4.,

MAR 2 91982 Docket Nos.:

50-445 and 50-446 MEMORANDUM FOR:

B. J. Youngblood, Chief. Licensing Branch No. 1, DL FROM:

S. B. Burwell, Project Manager, Licensing Branch No.1 DL

SUBJECT:

NOTICE OF MEETING AND SITE VISIT BY CASELOAD FORECAST PANEL TO ASSESS CONSTRUCTION COMPLETION SCHEDULES - COMANCHE PEAV, STEAM ELECTRIC STATI0fi, UNITS 1 AND 2 DATE AND TIME:

April 13 and 14, 1982: 9:00 AM - 4:00 PM April 15,1982; 9:00 AM - 2:00 PM LOCATION:

April 13,1982; fluclear Regulatory Consnission, Region IV, Arlington, Texas j

  • April 14 and 15,1982; Comanche Peak Steam Electric Station, Glen Rose, Texas PURPOSE:

The Caseload Forecast Panel will review construction progress to collect data for accessing projected fuel load dates.

AGENDA:

April 13, 1982; Meeting:

Review design and engineering, procurement and construction progress. Review progress on preoperation procedures and testing. See enclosed agenda.

  • April 14 and 15, 1982; Site Visit: The Panel will tour the site and observe construction activit-ies for Units 1 and 2.

PARTICIPANTS:

Texas Utilities Generating Company J. Merritt, J. Marshall, et. al.

NRC Staff l

S. Burwell, W. Lovelace, J. Youngblood, M. Rothschild and G. flizuno

  • NOTE: The meeting on April 13. 1982 is open to interested members of the public to attend as observers pursuant to the NRC Policy Statement on open meetings, i

For the site visit on April 14 and 15,1982, permission to enter the con-struction site must be obtained from the Texas Utilities Generating Company.

5204 369..4..3/..i omen,

sua=we >

om)

Nnc ronu sie omee) Nacu om OFFIClAL RECORD COPY uscm mi-mm

g4;,-

l b

NAR 2 01982 B. J. Youngblood t t

1 h

I Original signed byz spettsveedsurwell S. B. Burwell, Project Manager Licensing Branch No. 1 Division of Licensing

Enclosure:

As stated cc w/ encl.: See next page 4

f r

DL;LM1 DL:LI

..'.1/

OF FtCE ).S.g..yg.g.B..B u..r..w..e l..l... 1.9

.B.J..Youn.R

..l.o.g.... o...d suanue>

3/. 2 6/. 82.........3.....'8............

om>

unc ronu sie po.aoi nneu ano OFFICIAL RECORD COPY usam mi.-aw m

q

.n

[

Mr. R. J. Gary Executive Vice President'and 4

General Manager Texas Utilities Generating Company 2001 Bryan Tower Dallas, Texas 75201 cc: Nicholas S. Reynolds, Esq.

J. Marshall Gilmore 1060 West Pipeline Road Debevoise & Liberman Hurst, Texas 76053 1200 Seventeenth Street, N. W.

Washington, D. C.

20036 Mr. Robert G. Taylor Spencer C. Relyea, Esq.

Resident Inspector / Comanche Peak Worsham, Forsythe & Sampels Nuclear Power Station 2001 Bryan Tower c/o U. S. Nuclear Regulatory i

Dallas, Texas 75201 Commission 1

P. O. Box 38 Mr. Homer C. Schmidt Glen Rose, Texas 76043 Manager - Nuclear Services Texas Utilities Services, Inc.

Richard Fouke 2001 Bryan Tower Citizens for Fair Utility Regulation Dallas, Texas 75201 1668-B Carter Drive-Arlington, Texas 76010 e

Mr. H. R. Rock l

Gibbs and Hill, Inc.

Mr. John T. Collins i

393 Seventh Avenue U. S. NRC, Region IV j

New York, New York 10001 611 Ryan Plaza Drive Suite 1000 Mr. A. T. Parker Arlington, Texas 76011 Westinghouse Electric Corporation P. O. Box 355 l

Pittsburgh, Pennsylvania 15230 O

David J. Preister j

Assistant Attorney General Environmental Protection Division P. O. Box 12548, Capitol Station i

Austin, Texas 78711 Mrs. Juanita Ellis, President i

Citizens Association for Sound

),.

Energy 1426 South Polk Dallas, Texas _ 75224 n-+

.n-,-

wa.,,,

.t; COMANCHE PEAK STEAM ELECTRIC STATION REVIEW OF UNIT 1 AND NEEDED COMMON FACILITIES, AND UNIT 2 CASELOAD FORECAST PANEL SITE VISIT MEETING AGENDA 1.

