ML20053C706

From kanterella
Jump to navigation Jump to search
IE Insp Rept 50-460/82-04 on 820222-26.Noncompliance Noted: Recording of Wrong Welder Identity,Failure to Document Corrective Action for Suspect Weld Electrodes & Changing Weld Specs W/Memo & QC Acceptance of Incorrect Butt Welds
ML20053C706
Person / Time
Site: Washington Public Power Supply System
Issue date: 05/17/1982
From: Dodds R, Narbut P, Powers E, Shackleton O, Toth A
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION V)
To:
Shared Package
ML20053C691 List:
References
50-460-82-04, 50-460-82-4, NUDOCS 8206020484
Download: ML20053C706 (16)


See also: IR 05000460/1982004

Text

.

U. S. NUCf. EAR RECUL\\ TORY C0!!MISSIO?T

.

y

RECIO!i V

Report No. 50-460/82-04

'

Docket No. 50-460

License No.

CPPR-134

Safeguards Group

Licensee: Washington Public Power Supply System

P. O. Box 968

Richland, Washington 99352

Facility Name: Washington Nuclear Project No. 1 (WNP-1)

.

Inspection at: WNP-1 Site, Benton County, Washington

Inspection conducted:

February 22-26 and March 2-12, 1982

Inspectors:

C%

f~

[ 72-

P. P. Narbut, Reactor Inspector

6 ate' S igned

R 3Mk

s/wlse

A. D. Tot , Senior Resident inspector

Date Signed

-

S f/l,4l Q,

-

Le

O. Cdhackleton, Invey igator

' Date' Signed

f/4kV

hw. -0

ferd

E. J( Power,A nvestigator

Date Signed

A 2 &&

s/n/ccu

R.'O. Dodds, Chief, Reactor Project bection 2

date Yigned

~

Reactor Construction Projects Branch

Summary:

'

-

Inspection during the period of February 22-26 and March 2-12, 1982.

i

l

Areas 'nspected:

The inspection was an investigation of allegations made

l

regarding the Heating Ventilation and Air Conditioning (HVAC) contractor,

University Nuclear Systems Inc. (UNSI). The inspection involved 288 inspector

j

hours onsite and 34 inspector hours in office by two NRC inspectors and

two NRC investightors.

Results: Four items of noncompliance were identified concerning recording

the wrong welder identity, 'not documenting corrective action for suspect

weld electrodes, changing weld procedure specifications with a memorandum

j

and QC acceptance of butt welds which were required to be fillet welds.

,

These items are discussad in paragraphs 2.c., 2.e., 2.i. and 3.a. respectively,

t

I

i

RV Form 219 (2)

S206020484 820517

i

- - . PDR ADOCK 05000460

G

PDR

ll_

'

1

~-

. , . . , - , _

, , . - - -

. , - -

-~

,

-

. . , - - - . . . -

,,y

-._

.m_

,~~

_

'

.

.

.

'

DETAILS

1.

Persons Contacted

)

a.

Washington Public Power Supply System (WPPSS)

  • D. W. Mazur, Program Director
  • C. B. Organ, Assistant' Program Director, Engineering

-

+*C. R. Edwards, Project Quality Assurance Ma n ager

-

+*W. Root, Assistant Program Director, Construction

.

  • F. C. Hood,' Construction Manager

.

  • L.'J. Garvin, Manager, Quality Performance and Measurements

.

.+*G. K.,Dykeman, Design Engineering Manager

+*M. E. Rodin, Senior QA Engineer

+*M. J. Farrell, QA Engineer

+ N. S.' Porter, Manager of Systems Engineering

.

+ R. C. Mertens, Senior QA Engineer

+ R. Glasscock, Director of Quality Assurance

b.

Bechtel Power Corporation (Bechtel)

+*D

R. Johnson, Manager.of Quality Assurance

+*J. Gatewood, Project Quality Assurance

+*T. Fallon, Project Quality Control Engineer

+*G. A. Hierzer, Field Constructior Ma nager

+*M. A.' Norm, QC Engineer

+ J. Ruud, QA Engineer

+ E. W. Edwards, Project Manager

c.

United Engineers and Constructors (UE&C)

+*E. C. Haren, Project Quality Assurance Manager

+*G. L. Faust, FSQA

+ K. J. Iverson, Manager Construction Services

d.

