Addendum to Annual Operating Rept for 1981
ML20052E739
Person / Time
Site: Crane 
Issue date: 05/03/1982
From:
GENERAL PUBLIC UTILITIES CORP.
To:
Shared Package
ML20052E737 List:
References
NUDOCS 8205110396
Download: ML20052E739 (1)


Text

. -,

)

m 7

l a

i Change 'ECM 862 Rev 0, 1 and 3 - 1981 Change l

Description These changes disconnected and removed nuclear sample lines and associated components between Unit I and II.

The removal was done under NRC order.

Electrical changes were made to ensure that valves remain in closed positions.

i 4

Safety Evaluation Summary i

The removal of sample' lines between Units I-and II does not affect nuclear safety in that all open lines are valved shut and capped and all valves are-red tagged shut. This eliminates the possibility of any releases from the disconnected lines. -Nuclear sampling is unaffected in Unit I and alternate 1

sampling paths are available in Unit II.

The removal of lines does'not create a situation outside the bounds of any previous analysis. Therefore, 2-the change does not create.an unreviewed safety question.

1 Change ECM 5884 Rev 0 - 1981 Change 4 -

[

Description This change installed tie down racks for-the nitrogen bottles for the SPC system.

j Safety Evaluation Summary l

This change was previously reviewed and approved by the on-site NRC staff.-

j Securing the nitrogen tanks reduces the potential for damage or injury that l

was created previously when the tanks were installed.