Forwards Info Re Status of NUREG-0737,Items II.K.3.22 Re Reactor Core Isolation Cooling Section transfer,II.K.3.24 Re Space Cooling for Hpci/Reactor Core Isolation Cooling & III.K.3.27 Re Common Ref Level
ML20053E824
Person / Time
Site: Vermont Yankee File:NorthStar Vermont Yankee icon.png
Issue date: 06/04/1982
From: Jackson E
VERMONT YANKEE NUCLEAR POWER CORP.
To: Vassallo D
Office of Nuclear Reactor Regulation
References
RTR-NUREG-0737, RTR-NUREG-737, TASK-2.K.3.22, TASK-2.K.3.24, TASK-2.K.3.27, TASK-TM FVY-82-65, NUDOCS 8206100127
Download: ML20053E824 (3)


Text

-o

?

VERMONT YAN KEE NUCLEAR POWER CORPORATION SEVENTY SEVEN GROVE STREET RUTLAND, VERMONT 05701 FW 82-65 REPLY TO:

ENGINEERING OFFICE 1671 WORCESTER HOAD FR AMINGH AM. H ASSACH USETTS O1701 TELEPHONE 617 872-8100 i

June 4, 1982 1

U.S. Nuclear Regulatory Commission Washington, D.C.

20555 Attention:

Office of Nuclear Reactor Regulation Mr. Domenic B. Vassallo, Chief Operating Reactors Branch #2 Division of Licensing

References:

a)

License No. DPR-28 (Docket No. 50-271) b)

Letter, VYNPC to USNRC, FVY 82-61, dated 5/27/82 c)

Letter, USNRC to VYNPC, dated 3/17/82 d)

Letter, VYNPC to USNRC, FVY 82-1, dated 1/5/82 e)

Letter, VYNPC to USNRC, FVY 81-110, dated 8/5/81 f)

Letter, VYNPC to USNRC, FVY 81-69, dated 4/17/81 g)

Letter, VYNPC to USNRC, WVY 80-170, dated 12/15/80

Dear Sir:

Subject:

Post-TMI Requirements Reference (b) requested Vermont Yankee to submit the completion status of certain NUREG-0737 items. We submitted the status via Reference (c); however, we inadvertently omitted information regarding the status of three of those items. This information is attached.

We trust that this information is acceptable; however, should you have any further questions, please contact us.

Very truly yours, VERMONT YANKEE NUCLEAR POWER CORPORATION i

Earl W.

ackson Manager of Operations EWJ/dm 55YAEWO15%gg, (D

PDR

d.S. Nuclear Regulatory Commission June 4, 1982 VERMONT YANKEE NUCLEAR POWER CORPORATION Page 2 STATE OF VERMONT)

)ss WINDilAM COUNTY )

Then personally appeared before me, E.W. Jackson, who, being duly sworn, did state that he is Manager of Operations of Vermont Yankee Nuclear Power Corporation, that he is duly authorized to execute and file the foregoing request in the name and on the behalf of Vermont Yankee Nuclear Power Corporation and that the statements therein are true to the best of his knowledge and belief.

Diane M. McCue Notary Public My commission Expires February 10, 1983 k

M it l

l A

IWC

=

l

{

i i

l l

ENCLOSURE 1 Item II.K.3.22 - RCIC Section Transfer References (d) and (g)

The implementation of this item, as discussed in the above References, was complete ne of November 25, 1981.

Item II.K.3.24 - Space Cooling for HPCI/RCIC References (d) and (g)

As disussed in the above References, no modifications were necessary.

Item III.K.3.27 - Common Reference Level References (c), (f), and (g)

The impicmentation of this item, as dicussed in the above References, was complete prior to the startup following the 1981 refueling outage.