University Nuclear System Inc. (UNSI)

_

+*R. Canipe, Corporate QA Manager

j

+*S. Cohen, Project Manager

+*B. Sachs, Project QA/QC Manager

  • Attended exit interview of February 26, 1982.

+ Attended exit interview of March 12, 1982.

!

,

..-

_.

. . .

-

-

,_

.

.

.

,

9

,

-2-

,

2.

Allegations against UNSI

On February 1,1982 the regional office received allegations against

the Heating Ventilation and Air Conditioning (HVAC) contractor, University

Nuclear System Inc. (UNSI), Contract 216. The allegations were pursued

during the weeks of February 1-5, February 22-26, and March 2-6 and

.

8-12, 1982.

In addition to the allegations initially received, additional

allegations and items considered worthy of-followup were received

as a result of interviews and investigations conducted. The allegations

and items are listed below with the NRC findings.

a.

Allegation: A foreman was fired because he refused to falsify

documents associated .;ith hangers.

Finding: The conclusions regarding the specific allegations will

De documented separately by the NRC investigative staff.

The underlying issue, that craft foremen were asked to sign off

work without looking at it, was substantiated.

The inspector examined the in-process inspection records (IPI's)

for the control room ducting, drawing 4586-1. There were a total

of 76 IPI sheets generated, with et.ch sheet having up to 8 items

signed off.

50 of the sheets had items which had been signed

off by different foremen within a three day period of January

6, 7 and 8, 1982. Eleven foremen were involved in the sign offs.

Nine of the foremen had a reasonable number of sign offs per day;

that is, approximately 8 to 11 items signed off per day. Two

of the foremen had an extraordinarily high number of items signed

off per day. One foreman had 77 items in one day and 49 items

the next day. The other of the two foremen had 39 items signed

off on one day.

,

An " item", as used above, is a unit of work accomplished. Typical

examples of " items" are:

" Install duct, 9092-175" and "All work

complete, 9805-78." The applicable procedure QCP/CP-27.0 states

the installation foreman is responsible to enter all appropriate

data on the IPI as work is performed.

If the item is complete,

the final column is to be initialed and dated. No IPI is to be

" torn apart" and distributed until the responsible foreman has

signified acceptability for all work performed by placing his

'

initials and date in the IPI work column.

The very high number of items signed off by the two foremen indicates

that they did not personally verify the work items were done, which

is an implicit requirement of the procedure.

The licensee's construction management personnel (Bechtel) responsible

-

for the UNSI contract stated that, in their opinion, the procedure

,

does not require craft foremen to personally verify work is done.

,

?


H

, - - - ,

.

-3-

The construction management's interpretation of the procedure

is basea on the absence of the words "shall personally verify".

The sign offs in question are not classified as " falsification"

because of this procedural interpretation.

The issue of circumvention of the intent of the procedtre was

discussed with licensee management at the exit interview.

The final hardware safety significance of this item is considered

minor on the basis that QC personnel subsequently inspected the

items prior to their sign off. The adequacy of QC inspection

is discussed further in paragraph 3.a. of this report,

b.

Allegation: ~ Documentation.is not being done in a timely fashion.

~

Finding: The lack'of timely documentation is a previously known

problem'(see Inspection Report 50-460/81-09).

No further examination

of.this problem.was performed during the current inspection.

,.

c .,

Allegation:

A~ welder's number was used on unmarked welds even

' -ttough they (the foremen) didn't know if the welder did those

welds. The applicable drawing is DH 4586 Sheet 1 and 2.

,

'Firiding: The al]egation was substantiated. The inspector examined

all of the IPI's for the control room for drawing DH 4586 Sheets

1, 2 and 3 and identified the work items charged to the welder

-

in question. Qual sty records indicate that on January 19, 1982

the welder's welding certifications were withdrawn. Discussions

s

with the welding foreman and the QC superintendent indicated the

, elder's work was bad, and that a lot of his work was required

w

to be ground out and rewelded by others. The inspector examined

records of work accomplished January 18-19, 1982 where the welder

was credited with welding in the control room. The IPI's show

him as the welder of record for eight items on IPI 5546. The

eight items involve the installation of duct branch take off stiffeners

per EAF numbers IE 1766 and IE 1964. The inspector examined voided

IPI's and determined the welder had been listed as performing

welding on an additional 17' duct branch take off stiffeners for

a total of 25 assemblies.

