPECTOR:

L. CONSTABLE DER (MWE):

1151 FUEL L0AD DATE CHANGES INSPECTION S T A T U 5:

AS REPQRTED BY UT I L I T Y:

TIME PERIOD OCT, 1981 - DEC, 1981 REPORT HEW REASON FOR CHANGE REPORT BEG DATE END DATE DATE SCHEDULE REPORTED BY UTILITY HUMBER OF INSP.

OF INSP.

09-27-74 06-00-79 INORDINATELY LENGTHY LICENSING PROCEEDING, WHICH IS CURRENTLY BEING PROLOHGED BY THE

)

8125 09-16-81 10-15-81 ANTI-TRUST ISSUE.

8127 10-19-81 10-22-81 8128 10-16-81 11-15-81 11-20-74 08-00-79 INORDINATELY LENGHTY LICENSING PROCEEDING.

WHICH WAS PROLOHGED BY THE ANTI-TRUST 8129 11-02-81 11-06-81 ISSUE.

02-06-76 11-00-80 REEVALUATION OF CONSTRUCTION SCHEDULE.

CHANGE REFLECTS A MORE REALISTIC AND PRECISE CONSTRUCTION SCHEDULE.

Inspection reports are available at local PDRs.

09-19-78 05-00-81 REEVALUATION OF CGNSTRUCTION SCHEDULE.

CHANGE REFLECTS A MORE REALISTIC AND PRECISE CONSTRUCTION SCHEDULE.

01-12-81 10-00-82 NO REASON PROVIDED.

L0 CAL PUBLIC D0CUMENT R 0 0 M:

UNIVERSITY OF NEW ORLEANS LIBRARY LOUISIANA COLLECTION. LAKEFRONT HEW ORLEANS, LOUISIANA 70122 l

C0N5TRUCTION 5TATUS REPORT PAGE NO: 2-139 WATERFORD 3 NUCLEAR POWER PLANTS STATUS AS OF:

12-31-81 C0NSTRUCTION S T A T U S:

APPLICANT'S CURRENT ESTIMATED FUEL LOADING DATE:

10-00-82 APPLICANTS CONSTRUCTION COMPLETION ESTIMATE AS APPLICANT'S PREVIOUS ESTIMATED FUEL LOADING DATE:

05-00-81 DEFINED IN CP: (EARLIEST)

APPLICANT'S ESTIMATED FUEL LOADING DATE AT CP ISSUANCE:

06-00-78 (LATEST)

APPLICANT'S CURRENT ESTIMATED COMMERCIAL OPERATION DATE: 04-00-83 CURRENT ESTIMATED PERCENT CONSTRUCTION COMPLETE: 94%

COMMENTS REGARDING CURRENT CONSTRUCTION STATUS:

ESTIMATED ACTUAL ESTIMATED ACTUAL ESTIMATED START START COMPLETION COMPLETION % COMPLETE MOBILIZE AND PREPARE SITE:

11-14-74 100%

PLACE STRUCTURAL CONCRETE:

12-08-75 05-01-82 100%

INSTALL REACTOR PRESSURE VESSEL:

10-01-78 01-21-79 100%

INSTALL LARGE BORE PROCESS PIPE:

09-01-77 09-30-82 98%

INSTALL LARGE BORE PIPE NANGERS, RESTRAINTS AND SNUBBERS:

09-01-77 09-30-82 92%

INSTALL SMALL BORE PIPE:

09-01-77 09-30-82 93%

INSTALL CABLE TRAY:

02-02-78 06-30-80 100%

INSTALL EXPOSED METAL CONDUIT:

02-02-78 09-30-82 90%

INSTALL POWER CONTROL, INSTRUMENTATION AND SECURITY CABLE:

09-01-78 39-30-82 88%

INSTALL ELECTRICAL TERMINATIONS:

05-01-79 09-30-82 77%

CONDUCT REACTOR COLD HYDROSTATIC TEST:

04-01-82 04-15-82 0%

CONDUCT HOT FUNCTIONAL TEST:

05-27-82 07-02-82 0%

CONDUCT PREOP AND ACCEPTANCE TESTS NECESSARY FOR FUEL LOAD:

02-19-79 09-01-82 34%

j

l PAGE NO: 2-140 C0NSTRUCTION STATUS REPORT STATUS AS OF:

12-31-81 NUCLEAR POWER PLANTS WATTS BAR 1 KEY P E R S O N N E L:

PLANT CHARACTERISTICS:

CORPORATE CONTACT:

G. KIMMONS, MANAGER DOCKET HO 05000390 DESIGN 4 CONSTRUCTION CP HD. A DATE ISSUED: CPPR-91 / 01-23-73 CORPORATE ADDRESS:

400 COMMERCE AVENUE CP EXPIRATION DATE:

06-01-79 KNOXVILLE, TENNESSEE 37092 APPLICANT:

TENNESSEE VALLEY AUTHORITY PLANT LOCATION:

10 MI S OF SPRING CITY, TENN CORPORATE PHONE HO:

(615) 632-2911 IE REGION:

2 TENNESSEE VALLEY AUTHORITY AE:

NSSS:

WESTINGHOUSE NRC LPM:

T. KENYON CONSTRUCTOR:

TENNESSEE VALLEY AUTHORITY IE PROJECT INSPECTOR:

R. %, CRLENJAK REACTOR TYPE:

PWR IE RESIDENT INSPECTOR:

J. MCDCNALD DER (MWE):

1165 FUEL L0AD DATE CHANGES INSPECTION S T A T U S:

AS REPORTED BY U T I L I T Y:

TIME PERIOD OCT. 1981 - DEC. 1981 REPORT NEW REASON FOR CHANGE REPORT BEG DATE END DATE DATE SCHEDULE REPORTED BY UTILITY l

HUMBER OF INSP.

