Georgia Power Company Post Office Box 4545
,Q{
Atlanta, Georgia 30302
- )
M O Telephone 404 522-6060 VOgtle Project Southern Company Services, Inc.
Post Office Box 262s Birmingham, Alabama 35202 19s / 'h Telephone 205 870-6011 April 5, 1982
/
b \\go).#
United States Nuclear Regulatory Commission 2
s..,
1 Office of Inspection and Enforcement L-e^k4
%
- c:j, Tlj$ h Region II - Suite 3100 J,
101 Marietta Street File: X7BG03-M22 5
8 Atlanta, GA 30303 Log:
GN-166
Reference:
Vogtle Electric Generating Plant - Unit'l and 2
'/s 50-424, 50-425 Leaks in Containment Cooling Coil Units Attention: Mr. James P. O'Reilly Gentlemen:
On March 4,1982 Georgia Power Company reported a potential deficiency to the Commission concerning some defective cooling coils in the containment coolers. Georgia Power Company is conducting an engineering evaluation to determine if the leaks could have prevented these coolers from performing their functional requirements. The engineering evaluation is scheduled for completion in mid-May.
Georgia Power Company expects to submit a final report to the NRC on this matter by June 4, 1982.
This reply contains no proprietary information and may be placed in the NRC Public Document Room.
Yours truly j
s D. O. Foster Project General Manager CWH/tlp xc:
U. S. Huclear Regulatory Commission Attn: Victor J. Stello J$
Office of Inspection and Enforcement go.
Washington, D. C.
20555 oo gg R. J. Kelly
- 0. Batum J. L. Vota o
R. E. Conway H. H. Gregory, III b
G. F. Head E. D. Groover o8 J. H. Boykin L. T. Gucwa 40 D. E. Dutton M. Malcom
- a:p s C 1 UN 7
D. L. McCrary C. R. Miles, Jr.
R. A. Thomas M. Manry m a.m J. A. Bailey R. W. Staffa 4 J2' t