The inspector estimated that approximately 100 filler metal electrodes

would ordinarily be used to weld the 25 assemblies, but, possibly

the job could be done with 75 electrodes if the welder used his

partially burned stubs. The welding foreman concurred with this

estimation. Examination of all filler metal withdrawal slips

credited to the welder for the month of January 1982 showed the

welder used only 26 electrodes.

The inspector, therefore, concluded

the welder could not have performed welding on the 25 assemblies

for which he had been credited.

.

. -

-

- -

-

.

.

.

.

,

9

.

.

-4-

,

The inspector interviewed the foreman who had listed the welder

as having performed work on the 25 assemblies. He stated that

at the time his -job was to fill out the paperwork, that he did

not have direct responsibility for supervising a production crew.

He used the welder's number for the 25 assemblies based on conversations

with foremen, the general foreman and the welder. He further

stated that at the time of the sign offs in January, he had not

been trained regarding how the paperwork was to be completed.

The failure of the installation foreman to enter appropriate data

on the IPI as work is performed as required by QCP/CP 27.0 Revision 9

dated M a y 11, 1981, paragraph 6.1 is an apparent item of noncompliance.

(EnforcementItem 50-460/82-04/01)

Related to this item, the inspector learned that the licensee

had received an allegation through their. hotline program on October

20, 1981 which dealt with, among other things, the subject of

" arbitrary assignment of a (welders) name to a weld." The same

information had been provided to UNSI management on. September

10, 1981. The construction manager, Bechtel, conducted the investigation

en November 17, 1981 and concluded that they were not able to

substantiate any irregularities, but, would request UNSI to take

corrective action. On December 11, 1981 a memorandum to.the Program

Director was issued stating " corrective action where found necessary

has been implemented and a daily and/or weekly check will be made

by Bechtel." On December 24, 1981 another memorandum to the Program

D i rector was issued stating "Bechtel conducted a daily surveillance

...and did not detect a generic welder identification problem.

UNSI will revise their procedure...to require independent welder

identity verification, this will strengthen the UNSI welder identity

program and provide a high degree of assurance that proper identification

is achieved."

It is of concern that, despite notification to the contractor

and the licensee regarding this problem and the subsequent investigation,

the contractor's construction foremen were not apparently informed

of the problem and, as of January 1982, continued to inaccurately

record welder identification numbers.

This lack of feed'ack to

first line personnel was discussed at the exit interview.

d.

Allegation: Welds that are obviously bad were accepted in the

1979-1980 time frame. Such welds can be found on elevation 421,

see ET 73831 Sheet 1.

Undersize welds are located on elevation

501, see Drawing 4368 Sheet 2.

Finding: The problem of inadequate weld inspection is a known

condition and has been discussed in previous inspection reports.

This problem is currently being carried as an open followup item

(no. 81-06-08). The licensee has committed to perform a 100%

reinspection of all welds. No further examination of this problem

was performed during this inspection. The current adequacy of

weld-inspections is discussed in paragraph la of this report.

.

'

.

.

-5-

e.

Allegation: There was a weld filler metal withdrawal slip forgery

on December 2, 1981.

F_inding: The allegation was substantiated. The forgery was identified

through the contractor's quality assurance system but the matter

was never fully resolved.

The filler metal slip in question is dated 12/2/81 for welder

number 3680 and shows fifteen E 7018 electrodes were issued at

3:29 p.m. and returned at 8:00 p.m.

The 8:00 p.m. time is lined

out and 7:00 p.m. is written in with the initials "EVB".

During the regular QC surveillance of welding filler metal control

on December 2, 1981, the QC inspector determined and stated in

his inspection report that " Welder ID 3680 had E 7018 weld filler

metal out over the 4 hour4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br /> maximum by 31 minutes.

Initials of...

the filler metal attendant wer e forged by. party unknown changing

the time from the correct 8:00 p.m. to 7:00 p.m."

The surveillance report was forwarded by a " speed memo" from the

. inspector to the contractor's QA Manager on December 3, 1981.

On February 2, 1982 speed memo no. 14297 was written by a welding

QC-inspector to the welding QC supervisor stating the original

filler metal withdrawal. slips had been returned and requesting

what actiontshould be taken. The memorandum reply stated to file

the filler metal slips.

-

'

fat;thetime~ofthe'currentinspection,theNRCinspectorfound

~

the original weld' filler metal withdrawal slip in the permanent

file with the forgery unco r rected. The inspector found no evidence

~

that the hardware welded by welder 3680 on December 2,1981 had

been evaluated for acceptability.