OF INSP.

11-16-73 01-16-78 IHABILITY TO OBTAIN STEEL ANCHOR BOLTS AND RLINFORCING RODS.

8121 10-06-81 10-09-81 8122 10-20-81 10-23-81 05-14-74 06-00-78 REDESIGN OF CONTAINMENT TO ACCOMMODATE HIGHER TRANSIENT PRESSURES, INABILITY TO 8123 10-19-81 10-23-81 OBTAIN REDESIGNED STEEL ANCHOR BOLTS AND 8124 10-26-81 10-28-81 REINFORCING RODS, PLUS AN INCREASE IN TIME 8125 09-21-81 10-24-81 TO ERECT STEEL PL ATE THICKER TH AN THE 8126 10-21-81 11-23-81 ORIGINAL DESIGN.

8127 11-24-81 11-24-81 8128 12-07-81 12-11-8' 07-23-76 12-05-78 LATE DELIVERY OF PRINCIPAL PIPING, VALVES, AND HANGERS WHICH FORCED IMPOSSIBLE PEAKS 8129 12-14-81 12-18-Sn IN STEAMFITTER MANPOWER, 8130 12-14-81 12-18-81 8131 11-24-81 12-20-81 01-09-78 06-00-79 LATE DELIVERY OF ICE CONDEHSER EMBEDMENTS 11-07-78 12-00-79 NO REASON GIVEN.

09-12-79 09-01-80 NO REASON GIVEN.

INSPECTION REPORTS ARE AVAILABLE AT LOCAL PDR'S.

09-10-80 11-00-81 HD REASON PROVIDED.

09-10-81 08-00-52 NO REASON PROVIDED.

L0 CAL PUBLIC D0CUMENT R 0 0 M:

CHATTANDOGA-HAMILTON COUNTY BICENTENNIAL LIBRARY 1001 BROAD STREET CHATTANOOGA, TENNESSEE 37402

C0NSTRUCTION STATUS REP 0RT PAGE NO: 2-141 WATTS BAR 1 NUCLEAR P0WER PLANTS STATUS AS OF 12-31-81 C0NSTRUCTION S T A T U S:

APPLICANT'S CURRENT ESTIMATED FUEL LOADING DATE:

08-00-82 APPLICANTS CONSTRUCTION COMPLETION ESTIMATE AS APPLICANT'S PREVIOUS ESTIMATED FUEL LOADING DATE:

11-00-31 DEFINED IN CP: (EARLIEST)

APPLICANT'S ESTIMATED FUEL LOADING DATE AT CP ISSUANCE:

05-00-77 (LATEST)

APPLICANT'S CURRENT ESTIMATED COMMERCIAL OPERATION DATE: 06-00-83 CURRENT ESTIMATED PERCENT CONSTRUCTION COMPLETE: 80%

COMMENTS REGARDING CURRENT CONSTRUCTION STATUS:

ESTIMATED ACTUAL ESTIMATED ACTUAL ESTIMATED START iTART COMPLETION COMPLETICH % COMPLETE MOBILIZE AND PREPARE SITE:

12-26-72 04-15-74 100%

PLACE STRUCTURAL CONCRETE:

04-09-74 09-12-78 100%

INSTALL REACTOR PRESSURE VESSEL:

12-07-76 05-05-77 100%

INSTALL LARGE BORE PROCESS PIPE:

10-17-77 11-14-80 100%

INSTALL LARGE BORE PIPE HANGERS, RESTRAINTS AND SHUBBERS:

10-17-77 11-14-80 100%

-INSTALL SMALL BORE PIPE:

07-01-77 07-31-81 100%

l INSTALL CABLE TRAY:

11-02-73 04-22-76 100%

INSTALL EXPOSED METAL CONDUIT:

09-08-75 03-24-77 100%

INSTALL POWER, CONTROL, INSTRUMENTATION AND SECURITY CABLE:

06-03-76 08-02-82 84%

INSTALL ELECTRICAL TERMINATIONS:

06-03-76 08-02-82 76%

CONDUCT REACTOR COLD NYDR0 STATIC TEST:

10-15-81 10-24-81 10-24-81 10-24-81 100%

CONDUCT NOT FUNCTIONAL TEST:

03-11-82 05-03-82 0%

CONDUCT PREOP AND ACCEPTANCE TESTS NECESSARY FOR FUEL LOAD:

01-02-79 08-02-82 52%

C0NSTRUCTION STATUS REPORT PAGE NO: 2-142 NUCLEAR POWER PLANTS STATUS AS OF:

