ML20052G225
| ML20052G225 | |
| Person / Time | |
|---|---|
| Site: | Fermi |
| Issue date: | 04/30/1982 |
| From: | Wells D DETROIT EDISON CO. |
| To: | James Keppler NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III) |
| References | |
| 10CFR-050.55E, 10CFR-50.55E, EF2-57469, NUDOCS 8205140420 | |
| Download: ML20052G225 (1) | |
Text
' Donald A. Wells wrages cuanty Assurance Q
G13) 237 Mi g
2 RECElVED iSOn (0M Second Avenue MAY 131982> i
~ '" "*"*"'
2
' > 2 **
MEN $$7 @
~
April 30,1982 mc EF2-57469 4
w Mr. Janes G. Keppler, Regional Administrator Region III U.S. Nuclear Regulatory Ca mission 799 Roosevelt Road Glen Ellyn, Illinois 60137
Subject:
Interim Report of 10CFR50.55(e) Item on Tubing Within Instrunent Rack Routed Incorrectly (#65)
Dear Mr. Keppler:
On April 1,1982, Project Quality Assurance's Mr. E.L. Thompson, Acting Supervisor-Construction Quality Assurance, telephoned Mr. J. Konklin of NRC Region III, to report on a problem with tubing within an instrument rack which was routed incorrectly at the Fermi 2 site.
This item deals with tubing within an instrument rack which was incorrectly routed. Evidently, the vendor had fabricated the tubing frcm two valves different fram the required design drawing. Investigation is being con-ducted to determine the cause of the discrepancy and the magnitude of the problem. Reportability will be determined by the results of the investiga-tion.
Another report on this item, either interim or final, is scheduled to be sent to you on or before August 27, 1982. If you have questions concerning this matter, please contact Mr. H.A. Walker, Supervisor-Construction Quality Assurance.
Very truly yours, DAN / HAW /cp cc: Mr. Richard DeYoung, Director Offim of Inspection and Enforcement Division of Feactor Inspection Programs U.S. Nuclear Regulatory Cm mission Washington, D.C. 20555 Mr. Bruce Little, Resident Inspector U.S. Nuclear Regulatory Conmission 6450 North Dixie Highway Newport, Michigan 48166 8205140420 820430 yDRADOCK 05000343 PDR
.