' The NRC inspector also examined QCRFI's as reported in paragraph

Sa. of this report. One of the requests for information (RFI)

was number'433 dated December 10, 1981 which dealt with weld filler

metal withdrawal slips which indicate E7018 electrodes were not

returned within 4 hours4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br />. Fourteen filler metal slips were identified

in a period that covered August 17,~1981 to September 4, 1981, 3 weeks.

The inspector and the contractor's QA manager attempted to. locate

the 14 listed weld filler metal withdrawal slips. Only'one could

be loc ated, weld filler metal withdrawal slip of August 21, 1981

for welder 4537 which showed E7018 electrodes had been out for

54 hours6.25e-4 days <br />0.015 hours <br />8.928571e-5 weeks <br />2.0547e-5 months <br />. The slip showed the time circled but no indication

that the work done by welder 4537 on August 21, 1981 had been

evaluated for acceptability.

The QA Ma nager stated that the missing filler metal slips were

probably filed separately but would not show whether the hardware

affected had been evaluated. He stated it appeared that UNSI had no system

,

.

.

_

-

-

.

'

.

'

W..

  • ~

.

-6-

'

-

,

.

.for-correcting filler metal withdrawal slips discrepancies. The QC

inspector'_s request on QCRFI No. 433 had stated in part "A definitive

method of' correction limits and criteria should be forthcoming

to all . applicable personnel to set guidelines for correction of

weld filler metal withdrawal slips."

~

The QA Manager's reply, QA memorandum QA 646 of January 11, 1982

stated in response " Corrections to Quality Class 1 documentation

are allowed as described by QCP/CP 5.1, QA Records, paragraphs

5.6.1 and 5.6.2 and therefore no code or procedural violations

exist."

Paragraph 5.6.1 and 5.6.2 of QCP/CP 5.1 state in part:

"For changes made due to error or oversight, a line shall be drawn

through the original information, and the new information shall

be entered adjacent to the original information and initialed

and dated by the perscn making the change. A written justification

shall be added to each change when the reason is not otherwise

apparent.

If supplemental, new, or corrective information needs to be added

to a QA record, due to error or omission, and there is insufficient

room on the record, a Records Clarification Form shall be used.

In utilizing the Records Clarification (RC) form to complete record

deficiencies, a written justification for each change shall be

prepared where the reason for clarification is not readily apparent.

If the required information is inadequate or has not been provided,

a Document Deficiency Notice (DDN) shall be issued.

If the required

information is not provided within thirty days of the DDN issue

data, a CNCR shall be written against the document deficiency (ies)."

The failure to correct safety related records in accordance with

QCP/CP 5.1 and the failure to evaluate safety related hardware

welded with low hydrogen E 7018 welding electrodes which exceeded the

allowable usage time of 4 hours4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br /> is an apparent item of noncompliance

(Enforcement Item 50-460/82-04/02).

f.

A]]egation: Two welders were never qualified. The welder's names

were provided.

Finding: The allegation was not substantiated. The NRC inspector

examined the qualification records and the work performance records

and found the welders were qualified during the periods that they

welded. The allegation apparently stemmed from the fact that

the record copy of the welder certification was not signed by

the documentation supervisor until several months after the certification

was put in effect. The inspector interviewed the documentation

.

,

-7-

.

supervisor who stated he had signed the typed official permenent

record on the basis of reviewing the hand written copy of the

certification which was signed by the welding examiner. Since

the welding examiner had lef t the site, the documentation supervisor

signed for him and dated his signature with the date on which

he performed his signature,

g.

Allegation: Drawings were withdrawn-from the field because base

plates didn't meet drawing tolerances.

-

Finding: The allegation was a correct statement but does not

represent a significant safety concern.

Drawing DH-4500, Sheet 8, Revision 0, had been in use in the field

and had location tolerances (+3") for certain items. Revision

4 of the drawing had been approved by UE&C for contractor use

but contained comments regarding areas of the drawing which had

not been submitted for revision approval. One of these comments

changed the location tolerances for certain items from 3 inches

to lh inches.

Revision 4, with the comments incorporated, was

issued to the field for use and caused concern since much of the

hardware had already been built to the looser tolerances. The

contractor's QA manager had Revision 4 withdrawn from tte field

and wrote a memorandum, 216-BEC-82-0054 of February 17, 1982 requesting,

essentially, that UE&C evaluate the necessity of changing the

location tolerances on equipment which hed been fabricated since

rework was involved.

