Advises That 820319 Review Re Const of Electrical Conduit Indicates That Part 21 Rept Is Not Required.Special Review Committee Has Been Established to Evaluate Work Being Done
ML20050R440
Person / Time
Site: Point Beach  NextEra Energy icon.png
Issue date: 03/26/1982
From: Fay C
WISCONSIN ELECTRIC POWER CO.
To: James Keppler
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III)
Shared Package
ML20050R248 List:
References
NUDOCS 8204140494
Download: ML20050R440 (2)


Text

PRTNCIPAk ST&FF r/ OIR 4 t y/l%IS 9/D

  1. AO c8 ll 0 cu W)tl "-

rrer wisconsin Electnc eom coupua 1ESTI 231 W. MICHIGAN, P.O. BOX 2046. MILWAUKEE. WI 53201 gpg pm Q y

March 26, 1982 Mr. J. G. Keppler, Regional Administrator Office of Inspection and Enforcement, Region III U.

S. NUCLEAR REGULATORY COMMISSION 799 Roosevelt Road Glen Ellyn, Illinois 60137

Dear Mr. Keppler:

DOCKET NOS. 50-266 AND 50-301 TMI MODIFICATIONS POINT BEACH NUCLEAR PLANT, UNITS 1 AND 2 On March 19, 1982, a review of the construction of electrical conduit being installed as part of modifications required by the NRC in response to the Three Mile Island accident indicated that some of the installation features might not be in strict accordance with approved drawings and speci-fications.

The Nuclear Engineering Section Safety Review Committee met in accordance with our procedures to review the available information and evaluate whether or not reporting in accordance with 10 CPR Part 21 was appropriate.

The Committee review -

indicates that the circumstances have not created a substantial safety hazard at this time and that a Part 21 report is not required.

We will, however, provide a 30-day report in accordance with Technical Specification requirements.

The Resident Inspector at Point Beach is aware of this matter.

While initial information indicates that the installation deficiencies are of a generally minor nature, we view a possible inadequacy in our Quality Assurance Program as a very serious matter.

In addition to the evaluation and corrective action that is being taken by the Nuclear Power Department and contractors, the Executive Vice President has appointed a special review committee composed of managers who are members of our corporate Quality Assurance Committee but who have no direct responsibility regarding the work being evaluated.

This committee will perform an independent 8204140494 820408 PDR ADOCK 05000266 PDR MAR 3 0 ;ggp G

4

~

Mr. J. G. Keppler March 26, 1982 evaluation of the events which took place and provide a report and recommendations to the Executive Vice President.

As noted above, further details regarding this matter will be provided to you by means of a 30-day report.

Very truly yours, 7

su af r

Assistant Vice President C. W. Fay Copy to NRC Resident Inspector p

1 l

l l