JOSEPH M. FARLEY NUCLEAR PLANT UNIT 1 NARRATIVE

SUMMARY

OF OPERATIONS  ;

MARCH, 1982 In the month of March, there were two (2) unit shutdowns. One automatic shutdown continued from last month and one manual shutdown was initiated on 3/10/82 for a maintenance outage. On March 27, while changing turbine control, a load transient occurred resulting in an increase in the pressurizer pressure. The increase in pressure caused a challenge to the pressurizer PORVs. The PORVs opened and following the decrease in pressure, the PORVs returned to the closed position.

The following safety-related maintenance was performed in the month of March:

i

1. Performed miscellaneous maintenance on diesel generators.

1

2. Repaired VCT letdown valve.
3. Repacked the ID service water pump.
4. Adjusted the packing on the "C" CCW Heat Exchanger Service Water Isolation Valve.
5. Repaired pressurizer liquid sample valve.
6. Repaired BIT "1A" recirculation pump.
7. Replaced ruptured disc on recycle evaporator.
8. Adjusted the packing on river water pumps #5 and #9.

i

9. Repaired the limit switches on all MSIVs.
10. Replaced the motor on H dilution fan IB.

2 i

l l

5 8204200137 820412 PDR ADOCK 05000348 R PDR

. = _ . _- .

o OPERATING DATA REPORT DOCKET NO. 5 0 'Q__.

l> ATE . 4/05/82 COMPLETED liY W.G. Hairston, III TELEPil0NE (205) 899-5156 OPER A IING STA I US

1. Unit Name: .To<:enh M. Frirley - tinit 1 Notes Cumulative data 1) t 2. Reporimg Period: March. 1982 since 12/01/77, date of
3. Licensed l hermal Power (MW ): 2652 commercial operation.

. 4. Nameplate Rating IGrow MWep 860

5. Design Liectrical Rating (Net MWeP 829
6. Masimum Dependable Capacity (Gross MWe): 844.6
7. Masimum Dependable Capacity (Net MWe): 803.6 H. If Changes Occur in Capacity Ratings (items Number 31hrough 7)Since Last Report,Gise Reasons:

N/A

9. Pemcr Lesel To Which Restricted,if Any (Net MWe): N/A
10. Reasons I or Restrictions. lf Any: N/A
i lhis Month Yr. to Date Cumularise ll. ilours in Reporting Period 744 2.160 37.968
12. Number Of Ilours Reactor was Critical 669.3 669.3 21,651.1
13. Reactor Resene Shutdown lionrs 26.4 26.4 3.518.4
14. Ilours Generator On-Line 567.5 567.5 20,897.2
15. Unit Rewne Shutdown flours 0 0 0
16. Crow Thermal Energy Generated (MWlO 1.254.038 1.254.038 52.198.949
17. Grow Liectrical Energy Generated IMWill 394t708 394,708 16,631,660
18. Net Electrical Energy Generated (MWil) 366.166 349,344 15.573.068
19. Unit Senice Factor 76.3 26.3 55.0
20. Unit Asailability Factor 76.3 26.3 55.0
21. Unit Capacity Factor (thing MDC Net) 61.2 20.1 51.0
22. Unit Capacity Factor 4Using DER Net) 59.4 _ _ _ . _

19.5 49.5

23. Unit forced Omage Rate 20.9 59.2 12.8
24. Shutdowns Scheduled Oser Nest 6 Months iIype. Date.and Duration of Each1:

N/A

25. If Shut Down A End Of Report Period. Esthnateil Date of Startup: N/A
26. Units in lest Staten (l'rior to Commercial OperationP forecast Achiesed INIII A L CRillCAll ry 8/06/77 g Isil:AL Etrc1RiCity COMMI.RCIAL OPER A IION 8/20/77 12/01/77 8/09/77 8/38/77 12/01/77 P)/77) g w. . -

m,m.

o .

, . DOCKETNO. 50-348 m.,

UNIT J . M. Farlev-Unit 1 DATI 4/07/82 COMPLETED BY W.G. Hairston, III TELEFl!ONE (205)899-5156 MONTil March -

DAY /.VERAGE DAILY l'Oh ER LEVEL ' DAY AVERAGE DAILY POWER LEVEL (MWe Net) (MWe Net) g, 0 17 710' 2 0 -

13 789 3 0 19 803 4 0 ;g 781 5 0 21 798 6 0 3 756 s 7 78 3 812 g 249 ;4 805 9 310 25 802 10 34. 26 808 11 109 n 804 12 315 ;3 814' ,

13 557 ;9 810 g.g 574 30 801 35 650 33 799 16  ; 663 .

lNSTRUCliONS On this form:t. list th- avenge daily unit power levet in MWe Net for each d:y in the reporting inonth. Compute to

, the neare:t whole nc;swatt.

9 w ., e

. (9(77) .

4*

f .

~

' ' ~ '

L

  • O 3 0 .

UNIT SIIUTDOWNS AND POWER REDUC 110NS DOCKET NO. 50-348 ,

UNIT NAME J . M. Farlev-Unit 1 DATE 4/05/82 COMPLETED BY W. G. Hairston, III REPORT MONTil March. 1982 TELEPif0NE (205)899-5156 w.

, ,$E };; $ Licensee Eg  % Cause & Corrective No. '

Date R 58 Es5 Event u? q Action to b

$= 5 j if; g Report a _

syc ju Prevent Recurrence 5

001 810910 F 150.1 A 3 NA EB GENERA Continued outage to repair damage to

  • the main generator which occurred September 10, 1981. Re fueling rescheduled to take advantage of l forced outage situation.  !

002 820310 S 26.4 1 B NA NA NA Maintenance outage. I 1

l l

l l

l l 2 3 4 F: Forced Reason: Method: Exhibit G -Instructions S: Scheduled A Equipment Failure (Explain) 1. Manual for Preparation of Data B Maintenance of Test 2 Manual Scram. Entry Sheets for Licensee C-Refueling 3-Automatic Scram. Event Report (LER) File (NUREG.

D-Regulato:y Restriction 4-Other (Explain) 0161)

E-Operator Training & Ucense Examination F-Administrative 5 G-Operational E:ror (Explain) Exhibit !- Same Source (9/77) ll-Other (Explain)