In the case where approved drawing tolerances were not achievable,

it would have been more appropriate for tre contractor to use

the established request-for-information (RFI) system or nonconformance

report system, rather than issue a memorandum. The use of memoranda

is further discussed in paragraph 2.i.

The drawing control implementation

l

of withdrawing revision 4 of the drawing from the field is discussed

in paragraph 3.b.

h.

Allegation: A memorandum was issued on how to measure welding

machine wire feed speed which violates procedure requirements.

!

Finding: The allegation was substantiated. Quality control request

l

for information (QCRFI) number 462 was written on January 29,

1982 regarding how quality control should verify wire feed speed for the

"Cobramatic" feeder monitors. The general welding standard QCP/CP-22.0

Revision 7 paragraph 6.4.5 requires quality control personnel to verify

wire feed speed on Attachment 6 to the procedure. Wire feed speed is the

rate at which welding electrode wire is fed to the welding torch.

'

l

'

The response to the QCRFI is a memorandum by the welding QC supervisor

(number 9929 of February 3, 1982) which states to measure the

inches of weld deposited per minute and record that as tne wire

feed speed.

i

.

.

-8-

This is an inaccurate method of measuring wire feed speed since,

with the same wire feed speed a welder can deposit widely varying

inches-per-minute of weld deposit depending on the size of the

weld pass he chooses to make. The use of this method is considered

to be contrary to the requirements of the procedure.

The subject of using memorandum to change procedure requirements

is discussed further in paragraph 2.1. bElow.

i.

Allegation: Memoranda are still being used in lieu of procedures.

Finding: The allegation was substantiated.

Background: On January 27, 1981 the Program Director had issued

a letter which was directed to all site contractors (letter WPUE-

-

81-048). The letter stated in part"...it's absolutely essential

that our field personnel provide us the assurance that procedures

are being followed and so verified. There is no latitude for

deviation. Contractor Management is encouraged in a parallel

fashion to seek procedure relief as is appropriate but not at

the expense of procedure adherence." In September of 1981 the

licensee was issued an item of noncompliance because memorandum

were being used in lieu of approved proced"res to perform quality

related work. The licensee's response to this item of noncompliance

(WPPSS letter G01-81-424 of December 23,1981) stated in part

that, "...all site contractors who perform quality affecting activities

are being reinstructed that speed letters or memoranda cannot

be used in lieu of approved procedures, or in advarice of procedural

changes, all quality work must be accomplished in accordance with

approved procedures." Also on December 23, 1981 the UNSI Project

Manager and QA Manager issued memorandum QA 617 to all UNSI supervisory

personnel which stated in part that no work affecting quality

shall be performed to speed memos or verbal directior which does

not agree with approved procedures."

Current Allegation: The NRC inspector examined the memorandum

files of=the contractor's QA manager and the Assistant QA manager

for the period from September 1981 to the most current memorandums.

These files were not necessarily complete since memoranda are

not a contrclled document and individuals file only what they

deem necessary.

,

'The inspector found one additional memorandum which resulted in

deviatio'n from established requirements, The memorandum, from

the General Superintendent to all field supervision, (number 23670

of, January 27, 1982)' states that the material thickness limitations

,

giv'en in the specific weld procedure specifications (WPS's) apply

e

^

to groove welds only.and that fillet welds may be made using any

WPS_for khich "the essential variables apply WITHOUT REGARD TO

MATERIAL THICKNESS."

,

,

,

-

+

e

'

.

-9-

Preceeding that memorandum, the General Superintendent had written

a memorandum on January 19, 1982 to the QA Manager requesting

concurrence to that policy. The QA Manager concurred to tre

memorandum (concurrence not dated) and his response stated in

part "WPS revision is not required."

The memorandum was generated (per the statement of the General

Superintendent) because the WPS's, as written, weren't adequate

for some fillet welding of thinner members, namely the current

ranges weren't adequate. When this problem was brought to the

engineering department for WPS changes, the memorandum approach

was chosen instead, which allows the welder to select the amperage

range desired from a selection of weld procedure specifications

regardless of base. material thickness range. However, this also

allows the foreman or welder to select a WPS for which the electrode

size, travel speed, preheat or heat input may be inappropriate.

In the inspector's opinion, the decision to allow welders or foremen to

choose a WPS which provides an adequate current and for which "the essential

variables apply" places an unrealistic reliance on welder's or foremen's

_

knowledge of the welding code's " essential variables".

