- fb f (412)456 4000 Pittstwegh, Pa February 4, 1982
"'2 "
N C3
/
United States Nuclear Regulatory Commission Division of Reactor Programs ggpj$O h
Attention: James Taylor, Director
]
r'
. &}
3 %F 7()
Washington, D. C.
20555 SM1 ul [ [hf) bg o d
2
Reference:
Beaver Valley Power Station, Unit No. 1 Docket No. 50-334, License No. DPR-66 b
%4
['
Response To Performance Appraisal Branch Inspection (
Gentlemen:
A response to Perfortrance Appraisal Branch Inspection 81-29 is required to be submitted by Duquesne Light Company on February 5, 1982.
This letter documents our verbal communication with Mr. Wayne Shafer of the Region 2 office whereby we requested an extension in the response date until March 1, 1982.
We requested this additional time in order to prepare our response because of the following factors:
1)
The comprehensive nature of Inspection 81-29, the complexity of the issues involved and our perception of those elements which would comprise effective corrective action will require additional time to provide a responsive reply.
2)
Beaver Valley Unit 1 is presently engaged in a major modification shutdown which has required a substantial amount of attention from key management personnel.
3)
Duquesne Light Company is scheduled to undergo a full scale drill of our Emergency Preparedness Plan for the Federal Emergency Management Agency on February 17, 1982.
Preparation for this drill has likewise placed an additional work load on key management personnel.
s kf
[ spas 8cPoS88S3g;
v.
e Beaver Valley Power Station, Unit No. 1 Docket No. 50-334, License No. DPR-66 Response To PAB Inspection 81-29 February 4, 1982 Page 2 It is our desire to make maximum use of the information that the Performance Appraisal Branch inspectors have developed at our site. We believe that the extension requested will allow us to take full advantage of the information contained in this inspection report.
Very truly yours, J. J. Carey Vice President, Nuclear cc:
Mr. Wayne Shafer United States Nuclear Regulatory Commission Region 2 799 Roosevelt Read Glen Ellyn, Illinois 60137 Mr. D. A. Beckman, Resident Inspector United States Nuclear Regulatory Commission Beaver Valley Power Station Shippingport, Pennsylvania 15077 United States Nuclear Regulatory Commission c/o Document Management Branch Washington, D. C.