Second Interim Rept of Significant Const Deficiency 42 Re Hma Auxiliary Relays.Final Rept Cannot Be Provided by 820528 as Promised.Matl Will Not Be Shipped Until 820625.Final Rept to Be Submitted by 820806
ML20053E819
Person / Time
Site: Waterford Entergy icon.png
Issue date: 06/02/1982
From: Mclenden G, Mclendon G
LOUISIANA POWER & LIGHT CO.
To: Jay Collins
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION IV)
References
10CFR-050.55E, 10CFR-50.55E, W3K-82-0307, W3K-82-307, NUDOCS 8206100122
Download: ML20053E819 (2)


Text

..

LOUISIANA f,42OuAnONOcsmeu POWE R & LIG H T/ P O BOX G000

  • NEW ORLEANS. LOUISIANA 70174 * (504) 366-2345

'^ SI;UNEO ut

,.._ June _2, 1982 l.,i

/c :l ;,

, i O '-,

(}

..~:...:

g, g_ McLENDON I[);

Senoor Vice President

\\

& b$

'(

W3K-82-0307 Q-3-A35.07.42 Mr. John T. Collins, Regional Administrator, Region IV U. S. Nuclear Regulatory Commission 611 Ryan Plaza Drive, Suite 1000 Arlington, Texas 76012

Subject:

Waterford SES Unit No. 3 Docket No. 50-382 Significant Construction Deficiency No. 42 "HMA Auxiliary Relays" Second Interim Report Ref e renc e:

1) LP&L Letter W3K 82-0069 to the USNRC dated 2/5/82
2) Telecon - L. L. Bass (LP&L) to W. Crossman (USNRC) on 5/28/82

Dear Mr. Collins:

The referenced letter submitted an Interim Report to the USNRC in which LP&L committed to providing a Final Report on Significant Construction Deficiency No. 42 by May 28, 1982.

General Electric has notified Ebasco of a shipping date of June 25, 1982 for replacement material. Upon receipt of material, corrective action will be accomplished in accordance with GE Service Advice 721-PSM-166.1. Due to the lack of material, an extension of time is necessary. We anticipate a completion date of August 6,1982, at which time a Final Report will be submitted.

If you have any questions, please let us know.

Very truly yours, r

h GDMcL/LLB/grf

'+>

8206100122 G20602 DR ADOCK 0500039g PDR 1

Mr. John T. Collins Regiunal Administrator, Region IV cc:

1) Director Of fice of Inspection & Enforcement-U. S. Nuclear' Regulatory Commission Washington, D. C. 20555