The failure to accomplish activities affecting quality in accordance

with documented instructions which prescribe the activities is

' considered a repeat item of noncompliance.

(Enforcement Item

L50-460/82-04/03)

A similar situation where a memorandum was used to change a procedure

requirement is discussed in paragraph 2.h. above. However the

safety significance of that memorandum is not considered sufficient

to warrant an item of nor. compliance.

j.

Allegation: An Engineering Action Form (EAF) was being used

in the field for work on Hilti bolt (concrete expansion anchor)

installation. The EAF violates the Hilti bcilt installation procedure.

Finding: The allegation was substantiated, but is not a safety

concern.

The inspector reviewed EAF No. IE2721 dated January 21, 1982

and the normal Hilti bc.lt installation procedure QCP/CP 33.0.

The EAF stated that Hilti Kwik bolt installation requirements

had been revised per a specification change. The EAF transmitted

the new requirements on an interim basis until QCP/CP 33.0 could

be revised. The EAF stated it would become void upon the revision

of QCP/CP 33.0.

Although the requirements of the EAF differ from that of the

procedure, the action to issue the new requirements is understandable

1

.

.

'

.

'

.

-10-

in terms of getting revised UE&C requirements in the field as

quickly as possible to minimize rework. UNSI can issue EAF's

without UE&C concurrence.

Revisions to QCP/CP's require UE&C

concurrence or a waiting period of 15 working days whichever

comes first before the procedure revision can be issued to the

field. There appeared to be no technical problem with the EAF

since it was interim in nature and invoked a UE&C approved specification

change. This item was discussed with -licensee management at

'

the exit interview.

k.

Allegation: Five to fifteen welders welded after the expiration

of their weldirig certifications.

Finding: The allegation was not substantiated. The NRC inspector

sampled records of several welders in the mid-1981 time frame.

Na records of welding after expiration of certifications were

found. The inspector noted that welder certification records

and welder performance records in that time frame appeared discrderly

and poorly organized and maintained. The records generated since

mid-1981 have greatly improved and are currently orderly and

required information can be systematically retrieved.

+

1.

Allegation: 'There'is no procedure for voiding IR's (Inspection

Reports) and'CNCR'.s (Contractor Non Conformance Reports).

Finding: The allegation was substantiated, but is not a safety

concern.

The NRC inspector examined the irs written for November and December

1981 and January and February of 1982. Although there is no procedure

for how to void an IR or CNCR, all the voided irs reviewed were

voided with an initial and date and in all cases but two, the

reason for voiding was recorded. Voided irs are retained for

the record.

The personnel ir.terviewed stated their intent was

to record a reason for all voided IR's.

The inspector reviewed

the rationale for each of the voided IR's and found it to be reasonable

in each case.

At the exit interview licensee management stated they would consider

changing their procedure to specify how IR's and CNCR's should

be voided.

This item will be inspected further in a future inspection.

(Followup Item 50-460/82-04/04)

3.

Additional inspections related to allegations

a.

Quality Control Inspection Accuracy

.

.

-

,

.

il

-

.

\\

.

-11-

f

The NRC inspector examined a sample of duct and hanger installations

in the control room against the requirements of UNSI Drawing

,

-

DH-4586 Sheets 1, 2.and 3.

Sheet 1 Section "C-C" shows the installation

'

of six inch diameter round duct take offs from the main duct.

Two horizontal lh inch x 1

inch x k inch reinforcing angle iron

-

bars.are shown to be installed to existing vertical members with

,

~

h . inch fillet welds, lh inches long. The vertical location of

'

the round duct take off assemblies on the vertical face of the

main ducts was not provided by the drawing information.

The NRC inspector observed that the horizontal angle iron was

installed with butt welds in lieu of the specified fillet welds.

This. condition was noted throughout the control room.

These welds had been final inspected and accepted by QC personnel.

Examples of final QC' acceptance on these welds are shown on IPI

5546 where'eight assemblies were accepted. Tv,o different inspectors

were involved in the inspection of iteme so the problem does

not appear to be confined to a single inspector. The items signed

off as acceptable and the dates were:

9087A-253 on January 21, 1982

9087A-254 on January 21, 1982

i

9087A-249 on January 21, 1982

9087A-433 on January 21, 1982

9087A-443 on January 21, 1982

9087A-421 on January 21, 1982

9087A-399 on January 19, 1982

9087A-171 on January 19, 1982

The NRC inspector interviewed the two QC inspectors involved.

