Text
.
Ob
'O DISTRIBUTION:
v Docket File
~
APR 2 91982 NRC PDR L DPR NSIC ORB #3 Rdg Docket f;o. 50-368 DEisenhut h.
JHeltemes fp t,
A
[2
,.csF 9 OELD I&E
'(
- 7 J.4 Mr. William Cavanaugh, III ACRS-10
[g.
' M p}
o Senior Vice President, Energy RAClark Supply Department PMKreutzer-3 GN ' "" ' M c~
Arkansas Power & Light Company REMartin vex
,7; P. O. Cox 551 Gray File h ?7y\\
Little Rock, isrkansas 72203 V v
Dear Mr. Cavanaugh:
We have reviewed your letter dated August 7, 1981 concerning the seismic qualification of the emergency feedwater system for Arkansas t:uclear One, Unit No. 2 and have determined that we need additional information to complete the review. The enclosed request for additional information identifies the information required. He request the information within 30 days from receipt of this letter.
The reporting and/or recordkeeping requirements of this letter affect fewer than ten respondents; therefore, OMB clearance is not required under P. L.96-511.
Sircerely, Cri;h.1 v.:
1<j Roheit A. C Robert A. C. lark, Chief Operating Reactors 3 ranch #3 Division of Licensing
Enclosure:
Request for Additional Inforaatien cc w/ enclosure:
See next page G205140019 020429 PDR ADOCK 05000368 P
pon Q,.
,. v'
.03B#3 : DL,,
OR B # 3,: DL,,,,,,,f; omcs >
.Fua((i}/.pn.
R A,Q 1,,ar,k,,[tf, su ~m >
. 41k)BR...
.91$1.V.......H '...
....... ~.
- - ~. ~. - - -
~ ~ ~ ~ ~ ~ -
- ~ ~ ~ ~ ~ * ~
onep OFFICIAL RECORD COPY us = - - m a NRC FORM 313 (10-80) NHCM 0240
C3 Arkansas Pow 2r & Light Company CC:
Mr. John Marshall
~ Manager, Licensing Arkansas Power & Light Company P. O. Box 551 Little Rock, Arkansas 72203 U.S. Environmental Protection Agency Mr. James P. O'Hanlon Region VI Office General Manager ATTN:
Regional Radiation Arkansas Nuclear One Representative P. O. Box 608 1201 Elm Street Russellville, Arkansas 72801 Dallas, Texas 75270 Mr. Robert B. Borsum Babcock & Wilcox Nuclear Power Generation Division Suite 220 7910 Woodmont Avenue S. L. Smith, Operations Officer Bethesda, Maryland 20814 Arkansas Nuclear Planning &
Response Program Nicholas S. Reynolds, Esq.
P. O. Box 1749 c/o DeBevoise & Liberman Russellville, Arkar<as 72801 1200 Seventeenth Street, N.W.
Washington, D. C.
20036 Arkansas Polytechnic College Russellville, Arkansas 72801 Mr. Charles B. Brinkman Manager - Washington Nuclear Operations C-E Power Systems 4853 Cordell Avenue, Suite A-1 Bethesda, Maryland 20014 Regional Administrator Nuclear Regulatory Commission, Region IV Office of Executive Director for Operations 611 Ryan Plaza Drive, Suite 1000 l
Arlington, Texas 76011 Mr. W. Johnson U.S. NRC P. O. Box 2090 l
Russellville, Arkansas 72801 i
i l
8 er O
~
e Arkansas Nuclear One ') nit 2 SEISMIC QUALIFICATICN OF THE AUXILIARY FEEDWATER SYSTEM RECUEST FCR ACCIT10NAL ItFORMATION Question 1:
Encicsure 1 of Generic Lette. 81-14 (GL 81-14) defines the auxiliary fee: water (AFW) system to be considered as:
(a) "The AFW system boundary from suction to cischarge (including the water source and heat sink) shall incluce those portions of the system required to accomplish the AFW system function and connecteo branch piping up to and incluaing the secenc valve which is normally closed or capable of automatic cicsure when the safety function is required."
(b) "The AFh system boundary shall also incluce any portion of branch piping that is structurally coupled to the AFW system boundary such that the seismic response of the branch piping transmits' loads to the AFW system. As a minimum, this incluoes the branch lines outside the AFW system boundary to a point of three orthogonal restraints."
(c) "All mechanical and electrical equipment, piping (e.g.,
instrument air), conduits and cable trays, which are necessary or contain items which are necessary for the operation of the AFW system, shall also be considered."
.(d) "In addition, the structures housing these systems and components shall be included."
Y 9
m
.F
?
'r
v 3
)
.u
.e
=
Clarify the extent to.nich your AFW system bouncary, censicered in your August 7, 1951 response letter, coincices with.the bouncary cefinec in GL 81-14 Guestion 2:
Generic letter 81-14, Enclosure 1, Part A states:
"Sp?cify whether your dW syste: is (a) cesigned, constructed, ano maintainec (and incluced within the scope of seismic related Bulletins 79-02, 79-04, 79-07d-14 and 80-11, anc IE 3
Informatien Notice SG-21), in accorcarcc w$th Seismic Category I requirements (e.g., confornance to Reguletcry Guides 1.29 and the applicable portions of the Standard Recies Plan or comparable criteria) or (b) designed, consuu.ted and maintained (and included within the sr.one of seishrele.tec Bulletins 79-02, 79-04, 79-07, 79-14, anc 80-11, Enc I[ Information Notice 8G-21) to withstand a Safe Shutoown Earthquake (SSE) utilizing the analytical, testing, evaluation methods and receptable criteria consistent with other safety.g ndo systems in your plant."
Clarify t.ne extent to which your AFW syste:" is incluced within the scope of seismic related Bulletins 79-02, 79-04, 79-07, l
79-14, and 80-11, and IE Information Notice 80-21.