12-31-81 WATTS BAR 2 KEY PERSONNELa PLANT C H A R A C T E R I $ T I C 5:

CORPORATE CONTACT:

G. KIMMONS, MANAGER DOCKET NO:

05000391 DESIGN 8 CONSTRUCTION CP NO. 8 DATE ISSUED: CPPR-92 / 01-23-73 CORPORATE ADDRESS:

400 COMMERCE AVENUE CP EXPIRATION DATE:

03-01-80 KNOXVILLE, TENNESSEE 37902 APPLICANT:

TENNESSEE VALLEY AUTHORITY PLANT LOCATION:

10 MI S OF SPRING CITY, TENN CORPORATE PHONE NO:

(615) 632-2911 IE REGION:

2 AE:

TENNESSEE VALLEY AUTHORITY NSSS:

WESTINGHOUSE CONSTRUCTOR:

TENNESSEE VALLEY AUTHORITY NRC LPM:

T. KENYON IE PROJECT INSPECTOR:

R. V.

CRLENJAK REACTOR TYPE:

PWR IE RESIDENT INSPECTOR:

J. MCDONALD DER (MWE):

1165 FUEL L0AD DATE CHANGES IN5PECTION S T A T U S:

TIME PERIOD AS REPORTED BY U T I L I T Y:

OCT, 1981 - DEC. 1931 REPORT NEW REASON FOR CHANGE REPORT BEG DATE END DATE DATE SCHEDULE REPGRTED BY UTILITY NUMBER OF INSP.

OF INSP.

11-16-73 10-16-78 INABILITY TO OBTAIN STEEL ANCHOR BOLTS AND REINFORCING RODS.

8121 10-20-81 10-23-81 8122 10-26-81 10-28-81 05-14-74 03-05-79 REDESIGN OF CONTAINMENT TO ACCOMMODATE HIGHER TRANSIENT PRESSURES, INABILITY TO 8123 09-21-81 10-24-81 OBTAIN REDESIGNED STEEL ANCHOR BOLTS AND 8124 10-21-81 11-23-81 REINFORCING RODS, PLUS AN INCREASE IN TIME 8125 11-24-81 11-24-81 TO ERECT STEEL PLATE THICKER THAN THE 8126 12-14-81 12-18-81 ORIGINAL DESIGN.

8127 12-14-81 12-18-81 8128 11-24-81 12-20-81 07-23-76 09-05-79 LATE DELIVERY OF PRINCIPAL PIPING, VALVES, AND HANGERS WHICH FORCED IMPOSSIBLE PEAKS IN STEAMFITTER MANPOWER.

INSPECTION REPORTS ARE AVAILABLE AT LOCAL PDR'S, 01-09-78 03-00-80 LATE DELIVERY OF ICE CONDENSER EMBEDMENTS 11-07-78 09-00-80 NO REASON GIVEN.

09-12-79 06-01-81 NO REASON GIVEN.

09-10-80 08-00-82 NO REASON GIVEN.

09-10-81 06-00-83 NO REASON GIVEN.

L0 CAL PUBLIC D0CUMENT R 0 0 Mr CHATTANDOGA-HAMILTON COUNTY BICENTENNIAL LIBRARY 1001 BROAD STREET CHATTAH00GA, TENNESSEE 37402

., s

~

.." ', 4 3

sw

' t..,

t w

r I

^

t 4

.g.

+

t

+

.G 3

4

C0NSTRUCTION STA TUS REPORT PAGE NO: 2-143 WATTS BAR 2 NUCLEAR P0WER P LA NTS STATUS AS OF:

12-31-81 C0NSTRUCTION S T A T U S:

APPLICANT'S CURRENT ESTIMATED FUEL LOADING DATE:

06-00-83 APPLICANTS CONSTRUCTION COMPLETION ESTIMATE AS APPLICANT'S PREVIOUS ESTIMATED FUEL LOADING DATE:

08-00-82 DEFINED IN CP: (EARLIEST)

APPLICANT'S ESTIMATED FUEL LOADING DATE AT CP ISSUANCE:

11-00-76 (LATEST)

APPLICANT'S CURRENT ESTIMATED CCMMERCIAL OPERATION DATE: 04-00-84 CURRENT ESTIMATED PERCENT CONSTRUCTION COMPLETE: 60%

COMMENTS REGARDING CURRENT CONSTRUCTION STATUS:

ESTIMATED ACTUAL ESTIMATED ACTUAL ESTIMATED START START COMPLETION

[pMPLETION % COMPLETE MOBILIZE AND PREPARE SITE:

12-26-72 04-15-74 100%

PLACE STRUCTURAL CONCRETE:

05-10-74 11-02-78 100%

INSTALL REACTOR PRESSURE VESSEL:

10-10-77 12-30-77 100%

INSTALL LARGE BORE PROCESS PIPE:

12-09-77 04-12-82 82%

INSTALL LARGE BORE PIPE HANGERS, RESTRAINTS AND SNUBBERS:

03-10-78 10-04-82 66%

INSTALL SMALL BORE PIPE:

11-01-77 04-15-82 59%

INSTALL CABLE TRAY:

11-02-73 06-01-83 89%

INSTALL EXPOSED METAL CONDUIT:

09-08-75 03-24-77 100%

INSTALL POWER, CONTROL. INSTRUMENTATION AND SECURITY CABLE:

08-20-76 06-01-83 78%

INSTALL ELECTRICAL TERMINATIONS:

08-20-76 06-01-83 64%

CONDUCT REACTOR COLD NYDR0 STATIC TEST:

09-1S-82 09-22-82 0%

CONDUCT NOT FUNCTIONAL TEST:

01-19-83 02-24-83 0%

CONDUCT PREOP AND ACCEPTANCE TESTS NECESSARY FOR FUEL LOAD:

10-01-82 06-01-83 2S%

l l

PAGE HD: 2-144 C0N5TRUCTION STATUS REPQRT STATUS AS OF:

12-31-81 NUCLEAR POWER PLANTS WOLF CREEK t KEY P E R S 0 N N E L:

PLANT C H A R A C T E R I S T I C S:

CORPORATE CONTACT:

G. L. K0 ESTER, VICE PRESIDENT DOCKET NO:

05000482 NUCLEAR CP NO. & DATE ISSUED: CPPR-147/ 05-17-77 CORPORATE ADDRESS:

P. O. BOX 208 CP EXPIRATION DATE:

03-01-84 WICHITA, KANSAS 67201 APPLICANT:

KANSAS GAS 1 ELECTRIC PLANT LOCATION:

3.5 MI NE OF BURLINGTON, KAN CORPORATE PHONE NO:

(316) 261-6451 IE REGION:

4 AE:

BECHTEL NSSS:

WESTINGHOUSE NRC LPM:

J. HOPKINS CONSTRUCTOR:

DANIEL INTERNATIONAL IE PROJECT INSPECTOR:

REACTOR TYPE:

PWR IE RESIDENT INSPECTOR:

T. VANDEL DER (MWE):

1150 h

FUEL LDAD DATE CHANGES INSPECTION S T A T U S:

AS REPORTED BY UTILITY:

TIME PERIOD OCT. 1981 - DEC. 1981 REPORT NEW REASON FOR CHANGE REPORT BEG DATE END DATE DATE SCHEDULE REPORTED BY UTILITY NUMBER OF INSP.

OF INSP.

01-14-81 04-01-83 NO REASON PROVIDED.

8116 09-01-81 10-30-81 11-27-81 12-16-83 NO REASON PROVIDED.

8117 11-02-81 11-19-31 Inspection reports are available at local PDRs.

L0 CAL PUBLIC DOCUMENT R O O M:

WILLIAM ALLEN WHITE MEMORIAL LIBRARY EMPORIA STATE UNIVERSITY 1200 COMMERCIAL EMPORIA, KANSAS 66801

C0NSTRUCTION STATUS REPORT PAGE NO: 2-145 WOLF CREEK 1 NUCLEAR POWER PLANTS STATUS AS OF:

12-31-81 C0NSTRUCTION 5 T A T U S:

APPLICANT'S CURRENT ESTIMATED FUEL LOADING DATE:

12-16-83 APPLICANTS CONSTRUCTION COMPLETION ESTIMATE AS APPLICANT'S PREVIOUS ESTIt1ATED FUEL LOADING DATE:

04-01-83 DEFINED IN CP: CEARLIEST)

APPLICANT'S ESTIMATED FUEL LOADING DATE AT CP ISSUANCE:

10-01-82 (LATEST)

APPLICANT'S CURRENT ESTIMATED COMMERCIAL OPERATION DATE: 05-31-84 CURRENT ESTIMATED PERCENT CONSTRUCTION COMPLETE: 80%

COMMENTS REGARDING CURRENT CONSTRUCTION STATUS: DATA PREVIOUSLY REPCRTED CORRECT AS OF 09/30/81.

REVISIONS INDICATED REFLECT CURRENT SCHEDULES ANNOUNCED THE WEEK OF NOVEMBER 16, 1981 ESTIMATED ACTUAL ESTIMATED ACTUAL ESTIMATED START START COMPLETIQM

[QMPLETION E_{DUPLETE MOBILIZE AND PREPARE SITE:

01-24-77 01-24-77 08-01-77 12-01-77 103%

PLACE STRUCTURAL CONCRETE:

08-31-77 06-01-77 06-01-83 97%

INSTALL REACTOR PRESSURE VESSEL:

10-01-79 02-29-80 11-01-79 04-11-80 100%

INSTALL LARGE BORE PROCESS PIPE:

03-01-78 04-01-83 89%

INSTALL LARGE BORE PIPE NANGERS, RESTRAINTS AND SNUBBERS:

04-01-78 12-01-82 65%

INSTALL SMALL BORE PIPE:

08-01-78 04-01-83 51%

l INSTALL CABLE TRAY:

08-01-78 04-01-82 90%

INSTALL EXPOSED METAL CONDUIT:

02-01-78 12-01-82 53%

l INSTALL POWER, CONTROL, INSTRUMENTATION AND SECURITY CABLE:

02-41-80 04-01-83 65%

INSTALL ELECTRICAL TERMINATIONS:

06-01-80 08-01-83 29%

CONDUCT REACTOR COLD HYDROSTATIC TEST:

05-20-83 05-27-83 0%

CONDUCT NOT FUNCTIONAL TEST:

09-02-83 09-23-83 0%

CONDUCT PREOP AND ACCEPTANCE TESTS NECESSARY FOR FUEL LOAD:

05-25-81 07-29-81 10-01-83 0%

p.

