Text
.
x m
o 4
e REceivgo W4 M, /9%
gC May1g 7 12 nn y
/
Docket Nos.i-50-443/444 -
4 to MEMORANDUM FOR:
F. J. Miraglia, Chief. Licensing Branch No. 3 DL FROM:
L. L. Wheeler, Project Manager, Licensing Branch No. 3. DL
SUBJECT:
SEABROOK EMERGENCY PREPAREDiESS MEETING DATE & TIME:
May 20, 1982 1:00 p.m. - 4:30 p.m.
May 21, 1982 8:30 a.m. - 3:00 p.m.
LOCATION:
Seabrook Station Seabrook, New Hampshire PURPOSE:
1.
Discuss selected significant aspects of the emergency preparedness review.
2.
Discuss ' applicant responses to NRC requests for information.
3.
On-site familiarization for emergency preparedness reviewers AGENDA:
See attached PARTICIPANTS:
NRC T. McKenna, N. Terc, R. Van Niel, L. Wheeler, R. Lessy FEMA E. Thomas, et.al.
PSNH/YAEC_
J. DeVincentis, J. Mcdonald, J. Robinson, et.al.
/5/
L uis L. Wheeler, Project Manager 820 5 27 0 Mfa f Licensing Branch No. 3 Division of Licensing
Enclosure:
Agenda cc: See next page.
Il0TE: NRC meetings are open to interested members of the public to attend observers. !! embers of the public who wish to attend this meeting must contact L. Wheeler (301/492-7792) no later than 3:45 pm, May 18, 1932 lih:li.a
. 0L : L ).3..
hg,!..
~
,FJ[L
.0
"""' > LLWti. l.. r.; j b, an) 5/.// /82 5// '/82 Nuc eosu m oc e..ucu o24o OFFICIAL RECORD COPY
.__ 7 " ',e m e2.
e SEABROOK William C. Tallman Chairman and Chief Executive Officer Public Service Company of New Hampshire P. O. Box 330 Manchester, New Hampshire 03105 John A. Ritscher, Esq.
E. Tupper Kinder, Esq.
Ropes and Gray Assistant Attorney General 225 Franklin Street Office of Attorney General Boston, Massachusetts 02110 208 State House Annex Concord, New Hampshire 03301 Mr. Bruce B. Beckley, Project Manager Public Service Company of New Hampshire The Honorable Arnold Wight P. O. Box 330 New Hampshire House of Representatives Manchester, New Hampshire 03105 Science, Technology and Energy Committee State House G. Sanborn Concord, New Hampshire 03301 U. S. NRC - Region I 631 Park Avenue Resident Inspector King of Prussia, Pennsylvania 19406 Seabrook Nuclear Power Station c/o U. S. Nuclear Regulatory Commission Ms. Elizabeth H. Weinhold P. O. Box 700 3 Godfrey Avenue Seabrook, New Hampshire 03874 Hampton, New Hampshire 03842 Mr. John DeVincentis, Project Manager Robert A. Backus, Esq.
Yankee Atomic Electric Company O'Neill, Backus and Spielman 1671 Worcester Road 116 Lowell Street Farmingham, Massachusetts 01701 Manchester, New Hampshire 03105 Mr. A. M. Ebner, Project Manager Norman Ross, Esq.
United Engineers and Constructors 30 Francis Street 30 South 17th Street Brookline, Massachusetts 02146 Fast Office Box 8223 Philadelphia, Pennsylvania 19101 l
Karin P. Sheldon, Esq.
Sheldon, Harmon & Weiss Mr. W. Wright, Project Manager 1725 I Street, N. W.
Westinghouse Electric Corporation Washington, D. C.
20006 Post Office Box 355 Pittsburg, Pennsylvania 15230 Laurie Burt, Esq.
Office of the Assistant Attorney General Thomas Dignan, Esq.
Environmental Protection Division Ropes and Gray One Ashburton Place 225 Franklin Street Boston, Massachusetts 02108 Boston, Massachusetts 02110 D. Pierre G. Cameron, Jr., Esq.
l General Counsel Public Service Company of New Hampshire P. O. Box 330 Manchester, New Hampshire 03105 l
ENCLOSURE AGENDA EMERGENCY PREPAREDNESS MEETING SEABROOK STATION MAY 20-21, 1982 Date: May 20, 1982 Time:
2:00 PM - 4:00 PM Location: Seabrook Construction Site NRC staff and FEMA representatives tour the site for a general familiarization of the site layout, then observe the status of the following specific facilities:
Technical Support Center Operations Support Center Emergency Operations Facility Laboratories (post-accident sampling facilities)
Nore: The scope of this familiarization tour is limited entirely to onsite facilities, and is, therefore, not open to the general public.
Date: May 21, 1982 Time: 8:30 AM 12:00 Noon and 1:00 - 4:00 PM Location: Seabrook Education Center j
NRC staff meets with Seabrook representatives to discuss the following:
NRC independent evacuation analysis On-site appraisal plans and requirements Exercise dates Scheduling of state and local planning actions I
FEMA intentions for warning systems tests Response centers (construction schedules, evaluation criteria, appraisals).
f 2
o I After the above items have been discussed, staff and applicant representatives review applicant responses to staff requests for additional infonnation that have resulted from review of the operating license application.
4 When the above reviews have been completed, participants may initiate discussions of any additional emergency preparedness related matters, within the time frame established for this meeting.
4 i,
1
.P e
1
MEETING NOTICE DISTRIBUTION _
Document Control (50-443/444 NRC PDR LPDR TERA NSIC LB#3 Files JLee Project Manager _ L. Wheeler ECase DEisenhut/RPurple EHHpX(only if participant or if held in Bethesda)
JYoungblood ASchwencer FMiraglia EAdensam JMiller Glainas WRussell DCrutchfield TIppolito JKnight WJohnston DMuller TSpeis RHouston LRubenstein FSchroeder MErnst JKramer 0 LD k' S OISE I
Regional Administrator, Region _
Resident Inspector ACRS (16) 050 (7)
NRC Participants T. McKenna N. Terc R. Van Niel L. Wheeler cc: Service List
.