They stated they had reviewed the drawing prior to performing

the inspection but did not take the drawing to the work at the

time of inspection. They did not note the absence of a vertical

locating dimension for the assembly on the duct nor did they

note butt welds had been installed in lieu of fillet welds.

Paragraph 6.7.1 of QCP/C0 No. 27.0 states in part that the QC

inspector shall assure that each item is installed in the proper

location and is the configuration specified by the applicable

drawing.

The failure to assure that the six inch round duct take off were

installed in the configuration specified by the drawing is an

apparent item of noncompliance.

(Enforcement Item 50-460/82-04/05)

The failure to note the absence of a vertical locating dimension

for the duct take off is not considered to have sufficient safety

significance to warrant an item of noncompliance.

The NRC inspector noted that another QC inspector had observed

that the drawing specified installation of stiffeners with filtet

welds was inappropriate since the weld joint configuration as

.

'

.

'

~

< _12_

drawn was actually a' butt joint and identified the deviation in

an ins'pection report IR-216-69 dated February 9, 1982.

b.

Drawing Control

Paragraph 2 9 of this report discusses an allegation regarding

Drawing DH 4500. Sheet 8, Revision 4 which was withdrawn from

the field because location tolerances had been changed and Revision 0

was to be reinstated. The resident inspector examined the crawing

control implementation of this action and found the following

conditions at different drawing stations:

1)

The UNSI procedure QCP/CP-5.2 Revision 0 dated July 16,

1981 in paragraph 5.3.7 requires that " Drawings in the field

identified as For-Information-Only must be separated from

.,

contract. drawings in a separate file."

It also describes

document control.

,

(a) GSB Elevation 519' Foreman Work Station

A memo (Sachs/Dixon-Bertsch BLS-261 dated 1-12-82,

  1. 16691) prescribed " reissue DH4500 Sheet 8 Revision 0

to the field. Revision 4 to drawing DH-4500 Sheet 8

is not released and is to be removed from the field."

The acknowledgement on the same memorandum states that

t

" Effective this date, Contracts / Document Control shall

comply with the body of your memo and implement removal

_

of this drawing from all ficld print stations...."

Drawing DH4500 Sheet 8 Revision 0 was available at

the work station.

It was marked " CONTROLLED", but

the drawing set was not identified.

Dr a wing DH4500 Sheet 8 Revision 4 was available at

the work station, but its title block had been torn

off. There was no marking of "V0ID", nor " CONTROLLED",

nor "INFORMATION ONLY".

A partial drawing was available at the work station;

it was marked in pen "DH4500-8".

It consisted of the

"End Plenum Base Dimensions" tabulation, ostensibly

/

a duplicate of that portion of Drawing DH4500 Sheet 8

Revision 4

There was no revision number noted, nor

marking of "V0ID", nor " CONTROLLED"; nor "INFORMATION

3

ONLY".

(b) GSB Elevation 519' QC Work Table

Drawing DH4500 Sheet 8 revision 0 was available at

'

the QC table.

It was marked " CONTROLLED".

,

,

!

i

s

.

_.

_

_

_.

.

.

'

.

-

,

,

'

-13-

.

(c) Central Weld Material Issue Room at Elevation 479'

The Drawing Log dated March 1, 1982 (which is updated

each week).showed a notation against drawing DH4500

Sheet 8, in that " Revision 4 was pulled from field

2-12-82 per memo BCS-261".

The Welding Filler Metal Withdrawal Slips Nos. 6873

and 6874 (dated 3-3-82) showed assignment of weld material

to drawing DH4500 Sheet 8 Revision 4.

The "4" was

circled, and the general foreman for the issue room

said that this had been identified as incorrect and

the responsible work foreman had been notified the

previous day.

(d) QC Document Control Trailer East of the GSB

!'

The QC working file contained DH4500 Sheet 8 Revision 4

It did not contain Revision 0.

The drawing control problems at the foreman work station and

at the QC document control trailer indicated that document control

within UNSI may be a problem.

This item will be inspected further in a future inspection.

(Followup Item 50-460/82-04/06)

c.

As Built Location Tolerances

i

The inspector examined the status of as-built drawings at UNSI.

At the time of inspection, as-built drawings were not yet being

generated by UNSI, since the as-built drawing procedure had not been

issu e d.