4 C0NSTRUCTIOH S T*A T U'S REP 0RT PAGE NO: 2-146 YELLOW CREEK 1 N U.C L E A R POWER PLANTS STATUS AS OF 12-31-81 PLANT C H A R A C T E R I S T I C S:

K E.Y PERS0NNEL 00'CKET NO:

65000566 CORPORATE CONTACT:

G. KIMMONS, MANAGER CP NO. & DATE ISSUED: CPPR-172/ 11-29-78 DESIGN & CONSTRUCTION-CP. EXPIRATION DATE:

05-01-85 CORPORATE ADDRESS:

400 COMMERCE AVENUE APPLICANT:

TENNESSEE VALLEY AUTHORITY KNOXVILLE, TENNESSEE 37902 PLANT LOCATION:

15.MI E OF CORINTH, MISS IE REGION:

-2' CORPORATE PHONE NO:

(615) 632-2911 AE:

TENNESSEE VALLEY-AUTHORITY NSSS:

COMBUSTION ENGINEERING CONSTRUCTOR:

TENNESSEE VALLEY AUTHORITY NRC LPM:

L. WHEELER REACTOR TYPE:

PWR IE PROJECT INSPECTOR:

R. V. CRLENJAK DER (MWE):

1285 IE RESIDENT INSPECTOR:

INSPECTION STATUSt FUEL L0AD D A T E, CHANGES TIME PERILO AS R E P Q R T'E D BY U T I L I T Y:

OCT, 1981 - DEC. twia REPORT NEW REASON FOR CHANGE REPORT BEG DAT" 6.3 DATE DATE SCHEDULE REPORTED BY UTILITY HUMBER OF INSP if IMIE.

09-12-79 01-02-85 NO REASON GIVEN.

8110 10-20-Sc

?? 23-81 09-10-80 10-00-86 NO REASON PROVIDED.

08-14-81 07-00-89 NO REASON PROVIDED.

s INSPECTION REPORTS ARE AVAILABLE AT LOCAL PDR'S.

l l

J L0 CAL PUBL IC D0CUMENT R 0 0 M:

l CORINTH PUBLIC LIBRARY i

1023 FILLMORE STREET l

CORINTH, MISSISSIPPI 38834 l

./

i

C0NSTRUCTION STATUS REPQRT PAGE HC: 2-147.

^

YELLOW CREEK 1 NUCLEAR P0WER PLANTS STATUS AS OF:

12-31-81 C0NSTRUCTION 5 T A T U S:

APPLICANT'S CURRENT ESTIMATED FUEL LOADING DATE:

07-01-89 APPLICANTS CONSTRUCTION COMPLETION ESTIMATE AS APPLICANT'S PREVIOUS ESTIMATED FUEL LDADING DATE:

10-00-86 DEFINED IN CP: (EARLIEST) 02-01-84 APPLICANT'S ESTIMATED FUEL LOADING DATE AT CP ISSUANCE:

02-01-84 05-01-85 APPLICANT'S CURRENT ESTIMATED COMMERCIAL OPERATION DATE: 01-01-90 CURRENT ESTIMATED PERCENT CONSTRUCTIL.5 COMPLETE: 33%

COMMENTS REGARDING CURRENT CONSTRUCTION STATUS:

ESTIMATED ACTUAL ESTIMATED ACTUAL ESTIMATED START START COMPLETION COMPLETION % COMPLETE MOBILIZE AND PREPARE SITE:

02-09-78 12-14-78 100%

PLACE STRUCTURAL CONCRETE:

12-14-78 06-23-82 81%

1 INSTALL REACTOR PRESSURE VESSEL:

06-23-82 07-15-82 0%

INSTALL LARGE BORE PROCESS PIPE:

02-25-81 11-27-87 1%

INSTALL L ARGE BORE PIPE HANGERS, RESTRAINTS AND SNUBBERS:

02-25-81 01-14-88 1%

INSTALL SMALL BORE PIPE:

07-07-83 01-14-88 0%

INSTALL CABLE TRAY:

05-13-81 12-31-87 1%

INSTALL EXPOSED METAL CONDUIT:

02-11-83 12-25-86 0%

INSTALL POWER, CONTROL, INSTRUMENTATION AND SECURITY CABLE:

03-24-83 01-14-88 0%

INSTALL ELECTRICAL TERMINATI0HS:

03-24-83 01-14-88 0%

CONDUCT REACTOR COLD HYDROSTATIC TEST:

11-30-87 12-14-87 0%

CONDUCT HOT FUNCTIONAL TEST:

03-10-88 04-21-88 0%

l CONDUCT PREOP AND ACCEPTANCE TESTS NECESSARY FOR FUEL LOAD:

05-01-84 07-01-89 0%

~.. _ _

.m._

m k

C0NSTRUCTION STATUS REP 0RT PACE NO: 2-148 -

YELLOW CREEK 2 NUCLEAR POWER PLANT $

STATUS AS OF:

