e Mr. J. M. Felton, Esq.

Director & Staff Attorney U.S. Nuclear Regulatory Commission Washington, D.C 20555 March 29, 1982 Dr. Douglas E. Lee, Ph.D. FREEDOM OF INFORMATION 75-A-1894 ACT REQUEST Drawer B f0[l-Sj. l }l Stormville, New York 12582

~

RE: FDIA # 82-94,82-101, & 82-119.

Dear Mr. Felton:

I would like at this time to expand the above mentioned FOTA's to include the following informations (a) Identify each of the following named persons with full name, (first name & last name), as well as their official titles and mailing addresses:

(1) R. Starostecki of Region I (2) Identify any person (s) with whom your agency has been in contact with either orally or in writing, in which you have collected or obtained any type of information, pertaining to the Robert E. Ginna Nuclear Power Plant incident which occurred on January 25, 1982 in Ontario, New York.

(b) Has your agency investigated or in the process of investigating whether or not any of the person (s) employed at or working at the Robert E. Ginna Nuclear Power Plant, had any type of (i) Alcohol, (ii) Drugs in their body at the tin.e of this incident, at the Ginna Nuclear Power Plant Lused](any typeor had any e of (iii) Drug or(iv) Alcohol within a time period of 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br />, 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br />, 48 hours5.555556e-4 days <br />0.0133 hours <br />7.936508e-5 weeks <br />1.8264e-5 months <br />, or 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br /> of going to work at the Ginna plant?

(c) If the above (b) is answered [Yes], then I ask that you identify that person (s) with complete name only.

(d) Did your agency conduct any type of medical investigation with reference to (b) abov .~s e - .Very tro yeurs, 82 04 2 8 DO 8~t , cA t

DEL /mk br ouglas'E. Lee, Ph.D.

j cc: file copy k #

*/

ATTACHMENT Rochester Gas & Electr ic Corporation 89 East Avenue Rochester, NY 14649 John Maier, Vice President Electric and Steam Production Robert Smith, Assistant Chief Engineer Design and Construction

Robert Mecredy, Manager Nuclear Engineering.

Jim Hutton, Manager Mechanical Engineering Al Curtis, Manager Materials Engineering  !

Paul Wilkens Senior Nuclear Engineer Rick Watt Corporate Health Phsicist  !

1 R. E. Ginna Nuclear Power Plant 1503 Lake Road .

Ontario, NY 14519 Bruce Snow Plant Superintendent Jack Noon Assistant Plant Superintendent

. Joe Larizza Technical Engineer i

h 1

i e - . .. . w .ar.--