TIIE CINCINNATI GAS & ELECTRIC COMPANY ss' -
CINCINNATI, OHIO 452o1 May 20, 1982
^
L A. BoROMANN SENeOR v*CE PRC580ENT U. S. Nuclear Regulatory Commission Region III 799 Roosevelt Road Glen Ellyn, Illinois 60137 Attention:
Mr. J. G. Keppler Regional Administrator RE:
WM. H. ZIMMER NUCLEAR POWER STATION - UNIT I 10CFR50.55(e) - ITEM M ASME STRUCTUAL ER:F & WELDER QUALIFICATION - DOCKET NO.
50-358, CONSTRUCTION PERMIT.NO. CPPR-88, W.O.
- 57300 JOB E-5590 FILE NO. NRC-8, M-34 Gentlemen:
This letter constitutes an interim report to the subject condition initially reported as a potentially reportable deficiency under 10CFR50.55(e).
Our previous report, QA-1699, dated April 14, 1982, stated that welders were qualified to the test requirements of H. J. Kaiser Co., procedure SPPM 3.1.51.
Contrary to the requirements of the ASME Section IX, 1971 thru 1973 Winter Addenda, welders were qualified only in two positions, vertical (3G) and overhead (4G). The Code states that qualification in the horizontal (2G),
vertical, or overhead position shall qualify-also for the flat position.
Qualification in the horizontal fixed position (5G) shall qualify for the flat, vertical and overhead positions. Qualification in the horizontal, vertical and overhead positions shall qualify for all postions. Qualification in the inclined fixed position (6G) shall qualify for all positions. Thus, several welders were not qualified to weld in the positions required to make several welds on the sacrificial shield.
In our last report we identified an ongoing investigation that was underway to resolve the deficiency and determine a resolution. The intent of the investigation was to determine if the welders could be qualified on production velds. As a result, another potentially reportable Item, M-49, was discovered and identified that a random review of radiographs, in the area where these welders performed, had identified discrepancies in the interpretation and records G206040125 820520 b
PDR ADOCK 05000358 8
0)
S PDR MAY 2 8 E62
o.
e Mr.-J. C. Keppler Regional Administrator U. S. Nucicar Regulatory Commission Region III n',y 20, 1982 - QA-1772 -
3e 2
.. the radiographs. Evaluation of this potential deficiency in radiography
.1 delay resolution of the welder qualification issue. The investigation into this deficiency is continuing and a final report shall be submitted by July 31, 1982.
We trust that the above will be found acceptable as an interim report under the requirements of 10CFR50.55(e).
Very truly yours, THE CINCINNATI GAS & ELECTRIC COMPANY By E. A. BORGMANN SENIOR VICE PRESIDENT KRS:as cc: NRC Resident Inspector Attn:
W. F. Christianson NRC Office of Inspection & Enforcement Washington, D.C.