12-31-81 PLANT C H A R A C T E R I S T I C S:

KEY PERS0NNELa DOCKET NO:

05000567 CORPORATE CONTACT:

G. KIMMONS, MANAGER CP HO. 8 DATE ISSUED: CPPR-173/ 11-29-78 DESIGN & CONSTRUCTION CP EXPIRATION DATE:

05-01-86 CORPORATE ADDRESS:

400 COMMERCE AVENUE APPLICANT:

TENNESSEE VALLEY AUTHORITY KNOXVILLE, TENNESSEE 37902 PLANT LOCATION:

15 MI E OF CORINTH, MISS IE REGIDH:

2 CORPORATE PHONE NO:

(615) 632-2911 AE2 TENNESSEE VALLEY AUTHORITY NSSS:

COMBUSTION ENGINEERING CONSTRUCTOR:

TENNESSEE VALLEY AUTHORITY NRC LPM:

L. WHEELER REACTOR TYPE:

PWR IE PROJECT INSPECTOR:

R. V. CRLENJAK DER (MWE):

1285 IE RESIDENT INSPECTOR:

IN$PECTION STATUSt FUEL L0AD DATE CHANGES TIMEPEkIOD AS REPQRTED BY UTILITY OCT. 1981 - DEC. 1981 REPORT NEW REASON FOR CHANGE REPORT BEG DATE END DATE DATE SCHEDULE REPORTED BY UTILITY HUMBER OF INSP.

OF INSP.

09-12-79 10-05-87 HO REASON GIVF.N.

8110 10-20-81 10-23-81 01-15-80 04-01-87 NO REASON GIVEN.

09-10-80 10-00-92 NO REASON GIVEN.

08-14-81 N/S DEFERRED.

INSPECTION REPORTS ARE AVAILABLE AT LOCAL PDR'S.

I i

i L0 CAL PUBLIC D0CUMENT R 0 0 M:

CORINTH PUBLIC LIBRARY 1023 FILLMORE STREET CORINTH, MISSISSIPPI 38834 l

C0NSTRUCTION STATUS REPQRT PAGE NO: 2-149 YELLOW CREEK 2 NUCLEAR POWER PLANTS STATUS AS OF:

12-31-81 C0NSTRUCTION STATUSt APPLICANT'S' CURRENT ESTIMATED FUEL LOADING DATE:

N/S APPLICANTS CONSTRUCTION COMPLETION ESTIMATE AS

-APPLICANT'S PREVIOUS ESTIMATED FUEL LOADING DATE:

10-00-92 DEFINED IN CP: (EARLIEST)

APPLICANT'S ESTIMATED FUEL LOADING DATE AT CP ISSUANCE:

N/S (LATEST)

APPLICANT'S CURRENT ESTIMATED COMMERCIAL OPERATION DATE: N/S CURRENT ESTIMATED PERCENT CONSTRUCTION COMPLETE:

3%

COMMENTS REGARDING CURRENT CONSTRUCTICH STATUS: PROJECT DEFERRED.

ESTIMATED ACTUAL ESTIMATED ACTUAL ESTIMATED START START COMPLETION C0t1P L ET T ON % COMPLETE MOBILIZE AND PREPARE SITE:

N/S PLACE STRUCTURAL CONCRETE:

INSTALL REACTOR PRESSURE VESSEL:

INSTALL LARGE BORE PROCESS PIPE:

INSTALL LARGE BORE PIPE MANGERS, RESTRAINTS AND SNUBBERS:

INSTALL SMALL BORE PIPE:

~ INSTALL CABLE TRAY:

. INSTALL EXPOSED METAL CONDUIT:

  • INSTALL POWER, CONTROL, INSTRUMENTATION AND SECURITY CABLE:

INSTALL ELECTRICAL TERMINATIONS:

CONDUCT REACTOR COLD HYDROSTATIC TEST:

CONDUCT NOT FUNCTIONAL TEST:

CONDUCT PREOP AND ACCEPTANCE TESTS NECESSARY FOR FUEL LOAD:

C0NSTRUCTION STATUS REPORT PAGE NO: 2-150 NUCLEAR POWER PLANTS STATUS AS OF:

12-31-81 2IMMER 1 KEY PERS0NNELa PLANT CHARACTERISTICSt CORPORATE CONTACT:

E.

A.

BORGMAN, VICE PRESIDENT DOCKET ND:

05000358 ENGINEERING CP NO. 8 DATE ISSUED: CPPR-83 / 10-27-72 CORPORATE ADDRESS:

139 EAST 4TH STREET CP EXPIRATION DATE:

01-01-77 CINCINNATI, ONIO APPLICANT:

CINCINNATI GAS 3 ELECTRIC PLANT LOCATIDH:

24 MI SE OF CINCINNATI, OH CORPORATE PHONE NO:

(513) 632-2663 IE REGION:

3 AE SARGENT & LUNDY

.NSSS:

GENERAL ELECTRIC CONSTRUCTOR:

KAISER ENGINEERS NRC LPM:

I. PILTIER IE PROJECT INSPECTOR:

L. MCGREGOR REACTOR TYPE:

BWR IE RESIDENT INSPECTOR:

W. CHRISTIANSON DER (MWE):

0810 FUEL L0AD DATE CHANGES INSPECTION S T A T U S:

AS REPQRTED BY UTILITY:

TIME PERIOD OCT, 1981 - DEC. 1981 REPORT NEW REASON FOR CHANGE REPORT BEG DATE END DATE DATE SCHEDULE REPORTED BY UTILITY NUMBER OF INSP.

