Text
,,.
D5 5'li A
UNITED STATES OF AMERICA NUCLEAR REGULATORY COMMISSION 2 py '0 M.*g 2
/
before the g_e ATOMIC SAFETY AND LICENSING BOARD
)
In the Matter of
)
)
MAINE YANKEE ATOMIC POWER COMPANY
)
Docket No. 50-309-OLA
)
(Maine Yankee Atomic Power Company) )
)
APPLICANT'S MOTION FOR PROPOSED SCHEDULE FOR FURTHER PROCEEDINGS 1.
At the prehearing conference held in the above-entitled matter on August 11, 1981 (Tr. 165-66) counsel for the applicant agreed to attempt, after issuance of the pre-hearing conference order, to obtain the agreement of all parties with respect to, and to propose, a schedule for further proceedings herein.
2.
On April 12, 1982 a comprehensive memorandum and order was issued by the Board.
3 Since that time, applicant's counsel has attempted t
l without success to obtain agreement of all parties as to scheduling.
Agreement has been possible only with the Staff and Maine.
4.
The schedule upon which the Staff, Maine, and appli-cant have agreed is set forth in Attachment A hereto.
Assum-3 ing issuance of the EIA and SER by May 31, 1982, this schedule D23 l
JD 8205240091 820517 I
PDR ADOCK 05000309 C
would call for the matter to be ready for evidentiary hear-ings in February of 1983.
5 SMP has advised counsel for the applicant that it would want discovery not to commence until all contentions (including any late-filed contentions) are ruled upon by the Board.
SMP also wants the discovery period to run for 180 days thereafter.
This would result in a hearing being held ir. June of 1983 assuming the rest of the schedule was adhered to.
WHEREFORE the Applicant moves the Board to adopt the schedule set forth as Attachment A hereto.
By its attorneys, s/ Thomas G.
Dignan, Jr.
s/ R. K. Gad III s/ Ropes & Gray Thomas G. Dignan, Jr.
R. K.
Gad III Ropes & Gray 225 Franklin Street Boston, MA 02110 (617) 423-6100 May 17, 1982 ATTACHMENT A Day "X" is the day on which the last of the EIA or SER' issues:
X Discovery Begins X+
30 Contentions due on EIA and SER issues X+
45 Reply to late filed contentions by Applicant and Staff X.+
60 Intervenor's currebuttal due X+
80 ASLB decision on late filed contentions X + 110 Last day for discovery requests on contentions admitted by April 12, 1982 order X + 140 Last discovery request on contentions, if any, admitted in X + 80 Board Order X + 170 Motions for Summary Disposition to be filed X + 190 Answer to motions for summary disposition X + 215 ASLB decision on motions for summary disposition X + 245 Prehearing Conference or Hearing as appropriate E
I l
i l
l
i CERTIFICATE OF SERVICE
+
.p ;, lg Jo F' d j,
i
.I, Thomas G. Dignan, Jr., hereby certify that on May 17, 1982, I made service of the within document, by mailing a copy thereof, postage prepaid, to:
Robert M. Lazo, Esquire Atomic Safety and Licensing Board Panel U.S. Nuclear Regulatory Commission Washington, D.C.
20555 i
Dr. Cadet H. Hand, Jr.
Director, Bodega Marine Laboratory University of California P.O. Bcx 247 Bodega Bay, California 94923 Administrative Judge Peter A. Morris Atomic Safety and Licensing Board Panel U.S. Nuclear Regulatory Commission Washington, D.C.
20555 Jay M. Gutierrez, Esquire Office of the Executive Legal Director U.S. Nuclear Regulatory Commission Washington, D.C.
20555 David Santee Miller, Esquire 213 Morgan Street, N.W.
Washington, D.C.
20001 Rufus E. Brown, Esquire Deputy Attorney General Department of the Attorney General State House - Station # 6 Augusta, Maine 04333 l
s/ Thomas G.
Dirnan Thomas G. Dignan, Jr.