Confirms Ja Pagliaro & Je Knorr Telcon Fixing 820604 as Due Date for Installation of Upgraded Meteorological Monitoring Sys.Mfg & Calibr Problems W/Telemetry Equipment Have Caused Delay
ML20053C626
Person / Time
Site: Point Beach  NextEra Energy icon.png
Issue date: 05/17/1982
From: Fay C
WISCONSIN ELECTRIC POWER CO.
To: James Keppler
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III)
References
NUDOCS 8206020400
Download: ML20053C626 (1)


Text

5?ik (" '

v

\\

)

a/n 'l 5'T t ?-

Wisconsin Electnc men cwar XM&

231 W. MICHIGAN, P.O. BOX 2046, MILWAUKEE, WI 53201 E.L _

May 17, 1982 fl Y O_ q. US &,,

Mr. J. G. Keppler, Regional Administrator Office of Inspection and Enforcement, Region III U. S. NUCLEAR REGULATORY COMMISSION 799 Roosevelt Road Glen Ellyn, Illinois 60137

Dear Mr. Keppler:

DOCKET NOS. 50-266 AND 50-301 EMERGENCY PREPAREDNESS POINT BEACH NUCLEAR PLANT, UNITS 1 AND 2 This letter is to confirm a telephone conversation between Mr. J.

A.

Pagliaro of your staff and Mr.

J.

E.

Knorr of our staff concerning the extension of the due date for the installation of an upgraded meteorological monitoring system.

The new due date will be June 4, 1982.

This short delay is due to manufacturing and calibration difficulties with the telemetry equipment to be installed with the monitoring equipment.

If you have any questions regarding this letter, please contact us at any time.

Very truly yours, hbd Assistant Vice President C. W.

Fay Copy to NRC Resident Inspector W

g f /y g g B206020400 920517 p

PDR ADOCK 05000 g