OF INSP.

09-26-74 02-00-78

1. PRODUCTIVITY.

2.

SOME MATERIAL SHORTAGES.

8105 07-28-81 07-31-81

3. CRAFT STRIKES WHICH CONSUMED MOST OF THE SUMMER BUILDING SEASON.

Inspection Reports are available at local PDRs.

10-15-74 04-00-78 REEVALUATION OF NOS.

1, 2 AND 3 ABOVE.

10-18-77 10-00-78 REEVALUATION OF CONSTRUCTION NETWORK.

04-00-78 06-00-79 CONSTRUCTION EXTENDED SCHEDULE.

05-14-79 10-00-79 NO REASON GIVEN.

09-2'-79 08-00-80 NO REASON GIVEN.

06-03-80 11-00-81 NO REASON GIVEN.

10-22-81 07-00-82 NO REASON GIVEN.

l L0 CAL PUBLIC D0CUMENT R 0 0 M:

I CLERMONT COUNTY LIBRARY THIRD AND BROADWAY STREETS BATAVIA, OHIO 45103

M C0NS'TRUCTION STATUS REP 0RT PAGE NO: 2-151

~

ZIMMER 1 NUCLEAR POWER PLANT $

STATUS AS OF:

12-31-81 C0NSTRUCTION STATU5:

APPLICANT'S CURRENT ESTIMATED FUEL LOADING DATE:

07-00-82 APPLICANTS CONSTRUCTION CCMPLETION ESTIMATE AS APPLICANT'S PREVIOUS ESTIMATED FUEL LOADING DATE:

11-00-81 DEFINED IN CP: (EARLIEST)

APPLICANT'S ESTIMATED FUEL LOADING DATE AT CP ISSUANCE:

01-00-77 (LATEST)

APPLICANT'S CUPRENT ESTIMATED COMMERCIAL OPERATION DATE: 11-00-82 CURRENT ESTIMATED PERCENT CONSTRUCTION COMPLETE: 97%

COMMENTS REGARDING CURRENT CONSTRUCTION STATUS: UPDATE NOT PROVIDED IN HEW FORMAT.

ESTIMATED ACTUAL ESTIMATED ACTUAL ESTIMATED START START COMPLETION COMPLETION % COMPLETE MOBILIZE AND PREPARE SITE:

03-00-71 06-00-71 100%

PLACE STRUCTURAL CONCRETE:

06-00-73 INSTALL REACTOR PRESSURE VESSEL:

11-00-75 01-00-76 100%

INSTALL LARGE BORE PROCESS PIPE:

INSTALL LARGE BORE PIPE HANGERS, RESTRAINTS AND SNUBBERS:

03-00-75 06-00-82 92%

INSTALL SMALL BORE PIPE:

INSTALL CABLE TRAY:

08-00-73 05-00-81 100%

INSTALL EXPOSED METAL CONDUIT:

08-00-73 05-00-81 100%

INSTALL POWER, CONTROL, INSTRUMENTATION AND SECURITY CABLE:

32-00-70 02-00-82 98%

INSTALL ELECTRICAL TERMINATIONS:

CONDUCT REACTOR COLD HYDROSTATIC TEST:

05-00-78 07-00-78 100%

CONDUCT HOT FUNCTIONAL TEST:

N/A N/A N/A CDHDUCT PREOP AND ACCEPTANCE TESTS NECESSARY FOR FUEL LOAD:

3 e

,.m.

l l

2E O_

G.3 LaJ M

t

,m y

y

S C H E-D U L E F0R U P.D A T E S PAGE NO: 3-001 CALENDAR YEAR 1 982 Thi s report is a quartorly publication.

Updatos from the respondents for Calendar Year 1982 are duo as follows:

FIRST QUARTER 1982 DUE APRIL 30, 1982 SECOND QUARTER 1982 DUE JULY 30, 1982 THIRD QUARTER 1982 DUE UCTOBER 29, 1982 FOURTH QUARTER 1982 DUE JANUARY 28, 1983 j

The _epdate information should be forwarded to:

Chief, Manancmont Information Branch Offico of Management and Program Analysis U. S. Nuc1 car Regulatory Commission Washington, D. C.

20555 1

I I

'PAGE NO: 3-002 C0NSTRUCTION STATUS REPQRT PAGE NO: 2-XXX FACILITY MAME APPEARS HERE NUCLEAR P0WER PLANTS STATUS AS OF PLANT CHARACTERISTICSt KEY P E R S O N N E L:

DOCKET N0 ~

05000XXX CORPORATE CONTACT:

CP NO. 8 DATE ISSUED:

CP EXPIRATION DATE:

CORPORATE ADDRESS APPLICANT:

PLANT LOCATION:

IE REGION:

CORPORATE PHONC NO:

A E: -

NS$$:

CONSTRUCTOR:

HRC LPM:

REACTOR TYPE IE PROJECT INSPECTOR:

DER (MWE):

IE RESIDENT INSPECTOR:

INSPECTION S T A T U S:

FUEL L0AD DATE CHANGES TIME PERIOD AS REPORTED BY U T I L I T Y:

REPORT NEW REASON FOR CHANGE REPORT BEG DATE END DATE DATE SCHEDULE REPORTED BY UTILITY NUMBER OF INSP.