Overview of project construction schedule including progress and major milestones ccmpleted, current problems and any anticipated problem areas that may impact the current projected fuel load dates for Units 1 and 2.

2.

Detailed review and current status of design and engineering effort (by major discipline) including any potential problems that may arise from necessary rework for Units 1 and 2.

3.

Detailed review and current status of procurement activities including valves, pipe, instruments, cable, major components, etc. for Units 1 and 2.

4.

Actual and proposed craft work force (by major craft), craft availability, productivity, potential labor negotiations and problems for Units 1 and 2.

5.

Detailed review and current status of all large and small bore pipe hangers, restraints, snubbers, etc., including design, rework, procurement, fabrica-tion, delivery and installation for Units 1 and 2.

6.

Detailed review of project schedule identifying critical path items, near critical items, amount of float for various activities, the current critical path to fuel loading, methods of implementation of corrective action for any activities with negative float, and provisions for contingencies. The estimated project percent complete as of March 31, 1982 for Units 1 and 2.

7.

Detailed review and current status of bulk quantities including current estimated quantities, quantities installed to date, quantities scheduled to date, current percent complete for each, actual versus forecast install-ation rates, and basis for figures for Units 1 and 2.

(a) Concrete (CY)

(b) Procesr. Pipe (LF)

Large Bore Pipe (2h" and larger)

Small Bore Pipe (2" and smaller)

(c) Yard. Pipe (LF)

(d) Large Bore Pipe' Hangers, Restraints, Snubbers (ea)

(e) Small Bore Pipe Hangers, Restraints (ea)

(f) Cable Tray (LF)

(g) Total Conduit (LF)

(h) Total Exposed Metal Conduit (LF)

(i) Cable (LF)

Power

- Control

- Security

.,c, Instrumentation Plant Lighting (j) Terminations (ea)

Power Control Security Instrumentation Plant Lighting (k) Electrical Circuits (ea)

Power Control Security (1)

Instrumentation (ea) 8.

Detailed review and current status of preparation of preop and acceptance test procedures, integration of preop and acceptance test activities with construction schedule, syttem turnover schedule, preop and acceptance tests, schedule, current and proposed preop and acceptance tests program manpower for Units 1 and 2.

(a) Total number of procedures required for fuel load.

(b) Number of draft procedures not started.

(c) Number of draft procedures being written.

(d) Number of procedures approved.

(e) Number of procedures in review.

( f) Total number of preop and acceptance tests required for fuel load.

(g) Nutter of preop and. acceptance tests completed.

(h) Number of preop and acceptance tests currently in p1 ogress.

(i) Number of systems turned over to start-up.

{

9.

Detailed discussion of potential schedular influence due to changes attributed to NUREG-0737 and other recent licensing requirements for Units 1 and 2.

j 10.

Discussion of schedular impact, if any, regarding potential deficiencies reported in accordance with 10 CFR 50.55(e) for Units 1 and 2.

11.

Overview of current construction management and startup group organization i

and activities intergrating Units 1 and 2.

,n

_ -. =

',. st o NAR 2 91982

~

MEETING NOTICE DISTRIBUTION QDii.kiQileQ J. Stolz "NRC PDR- "

S. Hanauer Local PDR H. Thompson m

g TIC /NSIC e

ACRS (16)

D. Ziemann 39 4

TERA W. Minners S'

l.B#1 Rdg.

F. Schroeder 2

f7 E. Case K. Kniel

~

C p'L i

1 D. Eisenhut/M. Jambor D. Skovholt S

g'od o G. Knightori fp T. Novak M. Ernst h

9 S. Varga L. Hulman D. Vassallo E. Adensam 6'D R. A. Clark A.'Thadani Attorney, OELD J. Youngblood 0IE A. Schwencer OSD (7)

F. Miraglia Project fianager S. B. Burwell J. R. Miller.

Licensing Assistant M. Rushbrook G. Lainas Receptionist D. Crutchfield i

W. Russell J. LeDoux, I&E J. 01shinki R. Vollmer I&E Headquarters R. Bosnak I&E Region I 1

F. Schauer I&E Region II R. E. Jackson ISE Region III G. Lear I&E Region IV W. Johnston I&E Region V S. Pawlicki V. Benaroya NRC

Participants:

Z. Rosztoczy S. Burwell W. Haass W. Lovelace O. Muller J. Youngblood R. Ballard M. Rothschild W. Regan G. Mizuno V. Moore R. Mattson i-l F. Congel-

0. Parr bec: Applicant & Service List F. Rosa W. Butler R. W. Hous ton W. Gammill L. Rubenstein T. Speis M. Srinivasan B. Grimes S. Schwartz F. Pagano p

S. Ramos 9

.