UNSI had received contract specification 9779-216 Revision

!

124 dated February 8, 1982 which revised as-built drawing requirements..

The inspector noted that the equipment location tolerances in

the specification revision, which represents the as-built location

accuracy, had greater latitude than the installation tolerances

used in the original erection as specified in the duct standards

.

drawing 604900.

The inspector interviewed the applicable designer supervisor

and was unable to conclusively determine which tolerances would

be used in design verification analysis.

This item will be inspected

further in a future inspection.

(Followup Item 50-460/82-04/07)

5.

Licensee Action on Previously Identified Items

,

.,.

, . _ . , ,

- - -

_

. _ - - . _ , . -

.

.

.-_

..

-

_

. . _ _.

_.

- - - .

-

..

..

.

'

.

-14-

'

a.

(0 pen) (50-460/81-07-06) Followup Item: Quality Control Requests

for Information (QCRFI's) are not answered in a timely fashion.

l

The inspector examined the licensee's action taken on this item

'

up to the date of the inspection. The licensee had not completed

their action on this item.

UNSI had changed the procedure QCP/CP 39 Revision 2 of January 12,

1982 to require the QCRFI's be answered within five working days

of receipt by Quality Assurance. The construction manager, Bechtel,

had closed the item based on the issuance of this revised procedure

requirement.

The licensee's QA organization had initiated an

audit of implementation of the revised procedure, sampling QCRFI 400 of

October 20, 1981 to 4E0 of January 8, 1982. They found that essentially

all QCRFI's were answered in a timely manner but 14 of the 50 sampled

did not have answers filed in the QCRFI file. The inspector examined

the 14 QCRFI's which originally did not have answers in the file

i

and the answers which were obtained. The answers to the QCRFI's

reviewed were considered reasonable with the following exceptions:

1)

QCRFI No. 433 of December 10, 1981 deals with low hydrogen

weld filler metal being returned to the rod room after the

4 hour4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br /> maximum time limit. This item is discussed fully

in paragraph 2.e. of this report. The answer to this QCRFI

was inappropriate in the inspector's opinion in that the underlying

,

problem was not resolved and the weld rod withdrawal slips ard

'

affected hardware were not examined for acceptability.

2)

QCRFI No. 424 of November 24, 1981 stated that a practical

welding problem existed in the field. Galvanized k" thick

angle iron had to be ground to remove the galvanizing prior

to welding resulting in thicknesses somewhat less than the

nominal

In many cases the duct standards require k"

"

.

fillet welds be made to the less than " thick angle iron.

UNSI Engineering posed the problem to UE&C by Contract Waiver

Request (CWR) No. 218 of January 8, 1982. UE&C responded

that, due to design requirements, the weld thickness ceuld

not be reduced and that the weld should be brought out to

full weld thickness.

The UNSI engineering response to the QCRFI dated March 9,

1982, Speed Memo No. 11946, stated that UE&C had not approved

the CWR but that the AWS code states the weld size need not

exceed the thickness of the thinner part.

..

i

, . . .

'

.

'

.

-15-

This answer appears to be contrary to the UE&C answer.

The UNSI engineering answer goes on to state that UNSI submitted

a letter to AWS, dated March 10, 1982, requesting clarification

of the AWS fillet weld details.

Specifically UNSI requested

an interpretation that when a weld throat size equivalent

to a k" fillet weld is obtained with one leg being shcrter

and the other leg being longer than h", then an acceptable

" weld has been achieved.

It appears that the RFI answer is insufficient since, although

it describes actions that may eventually resolve the problem,

it does not instruct the QC inspector on what actions should

be taken for ongoing work, and seems to suggest that welds

less than \\" are acceptable. Additionally, the UE&C answer

to the CWR appears inappropriate since the answer does not

resolve the practical field installation problems and simply

restates the requirement without ensuring a practical solution

will be achieved. An additional example of an inappropriate

QCRFI' answer is discussed in paragraph 2.h. of this report.

QCRFI 462 of January 29, 1982 dealt with a question on how

to measure wire feed speed for a MIG welding machine.

Thisitemremainsopenandwilibeinspectedfurtherduringa

future inspection for timeliness and appropriateness of QCRFI's.

6.

Exit Interview

,

The persons, identified in paragraph 1 met with the inspector on the

. dates indicated in paragraph 1.

The scope of the investigation and

the findings as discussed in this report were discussed.

t

i

i

!

t

.

_

-

_.

- . . .