OF INSP.

t I

i I

L l

L0 CAL PUBLIC DOCUMENT R 0 0 M:

I

m, PAGE NO: 3-803 C0NSTRUCTION STATUS REPORT PAGE NO: 2-XXX FACILITY NAME APPEARS HERE NUCLEAR POWER PLANTS STATUS AS OF J

C0NSTRUCTION S T A T U S:

APPLICANT'S CURRENT ESTIMATED FUEL LOADING DATE:

APPLICANTS CONSTRUCTION COMPLETION ESTIMATE AS APPLICANT'S PREVIOUS ESTIMATED FUEL LOADING DATE:

DEFINED IN CP: (EARLIEST)

APPLICANT'S ESTIMATED FUEL LOADING DATE AT CP ISSUANCE:

(LATEST)

APPLICANT'S CURRENT ESTIMATED COMMERCIAL OPERATION DATE:

CURRENT ESTIMATED PERCENT CONSTRUCTION COMPLETE:

COMMENTS REGARDING CURRENT CONSTRUCTION STATUS:

ESTIMATED ACTUAL ESTIMATED ACTUAL ESTIMATED START START COMPLETION COMPLETION % COMPLETE MOBILIZE AND PREPARE SITE:

PLACE STRUCTURAL CONCRETE:

INSTALL REACTOR PRESSURE VESSEL:

INSTALL LARGE BORE PROCESS PIPE:

INSTALL LARGE BORE PIPE HANGERS, RESTRAINTS AND SNUBBERS:

INSTALL SMALL BORE PIPE:

INSTALL CABLE TRAY:

INSTALL ~ EXPOSED METAL CONDUIT INSTALL POWER, CONTROL, INSTRUMENTATION AND SECURITY CABLE:

INSTALL ELECTRICAL TERMINATIONS:

CONDUCT REACTOR COLD HYDROSTATIC TEST:

CONDUCT HOT FUNCTIONAL TEST:

CONDUCT PREOP AND ACCEPTANCE TESTS NECESSARY FOR FUEL LOAD:

5

f,HC F oRu 335 U.S NUCLE AR REGUL ATORY COMMISSION BIBLIOGRAPHIC DATA SHEET NUREG-0030, Vol. 5, No. 4

4. TSTLE AND SUBTITLE (Asid Volume Na, ef apprcenate) 2 (Leave blarsk)

Nuclear Power Plants - Construction Status Report Data as of 12/31/8l 3 RECsPIENT'S ACCESSION NO.

7. AUTHORfS)
5. DATE REPORT COMPLE1ED MONTH l YEAR April 1982
9. PE RFORMING ORGANIZATION NAME AND M AILING ADDRESS (include les Code)

DATE REPORT ISSUED U. S. Nuclear Regulatory Conunission gp p*j'j" I jy2 Office of Management and Program Analysis Managenent Information Branch 8 " " "'

Washington, D. C.

20555 8 ILeave Nanal

12. SPONSORING ORcANIZ ATION N AME AND MAILING ADDRESS (/nclude lip Cadel U. S. Nuclear Regulatory Commission Office of Managenent and Program Analysis II. CONTRACT NO.

Management Information Branch Washington, D. C.

20555

13. TYPE OF REPORT PE RIOD COVE RE D //nclus.ve dates)

Construction Status Report October 1,1981 Thru December 31, 1981

15. SUPPLEMENTARY NOTES 14 (L Paw DWi& J
16. ABSTR ACT (200 words or ressi i

The " Construction Status Report," also referred to as the " Yellow Book," is a quarterly publication containing nuclear power plant construction data and actual progress. The information contained in this report is supplied to the NRC by applicants with Construction Permits, i

l i

17 KE Y WORDS AND DOCUME NT AN ALYSIS 3 7a DESCRIPTOHS 17ti SDENTIFIE RS.OPEN ENDE D TE RMS 13 AV AILABILITY ST ATEMENT EC RITY CLAS$ iTn 8 "eDo'rs 21 *.O OF Pt4E S 19 IncYassified L

Unlimited 2 E d's's'i"fleS" "'

S s

dr U.S. COVERNMENT PRINTING OFFICE: 1982 361 302/523

UNITED STATES NUCLE AQ QEGULATOQY COMMisslON f

7 W ASHINGTON, 0. C. 20$55 POSTAGE AND FEES PAID OFFICI AL BustNESS U.S. NUCLE A R RE GUL ATO R Y PEN ALTY FOR PRIVATE USE,3300 CommissioM L

j

)

i r

EE555ClEb77 LS npc 1 4.g 7, g fgfy Y CF T10c P

c a ynwi1a8 -,

u su r,c r n d'

2U55S 1

1 1

(